DRRRP Awarded Dl DL Stage 03

RR/RDA/01/25/17

Access road to Polgasowita Dikhena Aranya

ColomboWestern ProvinceAvissawellaDivisional Secretariat-ContractorLKR 7,965,231.10Contract Sum51 daysProject Duration
100%
Complete

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2025-09-26
Completed
Scheduled Completion
2025-11-15
Completed
Anticipated Completion Date
2025-11-15
Completed