DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 117 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:117 awarded · Northern Province
0%

0

Delay

0 / 117 awarded

Portfolio Breakdown · Northern Province · Province

579Awarded739Total
Northern Province 117 awarded of 136 Open filtered view
CategoryImplementation MethodTotal PortfolioAwarded PortfolioPending RoadsAwarded %Planned Exp MnActual Exp inclusive-VATPlanned %Actual %On ProgressDelay (10% - 20%)Critical Delay > 20%LOA Issued, Not Started yet
Total RoadsTotal ProjectsEst. Sanctioned ProjectsEst. Sanctioned RoadsPending Sanctioned RoadsSanctioned Length kmSanctioned Amount LKR MnEstimate LKR MnLOA Issued ProjectsLOA Issued RoadsAwarded Est LKR MnContract LKR Mn
TenderTender Above 50Mn494949490105.566,174.26,174.238385,140.03,653.11178%1,464.4685.919% of contract42.1%42.0%20—153
Tender Below 50Mn67676767057.472,075.02,075.062621,858.61,321.6593%539.2515.639% of contract43.5%75.5%49—13—
PIU9229029.791,344.91,344.9291,344.91,460.90100%——0.0%0.0%———2
Not Specified330030.000.00.00—0.00.030%————————
Tender Total1281211181253192.829,594.19,594.11021098,343.56,435.61984%2,003.61,201.519% of contract42.1%61.5%690285
Direct LabourDL Stage 01555504.34129.1129.155129.1129.10100%82.694.673% of contract80.0%100.0%5———
DL Stage 02666609.49255.1256.466256.4255.10100%187.7173.568% of contract66.7%100.0%6———
DL Stage 03222202.7085.285.22285.285.20100%85.248.857% of contract100.0%100.0%2———
DL Stage 04222201.0038.638.62238.638.60100%—22.759% of contract0.0%100.0%2———
Direct Labour Total15151515017.53508.0509.41515509.4508.00100%355.6339.667% of contract66.7%100.0%15000
—Northern Province1431361331403210.3510,102.210,103.51171248,852.96,943.61986%2,359.21,541.122% of contract45.3%66.5%840285

Avg Physical Progress per EE Division · Northern Province

At-Risk Projects · Northern Province

218
Portfolio Timeline· 104 scheduled projects · Northern Province Toggle
2025-06-21 today2026-11-04

Showing first 80 of 104 projects.

Portfolio · Awarded Works

Awarded Projects

29 projects

25/29 (filtered)

Filter awarded works

29 matching projects2 active

ActiveDelayed onlyOn Progress
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/12/25/17/NP/VVNRR/RDA/12/25/17
Lyca village enterance Road
35%
—54,064,384.24Awarded
2RR/RDA/12/25/22/NP/VVNRR/RDA/12/25/22
Mannankerny road
50%
—51,515,196.20Awarded
3RR/RDA/12/25/52/NP/VVNRR/RDA/12/25/52
Menanager Malakattu Kalkuwari Road
65%
—54,861,523.89Awarded
4RR/RDA/12/25/18/NP/VVNRR/RDA/12/25/18
Nedunkerny North sandankulam Road
35%
32,829,160.1046,839,314.91Awarded
5RR/RDA/12/25/19/NP/VVNRR/RDA/12/25/19
Senaipilavu Road
70%
32,576,225.0043,285,227.82Awarded
6RR/RDA/12/25/20/NP/VVNRR/RDA/12/25/20
Puthiyakudiyiruppu parasankulam road
70%
23,259,239.3034,966,229.53Awarded
7RR/RDA/12/25/21/NP/VVNRR/RDA/12/25/21
Bagaswewa 01st 22nd lane
35%
22,749,983.3033,747,516.65Awarded
8RR/RDA/12/25/24/NP/VVNRR/RDA/12/25/24
Kanagarayankulam puthuvilankulam road (NVVNE073)
70%
31,165,786.3046,468,981.72Awarded
9RR/RDA/12/25/25/NP/VVNRR/RDA/12/25/25
2nd cross Lane Ginigathhena
70%
27,770,291.0040,686,140.26Awarded
10RR/RDA/12/25/27/NP/VVNRR/RDA/12/25/27
From Acre 400 7th Lane to cross end of the 2nd internal road close to Andarawewa
30%
46,360,659.2457,948,785.02Awarded
11RR/RDA/12/25/28/NP/VVNRR/RDA/12/25/28
From Janaudanagama 2nd internal road to end of the free school
35%
26,569,012.2537,396,800.47Awarded
12RR/RDA/12/25/29/NP/VVNRR/RDA/12/25/29
Kalasiyambalawa Road
50%
13,504,281.4519,583,811.27Awarded
13RR/RDA/12/25/31/NP/VVNRR/RDA/12/25/31
Mahakachchakodiya to Ettambagaskada
30%
45,254,190.8559,974,624.42Awarded
14RR/RDA/12/25/35/NP/VVNRR/RDA/12/25/35
Awusadapitiya Pubudugama Road
70%
32,504,637.4346,347,432.25Awarded
15RR/RDA/12/25/38/NP/VVNRR/RDA/12/25/38
Salalinigama 11 lane
50%
30,830,906.7040,853,027.30Awarded
16RR/RDA/12/25/40/NP/VVNRR/RDA/12/25/40
Halabagaswewa
5%
25,032,191.2536,283,467.53Awarded
17RR/RDA/12/25/54/NP/VVNRR/RDA/12/25/54
Nikawewa Right Village Road
70%
17,143,053.9522,922,029.40Awarded
18RR/RDA/13/25/11/NP/MULRR/RDA/13/25/11
Ethawetuvuwewa to Sampathnuwara
30%
110,422,944.50141,810,206.62Awarded
19RR/RDA/11/25/01/NP/MNRRR/RDA/11/25/01
Mahilankulam Pallamadhu road
50%
189,602,588.30274,228,723.54Awarded
20RR/RDA/11/25/02/NP/MNRRR/RDA/11/25/02
Piramanayankulam Parappukadanthan road
55%
169,538,631.82244,135,763.06Awarded
21RR/RDA/11/25/04/NP/MNRRR/RDA/11/25/04
Tharavankottai to Keeri Main Road
60%
146,489,579.5076,333,504.20Awarded
22RR/RDA/11/25/07/NP/MNRRR/RDA/11/25/07
Avithappar Panimayam Internal Road with Culvert - Pesalai
70%
—85,087,335.02Awarded
23RR/RDA/11/25/11/NP/MNRRR/RDA/11/25/11
Eruvittan - Vellalakaddu Road
5%
—57,826,727.83Awarded
24RR/RDA/11/25/05/NP/MNRRR/RDA/11/25/05
Konnayan Kudiyiruppu Internal Main Road
5%
90,000,000.00135,947,165.98Awarded
25RR/RDA/11/25/09/NP/MNRRR/RDA/11/25/09
Renovation of Mathirikiramam internal Road Naruvilikulam
70%
28,422,878.0040,820,067.58Awarded
Showing 1–25 of 29
Per page:
Source: DRRRP • 136 projects • Data updated 2026-11-02 10:30 • 14:37:33