DRRRP Awarded Emergency

RDA/DRP/CEN/KDY/KAN/14

Rehabilitation /Improvement of Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370)

KandyCentral ProvinceKandyDivisional SecretariatAlucon Industries (Pvt) LtdContractorLKR 74,836,014.77Contract Sum182 daysProject Duration
9%
Complete
Physical Progress9%
Planned Progress24.9%
Time Elapsed35.2%
On Track • 117 days left

Project Timeline

LOA
2026-08-14
Completed
Possession
2026-09-01
Completed
Commencement
2026-09-01
Completed
Scheduled Completion
2027-03-01
On Track
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceCentral Province
DistrictKandy
PD RegionCentral Province
CE RegionKandy
EE DivisionKandy
Package No.2
Tender By-
Scope
Contract NameRehabilitation /Improvement of Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryConstruction of Retaining structures, Construction of culverts,
Contractor & Award
Contract No.RDA/DRP/CEN/KDY/KAN/14
Tender Batch No.-
Contractor NameAlucon Industries (Pvt) Ltd
ConsultantTeam Leader
Tender StatusAwarded
LOA Date2026-08-14
Contract Amount74,836,014.77
Engineer Estimate Amount (LKR)72,827,654.90
Duration (Days)182
CategoryEmergency