DRRRP Awarded Emergency

RDA/DRP/UVA/BAD/BAN/21

Rehabilitation / Improvement of Wellawaya - Ella - Kumbalwela (14+000-30+0000 (AA-023), Ella - Passara (B113) (0+000 -5+000) and Beragala Hali-Ela (A016) (0+000 -25+000)

BadullaUva ProvinceBadullaDivisional SecretariatSuhada EnterprisesContractorLKR 321,850,877.98Contract Sum182 daysProject Duration
56%
Complete
Physical Progress56%
Planned Progress100%
Time Elapsed100%
1 days behind schedule

Project Timeline

LOA
2026-04-22
Completed
Possession
–
Pending
Commencement
2026-05-06
Completed
Scheduled Completion
2026-11-03
Completed
Anticipated Completion Date
2026-11-03
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceUva Province
DistrictBadulla
PD RegionUva Province
CE RegionBadulla
EE DivisionBadulla
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Wellawaya - Ella - Kumbalwela (14+000-30+0000 (AA-023), Ella - Passara (B113) (0+000 -5+000) and Beragala Hali-Ela (A016) (0+000 -25+000)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryRetaining Structures
Contractor & Award
Contract No.RDA/DRP/UVA/BAD/BAN/21
Tender Batch No.7
Contractor NameSuhada Enterprises
Consultant-
Tender StatusAwarded
LOA Date2026-04-22
Contract Amount321,850,877.98
Engineer Estimate Amount (LKR)321,810,896.40
Duration (Days)182
CategoryEmergency