DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/11/25/20/NP/MNR

Kondachchi to Pasithenral Road

MannarNorthern ProvinceMannarDivisional SecretariatAbdul Cader ConstructionsContractorLKR 18,513,473.00Contract Sum0 daysProject Duration
70%
Complete
Physical Progress70%
Planned Progress0%
Time Elapsed0%
On Track • 0 days left

Project Timeline

LOA
2025-11-26
Completed
Possession
–
Pending
Commencement
2026-01-01
Completed
Scheduled Completion
–
Pending
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorthern Province
DistrictMannar
DS Division-
GN Division-
Electorate-
PD RegionNorthern Province
CE RegionVavuniya
EE DivisionMannar
Authority Tier-
Authority Name-
Package No.RR/RDA/11/25/20
Tender ByProvincial Director