DRRRP Awarded Tender Tender Above 50Mn

RR/RDA/18/25/24/NWP/KRG

Paving and developing the road from Seelarathana Mawatha to Girana Junction

KurunegalaNorth Western ProvinceKuliyapitiyaDivisional SecretariatSenerath Engineering (pvt) LtdContractorLKR 37,201,129.80Contract Sum119 daysProject Duration
100%
Complete

Project Timeline

LOA
2025-11-20
Completed
Possession
–
Pending
Commencement
2026-01-03
Completed
Scheduled Completion
2026-03-05
Completed
Anticipated Completion Date
2026-04-02
Completed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorth Western Province
DistrictKurunegala
DS Division-
GN Division-
Electorate-
PD RegionNorth Western Province
CE RegionKurunegala
EE DivisionKuliyapitiya
Authority Tier-
Authority Name-
Package No.RR/RDA/18/25/24
Tender ByProcurement Division