DRRRP Awarded Emergency

RDA/DRP/CEN/MTL/MTL/33

Rehabilitation / Improvement of Wattegama Matale Road (5+280 - 13+160) and Ukuwela Railway station (0+000 - 0+190)

MataleCentral ProvinceMataleDivisional SecretariatJayasinghe Construction (Pvt) LtdContractorLKR 165,006,430.79Contract Sum91 daysProject Duration
30%
Complete
Physical Progress30%
Planned Progress100%
Time Elapsed100%
96 days behind schedule

Project Timeline

LOA
2026-03-16
Completed
Possession
–
Pending
Commencement
2026-05-02
Completed
Scheduled Completion
2026-07-31
Completed
Anticipated Completion Date
–
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceCentral Province
DistrictMatale
PD RegionCentral Province
CE RegionMatale
EE DivisionMatale
Package No.3
Tender ByRM&M
Scope
Contract NameRehabilitation / Improvement of Wattegama Matale Road (5+280 - 13+160) and Ukuwela Railway station (0+000 - 0+190)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryShoulder and embankment construction, surface application, construction of drainage structures and construction of retaining walls
Contractor & Award
Contract No.RDA/DRP/CEN/MTL/MTL/33
Tender Batch No.4
Contractor NameJayasinghe Construction (Pvt) Ltd
ConsultantMatale EE
Tender StatusAwarded
LOA Date2026-03-16
Contract Amount165,006,430.79
Engineer Estimate Amount (LKR)188,777,407.11
Duration (Days)91
CategoryEmergency