DRRRP Awarded Emergency

RDA/DRP/UVA/BAD/BAD/11

Rehabilitation / Improvement of (1) PASSARA MADULSIMA METIGAHATENNA ROAD (18+030-26+430)

BadullaUva ProvinceBadullaDivisional SecretariatJayanetti ConstructionContractorLKR 149,405,885.14Contract Sum182 daysProject Duration
70%
Complete
Physical Progress70%
Planned Progress97.3%
Time Elapsed89.6%
On Track • 18 days left

Project Timeline

LOA
2026-05-11
Completed
Possession
–
Pending
Commencement
2026-05-25
Completed
Scheduled Completion
2026-11-22
On Track
Anticipated Completion Date
2026-11-22
On Track

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceUva Province
DistrictBadulla
PD RegionUva Province
CE RegionBadulla
EE DivisionBadulla
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of (1) PASSARA MADULSIMA METIGAHATENNA ROAD (18+030-26+430)
Estimated Road Lengths- km
Number of Roads-
Scope Summary-
Contractor & Award
Contract No.RDA/DRP/UVA/BAD/BAD/11
Tender Batch No.8
Contractor NameJayanetti Construction
Consultant-
Tender StatusAwarded
LOA Date2026-05-11
Contract Amount149,405,885.14
Engineer Estimate Amount (LKR)159,486,625.18
Duration (Days)182
CategoryEmergency