DRRRP Awarded Emergency

RDA/DRP/UVA/BAD/BAD/13

Rehabilitation / Improvement of Ella Passara Road (B113) (9+500 - 27+000)

BadullaUva ProvinceBadullaDivisional SecretariatSF Construction (Pvt) LtdContractorLKR 290,901,643.58Contract Sum182 daysProject Duration
66.5%
Complete
Physical Progress66.5%
Planned Progress97.3%
Time Elapsed89.6%
On Track • 18 days left

Project Timeline

LOA
2026-05-11
Completed
Possession
–
Pending
Commencement
2026-05-25
Completed
Scheduled Completion
2026-11-22
On Track
Anticipated Completion Date
2026-11-22
On Track

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceUva Province
DistrictBadulla
PD RegionUva Province
CE RegionBadulla
EE DivisionBadulla
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Ella Passara Road (B113) (9+500 - 27+000)
Estimated Road Lengths- km
Number of Roads-
Scope Summary-
Contractor & Award
Contract No.RDA/DRP/UVA/BAD/BAD/13
Tender Batch No.8
Contractor NameSF Construction (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-05-11
Contract Amount290,901,643.58
Engineer Estimate Amount (LKR)292,073,080.75
Duration (Days)182
CategoryEmergency