DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 58 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:58 awarded · North Central Province
69% awarded

0

Awarded

84 total projects 84 roads in portfolio

2,521.0M

2,521.0 Mn

Contract Value

Spent 46.8% Remaining 53.2%
Avg
65.7%

25

works in progress

26 completed

Avg Progress

1,179.8M

1,179.8 Mn

Total Expenditure (incl. VAT)

46.8% of contract incl. VAT
84.5%

0

On Progress

49 / 58 awarded

0%

0

Delay

0 / 58 awarded

Portfolio Breakdown · North Central Province · Province

579Awarded739Total
North Central Province 58 awarded of 84 Open filtered view
CategoryImplementation MethodTotal PortfolioAwarded PortfolioPending RoadsAwarded %Planned Exp MnActual Exp inclusive-VATPlanned %Actual %On ProgressDelay (10% - 20%)Critical Delay > 20%LOA Issued, Not Started yet
Total RoadsTotal ProjectsEst. Sanctioned ProjectsEst. Sanctioned RoadsPending Sanctioned RoadsSanctioned Length kmSanctioned Amount LKR MnEstimate LKR MnLOA Issued ProjectsLOA Issued RoadsAwarded Est LKR MnContract LKR Mn
TenderTender Above 50Mn21212121042.591,696.51,696.51313999.6715.1862%87.477.511% of contract15.4%42.3%10—21
Tender Below 50Mn35353535035.181,187.41,187.42323851.4653.01266%—167.526% of contract0.0%44.7%18——5
PIU000000.000.00.00—0.00.000%————————
Not Specified660060.000.00.00—0.00.060%————————
Tender Total62625656677.772,883.82,883.836361,851.01,368.12658%87.4245.018% of contract5.6%43.8%28026
Direct LabourDL Stage 01555506.49232.8232.855232.8232.80100%182.0202.487% of contract80.0%100.0%5———
DL Stage 02555504.76173.2173.255173.2173.20100%34.9133.877% of contract20.0%100.0%5———
DL Stage 036666011.39346.4349.266349.2346.40100%—285.883% of contract0.0%100.0%6———
DL Stage 04666608.36400.5400.566400.5400.50100%—312.978% of contract0.0%96.0%5——1
Direct Labour Total22222222031.001,152.91,155.722221,155.71,152.90100%216.9934.881% of contract22.7%98.9%21001
—North Central Province848478786108.774,036.84,039.558583,006.72,521.02669%304.31,179.847% of contract12.1%64.7%49027

Avg Physical Progress per EE Division · North Central Province

At-Risk Projects · North Central Province

218
Portfolio Timeline· 46 scheduled projects · North Central Province Toggle
Portfolio · Awarded Works

Awarded Projects

0 projects

0/0 (filtered)

Filter awarded works

0 matching projects1 active

ActiveDelay
Showing 0–0 of 0
Per page:
Source: DRRRP • 84 projects • Data updated 2026-11-02 10:30 • 20:48:39