DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 80 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:80 awarded · Central Province
0%

0

Delay

0 / 80 awarded

Portfolio Breakdown · Central Province · Province

579Awarded739Total
Central Province 80 awarded of 97 Open filtered view
CategoryImplementation MethodTotal PortfolioAwarded PortfolioPending RoadsAwarded %Planned Exp MnActual Exp inclusive-VATPlanned %Actual %On ProgressDelay (10% - 20%)Critical Delay > 20%LOA Issued, Not Started yet
Total RoadsTotal ProjectsEst. Sanctioned ProjectsEst. Sanctioned RoadsPending Sanctioned RoadsSanctioned Length kmSanctioned Amount LKR MnEstimate LKR MnLOA Issued ProjectsLOA Issued RoadsAwarded Est LKR MnContract LKR Mn
TenderTender Above 50Mn27272727069.312,423.22,426.819191,758.41,398.4870%1,034.2290.621% of contract73.5%51.6%5—131
Tender Below 50Mn44444444049.481,358.61,359.537371,199.6912.8784%692.5506.555% of contract78.4%81.5%28—9—
PIU000000.000.00.00—0.00.000%————————
Not Specified220020.000.0209.30—0.00.020%————————
Tender Total737371712118.793,781.83,995.656562,958.02,311.31777%1,726.8797.134% of contract76.7%71.4%330221
Direct LabourDL Stage 019999012.26359.8361.499361.4359.80100%359.8323.890% of contract100.0%100.0%9———
DL Stage 02666607.81212.7212.766212.7212.70100%212.7158.675% of contract100.0%100.0%6———
DL Stage 03888807.03179.4179.488179.4179.40100%179.478.144% of contract100.0%82.3%5—3—
DL Stage 04111101.5056.256.21156.256.20100%56.218.834% of contract100.0%75.0%——1—
Direct Labour Total24242424028.60808.1809.62424809.6808.10100%808.1579.372% of contract100.0%93.0%20040
—Central Province979795952147.394,589.94,805.280803,767.63,119.31782%2,534.81,376.444% of contract83.7%77.9%530261

Avg Physical Progress per EE Division · Central Province

At-Risk Projects · Central Province

218
Portfolio Timeline· 80 scheduled projects · Central Province Toggle
2025-06-19 today2026-11-20
100%
10%
73%
40%
25%
20%
5%
Portfolio · Awarded Works

Awarded Projects

47 projects

25/47 (filtered)

Filter awarded works

47 matching projects2 active

ActiveProgress 100–100%Completed
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/04/25/15/CP/KYRR/RDA/04/25/15
Madolkale sita Huluganga dakwa yana athuru margaye Bandaranayakapura gam kotasata adala Margaya
100%
12,711,509.5920,856,501.79Awarded
2RR/RDA/04/25/16
Palawa ihala meda Wijitha mawatha Waliyangadeniya margaya yakarana athuru Margaya
100%
12,240,493.1016,221,430.00Awarded
3RR/RDA/04/25/17/CP/KYRR/RDA/04/25/17
Nuganga Margaya
100%
9,650,635.5015,455,845.00Awarded
4RR/RDA/04/25/22/CP/KYRR/RDA/04/25/22
Rambukwella viharasthanaya asala sita Dodamgolla Rambukwella nagenhira haraha Udispaththuwa dakwa diwena Margaya
100%
15,056,107.0026,802,449.26Awarded
5RR/RDA/04/25/23/CP/KYRR/RDA/04/25/23
Minuwangamuwa gammada margaye Aberathne mahathage niwasa asala sita Abesinha Banda mahathage Niwasa dakwa
100%
27,734,432.5549,079,937.23Awarded
6RR/RDA/04/25/27/CP/KYRR/RDA/04/25/27
Dadahogama pitiye gedara pathibami sahitha Margaya
100%
12,532,355.0014,990,258.08Awarded
7RR/RDA/04/25/31/CP/KYRR/RDA/04/25/31
Shantha Janapada Village middle road
100%
42,357,645.0047,278,636.42Awarded
8RR/RDA/04/25/32/CP/KYRR/RDA/04/25/32
Pilawala Navodya pasala asala sita Nelumpathhinna pansala dakwa margaya
100%
18,059,531.2719,939,938.98Awarded
9RR/RDA/04/25/33/CP/KYRR/RDA/04/25/33
New forest kotase Jana Udana gammana margaya
100%
6,992,144.5012,512,939.76Awarded
10RR/RDA/04/25/34/CP/KYRR/RDA/04/25/34
Liyandeniya wewa margya
100%
9,134,433.0011,711,039.23Awarded
11RR/RDA/04/25/35/CP/KYRR/RDA/04/25/35
Gamunupura Gonawatta pradana margaye Gamunupura pera pasala asala sita idiriyata pradana margaya
100%
30,043,716.0134,175,878.49Awarded
12RR/RDA/04/25/43/CP/KYRR/RDA/04/25/43
Dodamgolla kowila asla sita hindu susana boomiya dakwa margaya
100%
14,680,539.5026,797,465.46Awarded
13RR/RDA/05/25/01/CP/MTLRR/RDA/05/25/01
Moragahamada pasala asalin arambhawa Rajagammana gama madin Madawala adawala para dakwa pradana athuru Margaya
100%
41,535,473.6460,115,019.16Awarded
14RR/RDA/05/25/02/CP/MTLRR/RDA/05/25/02
Lakshahena maragaya Mathalapitiya margaye sita Lakshahena Kosgolla dakwa Margaya
100%
36,743,107.5050,437,576.84Awarded
15RR/RDA/05/25/04/CP/MTLRR/RDA/05/25/04
Aiththaliyadda sita Porcilain eka dakwa Margaya
100%
27,015,791.0033,583,183.30Awarded
16RR/RDA/05/25/12/CP/MTLRR/RDA/05/25/12
A9 pare Kist biscuit factoryata meha sithuwam kanda board eka (savikara athi) Nalanda wattata yana para
100%
10,340,000.0014,006,802.35Awarded
17RR/RDA/05/25/13/CP/MTLRR/RDA/05/25/13
A9 pare Elik Aluvihare niwasa lagin arambha wee Hunugalwala dakwa margaya
100%
19,486,197.5027,383,521.12Awarded
18RR/RDA/05/25/16/CP/MTLRR/RDA/05/25/16
Dangan pedesa Mithragama margya Kurunegala margaye sita Mithragama
100%
23,856,545.3533,031,745.33Awarded
19RR/RDA/05/25/17/CP/MTLRR/RDA/05/25/17
Ambagastenna to gurubebila temple via Polwaththa nikawella
100%
56,391,365.6373,216,443.75Awarded
20RR/RDA/05/25/18/CP/MTLRR/RDA/05/25/18
Bandarapola Ulpathapitiya haraha Kiula margaya
100%
26,720,870.0034,151,478.52Awarded
21RR/RDA/05/25/19/CP/MTLRR/RDA/05/25/19
Katudeniya bahukarya godanagilla asala Hettiyawatta dakwa margaya
100%
13,129,506.5017,556,901.60Awarded
22RR/RDA/05/25/20/CP/MTLRR/RDA/05/25/20
Harispattuwa margaya arambaka mansandiye sita Thusitha maranadara godanagilla dakwa
100%
15,584,937.5021,943,997.74Awarded
23RR/RDA/05/25/22/CP/MTLRR/RDA/05/25/22
Sigirimulla sita Mailetthewa Aluthyaya dakwa margaya
100%
33,057,264.9048,133,410.98Awarded
24RR/RDA/05/25/24/CP/MTLRR/RDA/05/25/24
Pahala Hombawa palama dakwa Daduwagolla kanaththa langa sita
100%
35,817,952.5049,816,825.04Awarded
25RR/RDA/05/25/27/CP/MTLRR/RDA/05/25/27
Welemulla sita Kandewaththa
100%
23,207,525.0032,539,052.69Awarded
Showing 1–25 of 47
Per page:
Source: DRRRP • 97 projects • Data updated 2026-11-02 10:30 • 19:05:08