DRRRP Awarded Emergency

RDA/DRP/SAB/RAT/EMB/08

Rehabilitation / Improvement of Pelmadulla - Embilipitiya - Naonagama Road (AA018) (43+700-47+000)

RatnapuraSabaragamuwa ProvinceRatnapuraDivisional SecretariatAnura ConstructionContractorLKR 259,436,963.35Contract Sum91 daysProject Duration
15%
Complete
Physical Progress15%
Planned Progress100%
Time Elapsed100%
87 days behind schedule

Project Timeline

LOA
2026-04-22
Completed
Possession
–
Pending
Commencement
2026-05-10
Completed
Scheduled Completion
2026-08-09
Completed
Anticipated Completion Date
2026-08-09
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictRatnapura
PD RegionSabaragamuwa Province
CE RegionRatnapura
EE DivisionRatnapura
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Pelmadulla - Embilipitiya - Naonagama Road (AA018) (43+700-47+000)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryBinder and Asphalt surfacing
Contractor & Award
Contract No.RDA/DRP/SAB/RAT/EMB/08
Tender Batch No.7
Contractor NameAnura Construction
Consultant-
Tender StatusAwarded
LOA Date2026-04-22
Contract Amount259,436,963.35
Engineer Estimate Amount (LKR)286,890,596.52
Duration (Days)91
CategoryEmergency