DRRRP Awarded Emergency

RDA/DRP/WP/COL/COL/09

Rehabilitation / Improvement of Koralawella Egodauyana Road (B235) section 2 (3+000 - 6+300)

ColomboWestern ProvinceColomboDivisional SecretariatJayasinghe Construction (Pvt) LtdContractorLKR 155,082,468.40Contract Sum91 daysProject Duration
5%
Complete
Physical Progress5%
Planned Progress100%
Time Elapsed100%
87 days behind schedule

Project Timeline

LOA
2026-04-22
Completed
Possession
–
Pending
Commencement
2026-05-10
Completed
Scheduled Completion
2026-08-09
Completed
Anticipated Completion Date
–
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceWestern Province
DistrictColombo
PD RegionWestern Province
CE RegionColombo
EE DivisionColombo
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Koralawella Egodauyana Road (B235) section 2 (3+000 - 6+300)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryAsphalt Overlaying
Contractor & Award
Contract No.RDA/DRP/WP/COL/COL/09
Tender Batch No.7
Contractor NameJayasinghe Construction (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-04-22
Contract Amount155,082,468.40
Engineer Estimate Amount (LKR)160,664,947.64
Duration (Days)91
CategoryEmergency