DRRRP Awarded Emergency

RDA/DRP/WP/GAM/NIT/20

Rehabilitation / Improvement of Bothale Mirigama Road (3+750-4+800), Warakapola Kandalama Road (7+000-8+000), (8+500-9+000) & (9+500-10+900), Negombo Mirigama Road and Construction of Gabion Wall on Colombo - Kandy Road at 54+950,Warakapola Kandalama Road at Culvert No. 10/4 LHS and Widening of Culvert Nos. 4/1 LHS 4/3 Bothsides and Reconstruction of Culvert No. 4/2 on Veyangoda Banduragoda Road

GampahaWestern ProvinceGampahaDivisional SecretariatJeyanthan ConstructionContractorLKR 217,881,464.96Contract Sum91 daysProject Duration
46%
Complete
Physical Progress46%
Planned Progress100%
Time Elapsed100%
62 days behind schedule

Project Timeline

LOA
2026-04-06
Completed
Possession
–
Pending
Commencement
2026-06-04
Completed
Scheduled Completion
2026-09-03
Completed
Anticipated Completion Date
–
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceWestern Province
DistrictGampaha
PD RegionWestern Province
CE RegionGampaha
EE DivisionGampaha
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Bothale Mirigama Road (3+750-4+800), Warakapola Kandalama Road (7+000-8+000), (8+500-9+000) & (9+500-10+900), Negombo Mirigama Road and Construction of Gabion Wall on Colombo - Kandy Road at 54+950,Warakapola Kandalama Road at Culvert No. 10/4 LHS and Widening of Culvert Nos. 4/1 LHS 4/3 Bothsides and Reconstruction of Culvert No. 4/2 on Veyangoda Banduragoda Road
Estimated Road Lengths- km
Number of Roads-
Scope SummaryAsphalt Overlaying, culvert & retaining wall construction
Contractor & Award
Contract No.RDA/DRP/WP/GAM/NIT/20
Tender Batch No.5
Contractor NameJeyanthan Construction
Consultant-
Tender StatusAwarded
LOA Date2026-04-06
Contract Amount217,881,464.96
Engineer Estimate Amount (LKR)245,395,696.16
Duration (Days)91
CategoryEmergency