DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 55 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:55 awarded · Western Province
77.5% awarded

0

Awarded

71 total projects 81 roads in portfolio

2,249.3M

2,249.3 Mn

Contract Value

Spent 15.8% Remaining 84.2%
Avg
81.3%

11

works in progress

29 completed

Avg Progress

355.4M

355.4 Mn

Total Expenditure (incl. VAT)

15.8% of contract incl. VAT
72.7%

0

On Progress

40 / 55 awarded

0%

0

Delay

0 / 55 awarded

52.7%

0

Completed

29 / 55 awarded

Portfolio Breakdown · Western Province · Province

579Awarded739Total
Western Province 55 awarded of 71 Open filtered view
CategoryImplementation MethodTotal PortfolioAwarded PortfolioPending RoadsAwarded %Planned Exp MnActual Exp inclusive-VATPlanned %Actual %On ProgressDelay (10% - 20%)Critical Delay > 20%LOA Issued, Not Started yet
Total RoadsTotal ProjectsEst. Sanctioned ProjectsEst. Sanctioned RoadsPending Sanctioned RoadsSanctioned Length kmSanctioned Amount LKR MnEstimate LKR MnLOA Issued ProjectsLOA Issued RoadsAwarded Est LKR MnContract LKR Mn
TenderTender Above 50Mn7777015.66575.6575.644291.0207.0357%—10.45% of contract0.0%44.0%2——2
Tender Below 50Mn35353535024.60703.9657.12626513.4391.7974%102.594.824% of contract30.8%81.7%14—48
PIU133313044.252,149.02,149.013658.3659.11033%——0.0%0.0%———1
Not Specified220020.000.00.00—0.00.020%————————
Tender Total57474555284.513,428.53,381.731331,462.61,257.72466%102.5105.28% of contract25.8%74.2%160411
Direct LabourDL Stage 01888807.31211.8211.888211.8211.80100%211.8170.580% of contract100.0%100.0%8———
DL Stage 02333301.3134.734.73334.734.70100%34.719.657% of contract100.0%100.0%3———
DL Stage 03444402.9073.573.54473.573.50100%22.741.456% of contract50.0%100.0%4———
DL Stage 04999908.72671.688.89988.8671.60100%12.518.73% of contract11.1%57.8%9———
Direct Labour Total24242424020.24991.6408.82424408.8991.60100%281.7250.125% of contract58.3%84.2%24000
—Western Province817169792104.754,420.23,790.555571,871.42,249.32477%384.3355.416% of contract40.0%78.6%400411

Avg Physical Progress per EE Division · Western Province

At-Risk Projects · Western Province

218
Portfolio Timeline· 48 scheduled projects · Western Province Toggle
Portfolio · Awarded Works

Awarded Projects

4 projects

4/4 (filtered)

Filter awarded works

4 matching projects1 active

ActiveCritical Delay
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/02/25/03/WP/GMPRR/RDA/02/25/03
Development of De silva road beginning from Angurukaramulla temble road to Negombo Colombo road
0%
5,430,100.006,886,574.13Awarded
2RR/RDA/02/25/15
Udupila South Dolewatta
0%
7,423,117.708,968,820.62Awarded
3RR/RDA/03/25/16/WP/KTRRR/RDA/03/25/16
Development of carpeting of 1 km from Gane Aramba Road, Bogalla Junction to Ambepitiya Pinhena
0%
27,990,360.0037,805,645.98Awarded
4RR/RDA/03/25/18/WP/KTRRR/RDA/03/25/18
Development of carpeting of the section (length 800 m) from near Minerithenna temple to Jananandanarama temple
0%
17,101,775.0023,076,319.79Awarded
Showing 1–4 of 4
Per page:
Source: DRRRP • 71 projects • Data updated 2026-11-02 10:30 • 16:30:13