DRRRP Awarded Emergency

RDA/DRP/CEN/NUE/NUE/60R

Rehabilitation / Improvement of Peradeniya Badulla Chenkaladi Road (A005) (40+750 - 42+850)

Nuwara EliyaCentral ProvinceNuwara EliyaDivisional SecretariatKSJ Construction (Pvt) LtdContractorLKR 336,313,078.73Contract Sum182 daysProject Duration
10%
Complete
Physical Progress10%
Planned Progress5.5%
Time Elapsed15.4%
On Track • 153 days left

Project Timeline

LOA
2026-09-21
Completed
Possession
2026-10-07
Completed
Commencement
2026-10-07
Completed
Scheduled Completion
2027-04-06
On Track
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceCentral Province
DistrictNuwara Eliya
PD RegionCentral Province
CE RegionNuwara Eliya
EE DivisionNuwara Eliya
Package No.2
Tender By-
Scope
Contract NameRehabilitation / Improvement of Peradeniya Badulla Chenkaladi Road (A005) (40+750 - 42+850)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryAsphalt overlay, Retaining wall Construction, U Drain Construction & Culvert Construction
Contractor & Award
Contract No.RDA/DRP/CEN/NUE/NUE/60R
Tender Batch No.10
Contractor NameKSJ Construction (Pvt) Ltd
ConsultantTeam Leader
Tender StatusAwarded
LOA Date2026-09-21
Contract Amount336,313,078.73
Engineer Estimate Amount (LKR)338,287,510.33
Duration (Days)182
CategoryEmergency