RDA/DRP/CEN/MTL/NAL/48R

Rehabilitation/Improvement of surfacing (ASphalt) hard shoulder,Shoulder, drain construction at Beligamuwa - Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)

MataleCentral ProvinceNalandaDivisional SecretariatS A P Engineering (Pvt) LtdContractorLKR 50,471,466.08Contract Sum154 daysProject Duration
5%
Complete
Physical Progress5%
Planned Progress11.9%
Time Elapsed21.4%
On Track • 120 days left

Project Timeline

LOA
2026-08-31
Completed
Possession
–
Pending
Commencement
2026-10-02
Completed
Scheduled Completion
2027-03-04
On Track
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceCentral Province
DistrictMatale
PD RegionCentral Province
CE RegionMatale
EE DivisionNalanda
Package No.6
Tender By-
Scope
Contract NameRehabilitation/Improvement of surfacing (ASphalt) hard shoulder,Shoulder, drain construction at Beligamuwa - Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
Estimated Road Lengths- km
Number of Roads0
Scope SummarySurfacing (Asphalt) , hard shoulder, shoulder, drain construction
Contractor & Award
Contract No.RDA/DRP/CEN/MTL/NAL/48R
Tender Batch No.11
Contractor NameS A P Engineering (Pvt) Ltd
ConsultantNalanda EE
Tender StatusAwarded
LOA Date2026-08-31
Contract Amount50,471,466.08
Engineer Estimate Amount (LKR)42,736,925.80
Duration (Days)154
CategoryEmergency