DRRRP Awarded Emergency

RDA/DRP/SAB/KEG/RUW/30

Rehabilitation of Dehiovita - Daraniyagala - Nooriya Road (from 23+850 to 27+960) due to catastrophic disaster cyclone Ditwa

KegalleSabaragamuwa ProvinceKegalleDivisional SecretariatAccon Engineering (Pvt) LtdContractorLKR 169,223,910.80Contract Sum91 daysProject Duration
68%
Complete
Physical Progress68%
Planned Progress100%
Time Elapsed100%
75 days behind schedule

Project Timeline

LOA
2026-04-06
Completed
Possession
–
Pending
Commencement
2026-05-22
Completed
Scheduled Completion
2026-08-21
Completed
Anticipated Completion Date
2026-08-21
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictKegalle
PD RegionSabaragamuwa Province
CE RegionKegalle
EE DivisionKegalle
Package No.-
Tender By-
Scope
Contract NameRehabilitation of Dehiovita - Daraniyagala - Nooriya Road (from 23+850 to 27+960) due to catastrophic disaster cyclone Ditwa
Estimated Road Lengths- km
Number of Roads-
Scope Summary-
Contractor & Award
Contract No.RDA/DRP/SAB/KEG/RUW/30
Tender Batch No.5
Contractor NameAccon Engineering (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-04-06
Contract Amount169,223,910.80
Engineer Estimate Amount (LKR)179,826,720.59
Duration (Days)91
CategoryEmergency