DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 59 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:59 awarded · North Western Province
74.7% awarded

0

Awarded

79 total projects 79 roads in portfolio

2,201.9M

2,201.9 Mn

Contract Value

Spent 50.3% Remaining 49.7%
1,107.0M

1,107.0 Mn

Total Expenditure (incl. VAT)

50.3% of contract incl. VAT
35.6%

0

Critical Delay

21 / 59 awarded

Portfolio Breakdown · North Western Province · Province

579Awarded739Total
North Western Province 59 awarded of 79 Open filtered view
CategoryImplementation MethodTotal PortfolioAwarded PortfolioPending RoadsAwarded %Planned Exp MnActual Exp inclusive-VATPlanned %Actual %On ProgressDelay (10% - 20%)Critical Delay > 20%LOA Issued, Not Started yet
Total RoadsTotal ProjectsEst. Sanctioned ProjectsEst. Sanctioned RoadsPending Sanctioned RoadsSanctioned Length kmSanctioned Amount LKR MnEstimate LKR MnLOA Issued ProjectsLOA Issued RoadsAwarded Est LKR MnContract LKR Mn
TenderTender Above 50Mn18181818046.851,299.21,299.213131,003.1690.6572%593.593.113% of contract84.6%62.9%4—9—
Tender Below 50Mn34343434031.67956.2956.22424689.5529.01071%529.0229.043% of contract100.0%77.6%9312—
PIU000000.000.00.00—0.00.000%————————
Not Specified550050.000.00.00—0.00.050%————————
Tender Total57575252578.522,255.42,255.437371,692.61,219.62065%1,122.6322.126% of contract94.6%72.4%133210
Direct LabourDL Stage 016666014.24445.0444.766444.7445.00100%132.2385.387% of contract83.3%100.0%6———
DL Stage 02777708.45264.3264.477264.4264.30100%122.7212.580% of contract42.9%100.0%7———
DL Stage 03111101.1025.225.21125.225.20100%—17.971% of contract0.0%100.0%1———
DL Stage 04888809.43247.8247.888247.8247.80100%—169.268% of contract0.0%94.0%8———
Direct Labour Total22222222033.22982.3982.02222982.0982.30100%254.9784.980% of contract36.4%97.8%22000
—North Western Province797974745111.743,237.63,237.459592,674.72,201.92075%1,377.51,107.050% of contract72.9%81.9%353210

Avg Physical Progress per EE Division · North Western Province

At-Risk Projects · North Western Province

218
Portfolio Timeline· 51 scheduled projects · North Western Province Toggle
Portfolio · Awarded Works

Awarded Projects

26 projects

25/26 (filtered)

Filter awarded works

26 matching projects1 active

ActiveDelayed only
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/18/25/01/NWP/KRGRR/RDA/18/25/01
Development of Egodagama Talakolawewa road
60%
98,323,766.14156,184,445.89Awarded
2RR/RDA/18/25/04/NWP/KRGRR/RDA/18/25/04
The road from Hunugallewa road junction to Madadenigama Hunugallewa Mahamaruwa Beligahaya to Mee Oya bridge
40%
59,066,766.7485,865,152.06Awarded
3RR/RDA/18/25/07/NWP/KRGRR/RDA/18/25/07
Road from Moragolla Junction to Nabadewa Girilla Carpet Road via Kirinda
75%
59,247,280.2979,393,864.19Awarded
4RR/RDA/18/25/09/NWP/KRGRR/RDA/18/25/09
Paving the road from Pahala Galapitiyagama to Tharanagolla Sports Ground
0%
70,405,428.6081,982,091.15Awarded
5RR/RDA/18/25/11/NWP/KRGRR/RDA/18/25/11
Development of road from Dambulu Road to Havanathenna via Ehelagollaya
65%
46,193,949.6864,750,199.52Awarded
6RR/RDA/18/25/22/NWP/KRGRR/RDA/18/25/22
Paving of culverts and sidewalls at the necessary places on the road from near Moragane Samiti Hall to Siyambalaweva via Galkadulla.
65%
67,074,479.5577,881,819.09Awarded
7RR/RDA/18/25/135/NWP/KRGRR/RDA/18/25/135
Kelegedara Gamameda Road (CTB Basaya Dawanaya wana) Kavudumunna, Kunumade, Hungan pitiya haraha diwena Margaya Kapat Kirima
20%
41,750,386.7055,779,764.12Awarded
8RR/RDA/18/25/137/NWP/KRGRR/RDA/18/25/137
Damunugolla Sita Kobbewehera Handiya Dakwa Margaya Kapat Kirima
45%
18,425,029.4623,865,719.81Awarded
9RR/RDA/18/25/138/NWP/KRGRR/RDA/18/25/138
Pudukkulama Bogas Handiye sita Keppitiya haraha Thihawa Dakwa Margaya Kapat Kirima
20%
30,650,394.0639,359,193.23Awarded
10RR/RDA/18/25/139/NWP/KRGRR/RDA/18/25/139
Akkara Panaha Mansandiye Sita Walahamulla Dakwa Margaya
90%
28,112,995.7541,102,824.35Awarded
11RR/RDA/18/25/308
Wijekoon Mawatha near Narammala Bus Stand and Hospital Mawatha from Peralaswella
65%
10,696,008.2811,985,499.69Awarded
12RR/RDA/19/25/01/NWP/PUTRR/RDA/19/25/01
Development of carpeting the Gammedda road up to Anathapara.
65%
27,734,432.5524,961,884.73Awarded
13RR/RDA/19/25/04/NWP/PUTRR/RDA/19/25/04
Carpeting of green light carpeted road from Bogus Junction (80 acres).
65%
34,055,720.0559,154,724.51Awarded
14RR/RDA/19/25/05/NWP/PUTRR/RDA/19/25/05
Development of the road from near Mr. Chaminda's house to Boga Pathaha
65%
36,592,843.9560,367,316.08Awarded
15RR/RDA/19/25/08/NWP/PUTRR/RDA/19/25/08
Carpeting of Velasia Main Road from Madurankuliya.
70%
39,584,083.5061,899,364.50Awarded
16RR/RDA/19/25/27/NWP/PUTRR/RDA/19/25/27
The entrance to the Medical Officer's Office in the Galahitiyawa Grama Niladhari Division
60%
38,495,776.0049,714,778.94Awarded
17RR/RDA/19/25/30/NWP/PUTRR/RDA/19/25/30
Development of carpeting from Mihirajthotupola to Serakkuliya 1 on the Serakkuliya main road
70%
38,494,009.5045,465,357.54Awarded
18RR/RDA/19/25/31/NWP/PUTRR/RDA/19/25/31
Development of carpeting from the point where carpeting has stopped on the Tammana main road
50%
26,013,841.8339,960,885.90Awarded
19RR/RDA/19/25/32/NWP/PUTRR/RDA/19/25/32
Development of the Bammeyaya Road
50%
10,904,293.4017,431,257.91Awarded
20RR/RDA/19/25/33/NWP/PUTRR/RDA/19/25/33
Development of the road from near the Sugatarama Temple, Periyakulam to Thalgaswewa
45%
24,440,875.2538,370,082.14Awarded
21RR/RDA/19/25/34/NWP/PUTRR/RDA/19/25/34
Carpeting & Development of Bodhirajapura 4th Lane
70%
12,568,847.5019,966,435.66Awarded
22RR/RDA/19/25/37/NWP/PUTRR/RDA/19/25/37
Lawyer Wijayananda's House Road
70%
7,763,919.689,913,614.44Awarded
23RR/RDA/19/25/38/NWP/PUTRR/RDA/19/25/38
North Dummaladeniya Cross Road
90%
10,005,001.7811,621,041.20Awarded
24RR/RDA/19/25/39/NWP/PUTRR/RDA/19/25/39
Renovation of Khemananda Road
95%
19,114,271.4522,000,226.26Awarded
25RR/RDA/19/25/40
Development of the road from Madurankuliya to Velasiya College
30%
55,254,878.0090,437,412.35Awarded
Showing 1–25 of 26
Per page:
Source: DRRRP • 79 projects • Data updated 2026-11-02 10:30 • 14:42:41