DRRRP Awarded Emergency

RDA/DRP/WP/COL/AVI/03

Rehabilitation / Improvement and Asphalt Overlaying on Colombo - Horana Road (B084) (10+500 - 13+500)

ColomboWestern ProvinceColomboDivisional SecretariatKeangnam Engineering & Construction (Pvt) LtdContractorLKR 176,739,557.41Contract Sum63 daysProject Duration
3%
Complete
Physical Progress3%
Planned Progress100%
Time Elapsed100%
134 days behind schedule

Project Timeline

LOA
2026-04-07
Completed
Possession
–
Pending
Commencement
2026-04-21
Completed
Scheduled Completion
2026-06-23
Completed
Anticipated Completion Date
2026-07-11
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceWestern Province
DistrictColombo
PD RegionWestern Province
CE RegionColombo
EE DivisionColombo
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement and Asphalt Overlaying on Colombo - Horana Road (B084) (10+500 - 13+500)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryAsphalt Overlaying
Contractor & Award
Contract No.RDA/DRP/WP/COL/AVI/03
Tender Batch No.6
Contractor NameKeangnam Engineering & Construction (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-04-07
Contract Amount176,739,557.41
Engineer Estimate Amount (LKR)201,633,881.18
Duration (Days)63
CategoryEmergency