DRRRP Awarded Emergency

RDA/DRP/UVA/BAD/BAN/31

Rehabilitation / Improvement of Colombo Rathnapura Wellawaya Batticaloa Road (AA004) (212+000 - 213+500)

BadullaUva Province-Divisional SecretariatNimna Holdings (Pvt) LtdContractorLKR 239,935,072.90Contract Sum182 daysProject Duration
16%
Complete
Physical Progress16%
Planned Progress22.5%
Time Elapsed33.5%
On Track • 121 days left

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2026-09-04
Completed
Scheduled Completion
2027-03-05
On Track
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceUva Province
DistrictBadulla
PD RegionUva Province
CE RegionBadulla
EE Division-
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Colombo Rathnapura Wellawaya Batticaloa Road (AA004) (212+000 - 213+500)
Estimated Road Lengths- km
Number of Roads-
Scope Summary-
Contractor & Award
Contract No.RDA/DRP/UVA/BAD/BAN/31
Tender Batch No.13
Contractor NameNimna Holdings (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date—
Contract Amount239,935,072.90
Engineer Estimate Amount (LKR)232,794,296.45
Duration (Days)182
CategoryEmergency