DRRRP Awarded Emergency

RDA/DRP/SAB/RAT/RAT/24

Rehabilitation / Improvement and Asphalt Overlaying on Kalawana - Deepdeen Rakwana (4+255-9+809)

RatnapuraSabaragamuwa ProvinceRatnapuraDivisional SecretariatSSP Engineers (Pvt) LtdContractorLKR 236,752,750.59Contract Sum91 daysProject Duration
85%
Complete
Physical Progress85%
Planned Progress100%
Time Elapsed100%
133 days behind schedule

Project Timeline

LOA
2026-03-19
Completed
Possession
–
Pending
Commencement
2026-04-07
Completed
Scheduled Completion
2026-06-24
Completed
Anticipated Completion Date
2026-07-07
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictRatnapura
PD RegionSabaragamuwa Province
CE RegionRatnapura
EE DivisionRatnapura
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement and Asphalt Overlaying on Kalawana - Deepdeen Rakwana (4+255-9+809)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryWidening and Asphalt overlaying, Retaing walls, culvert and Drains at necessary locations
Contractor & Award
Contract No.RDA/DRP/SAB/RAT/RAT/24
Tender Batch No.3
Contractor NameSSP Engineers (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-03-19
Contract Amount236,752,750.59
Engineer Estimate Amount (LKR)264,741,911.81
Duration (Days)91