DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 58 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:58 awarded · North Central Province
69% awarded

0

Awarded

84 total projects 84 roads in portfolio

2,521.0M

2,521.0 Mn

Contract Value

Spent 46.8% Remaining 53.2%
Avg
65.7%

25

works in progress

26 completed

Avg Progress

1,179.8M

1,179.8 Mn

Total Expenditure (incl. VAT)

46.8% of contract incl. VAT
84.5%

0

On Progress

49 / 58 awarded

0%

0

Delay

0 / 58 awarded

Portfolio Breakdown · North Central Province · Province

579Awarded739Total
North Central Province 58 awarded of 84 Open filtered view
CategoryImplementation MethodTotal PortfolioAwarded PortfolioPending RoadsAwarded %Planned Exp MnActual Exp inclusive-VATPlanned %Actual %On ProgressDelay (10% - 20%)Critical Delay > 20%LOA Issued, Not Started yet
Total RoadsTotal ProjectsEst. Sanctioned ProjectsEst. Sanctioned RoadsPending Sanctioned RoadsSanctioned Length kmSanctioned Amount LKR MnEstimate LKR MnLOA Issued ProjectsLOA Issued RoadsAwarded Est LKR MnContract LKR Mn
TenderTender Above 50Mn21212121042.591,696.51,696.51313999.6715.1862%87.477.511% of contract15.4%42.3%10—21
Tender Below 50Mn35353535035.181,187.41,187.42323851.4653.01266%—167.526% of contract0.0%44.7%18——5
PIU000000.000.00.00—0.00.000%————————
Not Specified660060.000.00.00—0.00.060%————————
Tender Total62625656677.772,883.82,883.836361,851.01,368.12658%87.4245.018% of contract5.6%43.8%28026
Direct LabourDL Stage 01555506.49232.8232.855232.8232.80100%182.0202.487% of contract80.0%100.0%5———
DL Stage 02555504.76173.2173.255173.2173.20100%34.9133.877% of contract20.0%100.0%5———
DL Stage 036666011.39346.4349.266349.2346.40100%—285.883% of contract0.0%100.0%6———
DL Stage 04666608.36400.5400.566400.5400.50100%—312.978% of contract0.0%96.0%5——1
Direct Labour Total22222222031.001,152.91,155.722221,155.71,152.90100%216.9934.881% of contract22.7%98.9%21001
—North Central Province848478786108.774,036.84,039.558583,006.72,521.02669%304.31,179.847% of contract12.1%64.7%49027

Avg Physical Progress per EE Division · North Central Province

At-Risk Projects · North Central Province

218
Portfolio Timeline· 46 scheduled projects · North Central Province Toggle
Portfolio · Awarded Works

Awarded Projects

19 projects

19/19 (filtered)

Filter awarded works

19 matching projects1 active

ActiveDelayed only
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/20/25/01/NCP/ANPRR/RDA/20/25/01
Road from Thambuttegama - Nochchiyagama road to the road near the DIG's office of Thambuthegama Rajanganaya
30%
96,940,000.00147,079,527.92Awarded
2RR/RDA/20/25/03/NCP/ANPRR/RDA/20/25/03
Thalawa - Eppawala margaye kele Amunukola handiyen aramba vee kele amunukola viddiyalayen divena margaya
40%
26,155,768.3741,286,372.10Awarded
3RR/RDA/20/25/04/NCP/ANPRR/RDA/20/25/04
A - 9 maragayen aramba vee wale kade dakwa margaya
45%
27,008,370.5143,911,304.25Awarded
4RR/RDA/20/25/06/NCP/ANPRR/RDA/20/25/06
Ududumbara boogas handiye sita sarakkugala pasal handiya dakwa margaya
0%
26,692,661.0144,183,866.35Awarded
5RR/RDA/20/25/11/NCP/ANPRR/RDA/20/25/11
Palayakulama sita halmillakulama dakwa margaya
75%
20,887,268.2033,233,870.01Awarded
6RR/RDA/20/25/16/NCP/ANPRR/RDA/20/25/16
Hiriwadunna handiye sita idigaswewa pansal handiya dakwa margaya
80%
33,000,000.0059,684,748.55Awarded
7RR/RDA/20/25/18/NCP/ANPRR/RDA/20/25/18
Pahala Talawa road of Thalawa Andarawewa road
80%
32,443,580.5046,999,616.70Awarded
8RR/RDA/20/25/26/NCP/ANPRR/RDA/20/25/26
Development of IV lane from Nuwara Road to Mihinthalaya Road
6%
29,650,453.2938,283,840.94Awarded
9RR/RDA/20/25/28/NCP/ANPRR/RDA/20/25/28
Development of Rathnayake Mawatha
5%
23,041,750.8030,142,796.86Awarded
10RR/RDA/20/25/29/NCP/ANPRR/RDA/20/25/29
Development of the road from Udugama Colony rural road near the A9 road to the front of Mr. Somaratne Senanayake's house
0%
27,986,392.0632,982,943.17Awarded
11RR/RDA/20/25/53
Development of road from Sripura main road to 38 Kolaniya Cemetery
2%
27,971,333.1333,546,861.12Awarded
12RR/RDA/20/25/54
Development of road from Wahalkada D6 to Thalapakattialam on Punchimudagama road
5%
33,242,915.6440,137,233.68Awarded
13RR/RDA/20/25/55
Development of first phase of road from Punewa to Warakwewa
25%
29,762,232.5034,843,454.40Awarded
14RR/RDA/20/25/56
Development of the road from Punewa Junction to Kudahalmillewa Lake
25%
28,506,545.0033,620,055.04Awarded
15RR/RDA/20/25/57
Development of the road from near Ikirigollawa Muslim Maha Vidyalaya to Ratmalgahawewa main road from near Ikirigollawa dam to Ratmalgahawa road
30%
10,767,548.0014,249,058.84Awarded
16RR/RDA/20/25/59
From Makicchawa Junction to Temple (to Kulumiwakada Junction)
35%
29,006,146.8037,056,005.00Awarded
17RR/RDA/21/25/03/NCP/POLRR/RDA/21/25/03
Mahasenpura pradeepika kadaya asala sita Katukeliyawa dakwa margaya Carpart kireema
80%
33,480,137.3353,473,343.43Awarded
18RR/RDA/21/25/17/NCP/POLRR/RDA/21/25/26
Development of the road from Kaduruwela Muslim Kolaniya road to Pachcha Palliya
80%
53,880,000.0075,598,504.72Awarded
19RR/RDA/21/25/17/NCP/POLRR/RDA/21/25/27
Development of 1 canal Road from Kadurwela Muslim Kolaniya Road to Parakum Mawatha
45%
54,640,000.0062,351,983.93Awarded
Showing 1–19 of 19
Per page:
Source: DRRRP • 84 projects • Data updated 2026-11-02 10:30 • 14:31:13