Construction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LHS 9+600 - 9+655), (15+450 - 15+500), (10+235 - 10+300) and Wattegama Matale road (0+400 - 0+435)
KandyCentral ProvinceKundasaleDivisional SecretariatS N O Builders (Pvt) LtdContractorLKR 157,909,825.01Contract Sum119 daysProject Duration
Schedule Delay3 daysbehind schedule
3 days behind schedule
Possession
2026-07-06
Completed
Commencement
2026-07-06
Completed
Scheduled Completion
2026-11-01
Completed
Anticipated Completion Date
–
Delayed Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictKandy
PD RegionCentral Province
CE RegionKandy
EE DivisionKundasale
Package No.6
Tender By-
Scope
Contract NameConstruction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LHS 9+600 - 9+655), (15+450 - 15+500), (10+235 - 10+300) and Wattegama Matale road (0+400 - 0+435)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryConstruction of Gabion Retaining Wall
Contractor & Award
Contract No.RDA/DRP/CEN/KDY/KUN/25
Tender Batch No.12
Contractor NameS N O Builders (Pvt) Ltd
ConsultantTeam Leader
Tender StatusAwarded
LOA Date2026-06-16
Contract Amount157,909,825.01
Engineer Estimate Amount (LKR)178,738,774.63
Duration (Days)119
CategoryEmergency
Document Readiness
5 of 12 required documents received.
5 Received7 Pending
Contractual5/7
LOA IssuedYes
Agreement SignedYes
Escrow AgreementYes
Performance BondYes
Contract Doc. Received—
Insurance—
Advance BondYes
Technical0/5
Source Approval Request—
Drawings Submitted—
Contractor Staff Details—
Work Programme—
Traffic Mgmt & Safety Plan—
Contract Period Timeline
Scheduled Completion
2026-11-01
Anticipated Completion Date
—
Duration Elapsed121 / 119 days
Schedule Status3 Days in Delay
Anticipated Completion Date—
Project Completed—
Completed Date—
Mobilization
Planned vs Actual
Physical Progress59% vs 100%
Financial Progress34.4% vs 100%
Progress MonitorCritical Delay
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 21.2% of contract
IPC 1 (Advance)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
Request2026-08-07
LKR 28,669,877.24LKR 33,830,455.14CE Certified2026-08-11
LKR 28,669,877.24LKR 33,830,455.14PD Certified2026-08-12
LKR 28,346,587.80LKR 33,448,973.60DateAmount (excl. VAT)Amount (incl. VAT)
Advance Summary
Advance BondYes
Advance PaidYes
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 34.4% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
IPC 2 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
Request2026-08-12
LKR 8,909,442.43LKR 10,513,142.07CE Certified2026-07-03
LKR 6,023,275.13LKR 7,107,464.65PD Certified2026-09-11
LKR 7,822,693.26LKR 9,230,778.05DateAmount (excl. VAT)Amount (incl. VAT)
IPC 3 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
PD Certified2026-09-29
LKR 18,099,571.28LKR 21,271,703.33DateAmount (excl. VAT)Amount (incl. VAT)
IPC 4 (IPC)PD Certified
DateAmount
(excl. VAT)Amount
(incl. VAT)
Request2026-10-17
LKR 16,439,044.89LKR 19,398,072.97CE Certified2026-10-29
LKR 10,705,591.47LKR 11,041,226.83PD Certified2026-10-30
LKR 10,705,591.47LKR 11,041,226.83DateAmount (excl. VAT)Amount (incl. VAT)
IPC 5Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 6Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 21Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 22Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 23Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 24Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Revised Contract
contract + approved VOs
No variations recorded
This project has no variation orders yet.
EOTs
0 approved · 0 pending
Days Requested
across 0 EOTs
Approved Days
0 approved EOTs
Revised Finish
planned 2026-11-01
No extensions recorded
This project has no extension-of-time requests yet.
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
Yes - projects.advance_bondBank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Time
Elapsed - 3 Days in Delay
Overall Progress
Overall
Planned: 100%Behind by 41%
Financial Actual: 54.27 Mn / Planned 157.91 MnBehind 103.64 Mn
Critical Issues-
Kandy - Kundasale
Construction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LHS 9+600 - 9+655), (15+450 - 15+500), (10+235 - 10+300) and Wattegama Matale road (0+400 - 0+435)
Project Name:
Project #25 - Contract No. RDA/DRP/CEN/KDY/KUN/25
Physical S-Curve - 2026-11-04 - Generated 2026-11-04 12:57
Contract No. RDA/DRP/CEN/KDY/KUN/25
Physical S-Curve - Planned vs Actual
Today: 2026-11-04 - 59%
17 customized weeks — kept on regenerate
Weekly Planned (Physical %)
Presentage
Actual financial
Kandy - Kundasale
Construction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LHS 9+600 - 9+655), (15+450 - 15+500), (10+235 - 10+300) and Wattegama Matale road (0+400 - 0+435)
Project Name:
Project #25 - Contract No. RDA/DRP/CEN/KDY/KUN/25
Financial S-Curve - 2026-11-04 - Generated 2026-11-04 12:57
Contract No. RDA/DRP/CEN/KDY/KUN/25
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-11-04 - LKR 54.27 Mn
Weekly Planned (Financial Mn)
Documents & Attachments
0 file(s) - up to 25 MB each
| Title | Category | Uploaded By | Size | Date | Actions |
|---|
| No documents uploaded. |
Completion Forecast
Current pace+3% / week
Estimated completion2027-02-19
Weeks to 100%13.5
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot2026-10-30
Snapshot value59%
Current progress59%
Change+2%
Project Notes 0
No notes yet. Add the first note to start the conversation.