DRRRP Awarded Emergency

RDA/DRP/UVA/BAD/BAN/16

Rehabilitation / Improvement of Rendapola Ambewela Road (0+000-1+435) (B-507) and Peradeniya Badulla Chenkaladi Road (76+000-90+000) (AA-005)

BadullaUva ProvinceBadullaDivisional SecretariatSubasingha Contractors (Pvt) LtdContractorLKR 297,237,284.97Contract Sum182 daysProject Duration
66%
Complete
Physical Progress66%
Planned Progress100%
Time Elapsed100%
35 days behind schedule

Project Timeline

LOA
2023-03-19
Completed
Possession
–
Pending
Commencement
2026-04-02
Completed
Scheduled Completion
2026-09-30
Completed
Anticipated Completion Date
2026-09-30
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceUva Province
DistrictBadulla
PD RegionUva Province
CE RegionBadulla
EE DivisionBadulla
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Rendapola Ambewela Road (0+000-1+435) (B-507) and Peradeniya Badulla Chenkaladi Road (76+000-90+000) (AA-005)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryRetaining wall construction ,Gabion wall construction
Contractor & Award
Contract No.RDA/DRP/UVA/BAD/BAN/16
Tender Batch No.3
Contractor NameSubasingha Contractors (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2023-03-19
Contract Amount297,237,284.97
Engineer Estimate Amount (LKR)293,827,930.50
Duration (Days)182
CategoryEmergency