RDA/DRP/WP/COL/COL/09
Rehabilitation / Improvement of Koralawella Egodauyana Road (B235) section 2 (3+000 - 6+300)
ColomboWestern ProvinceColomboDivisional SecretariatJayasinghe Construction (Pvt) LtdContractorLKR 155,082,468.40Contract Sum91 daysProject Duration
5%
Complete
Physical Progress5%
Planned Progress100%
Time Elapsed100%
Schedule Delay87 daysbehind schedule
87 days behind schedule
Project Timeline
LOA
2026-04-22
CompletedPossession
–
PendingCommencement
2026-05-10
CompletedScheduled Completion
2026-08-09
CompletedAnticipated Completion Date
–
DelayedSwipe tabs to see all sections — tap to switch
Location & Package
ProvinceWestern Province
DistrictColombo
PD RegionWestern Province
CE RegionColombo
EE DivisionColombo
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Koralawella Egodauyana Road (B235) section 2 (3+000 - 6+300)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryAsphalt Overlaying
Contractor & Award
Contract No.RDA/DRP/WP/COL/COL/09
Tender Batch No.7
Contractor NameJayasinghe Construction (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-04-22
Contract Amount155,082,468.40
Engineer Estimate Amount (LKR)160,664,947.64
Duration (Days)91
CategoryEmergency
IPC 2Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 3Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 4Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 5Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 6Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 21Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount