Project Monitoring Dashboard
Comprehensive overview of 29 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka.
Updated 2026-11-02 10:30Live
Graphs reflect current view:29 awarded · Galle
61.7% awarded
0
Awarded
47 total projects 47 roads in portfolio
Awarded projects29
RR/RDA/07/25/02/SP/GALDelgahabedda-Kirimatiya MargayaRR/RDA/07/25/05/SP/GALAtawalawatta Sri Rewatha Viduhala Idiripita MargayaRR/RDA/07/25/06/SP/GALMulana Nagenahira ha Panwila Grama Niladari Wasam Sambandha wana athuru MargayaRR/RDA/07/25/08/SP/GALMahajana Mawatha Magurukaduwa Margaya Elpitiya Pitigala Pradhana Margaye sita Magurukaduwa Awasanaya dakwa Concrete athura Sanwardanaya KirimaRR/RDA/07/25/09/SP/GALPanwila Hena Pradhana Margaya Lalith Mahathage Niwasa Asala Sita Manjula Jayaweera Mahathage Niwasa Dakwa MargayaRR/RDA/07/25/11/SP/GALElathota Pituwara Margaya Depasa Kanu ha Pathi Bami Yoda Carpet KirimaRR/RDA/07/25/12/SP/GALGalandeniya MargayaRR/RDA/07/25/13/SP/GALAganaketiya Anuruddagama Mansandiye sita Samagipura dakwa Pradana MaragayaRR/RDA/07/25/15/SP/GALDikhena MargayaRR/RDA/07/25/17/SP/GALDasa Kadaya Asala sita Jack Fruit Ceylon (Pvt) ayathanaya dakwa Margaya 1 Km carpert kirimaRR/RDA/07/25/19/SP/GALSuriEla MargayaRR/RDA/07/25/20/SP/GALRoad from Kammale Kadaya Junction to Udumalagala JuunctionRR/RDA/07/26/10KM/05Widening and Development of the road from Angaliya Junction to Akuratiya Hill with culvertsRR/RDA/07/26/10KM/08Development of 700 meters from Baddegama Vanduramba Road near Kola Kids Preschool and 300 meters from Temple Junction towards DolahenaRR/RDA/07/26/10KM/129 Pillar Junction to Mr. Asanka's Shop on Udubattawa Watta Road
+14 more…
Click to filter the awarded table
847.6M
847.6 Mn
Contract Value
Awarded projects29
RR/RDA/07/25/02/SP/GALDelgahabedda-Kirimatiya MargayaRR/RDA/07/25/05/SP/GALAtawalawatta Sri Rewatha Viduhala Idiripita MargayaRR/RDA/07/25/06/SP/GALMulana Nagenahira ha Panwila Grama Niladari Wasam Sambandha wana athuru MargayaRR/RDA/07/25/08/SP/GALMahajana Mawatha Magurukaduwa Margaya Elpitiya Pitigala Pradhana Margaye sita Magurukaduwa Awasanaya dakwa Concrete athura Sanwardanaya KirimaRR/RDA/07/25/09/SP/GALPanwila Hena Pradhana Margaya Lalith Mahathage Niwasa Asala Sita Manjula Jayaweera Mahathage Niwasa Dakwa MargayaRR/RDA/07/25/11/SP/GALElathota Pituwara Margaya Depasa Kanu ha Pathi Bami Yoda Carpet KirimaRR/RDA/07/25/12/SP/GALGalandeniya MargayaRR/RDA/07/25/13/SP/GALAganaketiya Anuruddagama Mansandiye sita Samagipura dakwa Pradana MaragayaRR/RDA/07/25/15/SP/GALDikhena MargayaRR/RDA/07/25/17/SP/GALDasa Kadaya Asala sita Jack Fruit Ceylon (Pvt) ayathanaya dakwa Margaya 1 Km carpert kirimaRR/RDA/07/25/19/SP/GALSuriEla MargayaRR/RDA/07/25/20/SP/GALRoad from Kammale Kadaya Junction to Udumalagala JuunctionRR/RDA/07/26/10KM/05Widening and Development of the road from Angaliya Junction to Akuratiya Hill with culvertsRR/RDA/07/26/10KM/08Development of 700 meters from Baddegama Vanduramba Road near Kola Kids Preschool and 300 meters from Temple Junction towards DolahenaRR/RDA/07/26/10KM/129 Pillar Junction to Mr. Asanka's Shop on Udubattawa Watta Road
+14 more…
Click to filter the awarded table
Avg
96.4%
6
works in progress
14 completed
Avg Progress
Awarded projects29
RR/RDA/07/25/02/SP/GALDelgahabedda-Kirimatiya MargayaRR/RDA/07/25/05/SP/GALAtawalawatta Sri Rewatha Viduhala Idiripita MargayaRR/RDA/07/25/06/SP/GALMulana Nagenahira ha Panwila Grama Niladari Wasam Sambandha wana athuru MargayaRR/RDA/07/25/08/SP/GALMahajana Mawatha Magurukaduwa Margaya Elpitiya Pitigala Pradhana Margaye sita Magurukaduwa Awasanaya dakwa Concrete athura Sanwardanaya KirimaRR/RDA/07/25/09/SP/GALPanwila Hena Pradhana Margaya Lalith Mahathage Niwasa Asala Sita Manjula Jayaweera Mahathage Niwasa Dakwa MargayaRR/RDA/07/25/11/SP/GALElathota Pituwara Margaya Depasa Kanu ha Pathi Bami Yoda Carpet KirimaRR/RDA/07/25/12/SP/GALGalandeniya MargayaRR/RDA/07/25/13/SP/GALAganaketiya Anuruddagama Mansandiye sita Samagipura dakwa Pradana MaragayaRR/RDA/07/25/15/SP/GALDikhena MargayaRR/RDA/07/25/17/SP/GALDasa Kadaya Asala sita Jack Fruit Ceylon (Pvt) ayathanaya dakwa Margaya 1 Km carpert kirimaRR/RDA/07/25/19/SP/GALSuriEla MargayaRR/RDA/07/25/20/SP/GALRoad from Kammale Kadaya Junction to Udumalagala JuunctionRR/RDA/07/26/10KM/05Widening and Development of the road from Angaliya Junction to Akuratiya Hill with culvertsRR/RDA/07/26/10KM/08Development of 700 meters from Baddegama Vanduramba Road near Kola Kids Preschool and 300 meters from Temple Junction towards DolahenaRR/RDA/07/26/10KM/129 Pillar Junction to Mr. Asanka's Shop on Udubattawa Watta Road
+14 more…
Click to filter the awarded table
433.8M
433.8 Mn
Total Expenditure (incl. VAT)
Awarded projects29
RR/RDA/07/25/02/SP/GALDelgahabedda-Kirimatiya MargayaRR/RDA/07/25/05/SP/GALAtawalawatta Sri Rewatha Viduhala Idiripita MargayaRR/RDA/07/25/06/SP/GALMulana Nagenahira ha Panwila Grama Niladari Wasam Sambandha wana athuru MargayaRR/RDA/07/25/08/SP/GALMahajana Mawatha Magurukaduwa Margaya Elpitiya Pitigala Pradhana Margaye sita Magurukaduwa Awasanaya dakwa Concrete athura Sanwardanaya KirimaRR/RDA/07/25/09/SP/GALPanwila Hena Pradhana Margaya Lalith Mahathage Niwasa Asala Sita Manjula Jayaweera Mahathage Niwasa Dakwa MargayaRR/RDA/07/25/11/SP/GALElathota Pituwara Margaya Depasa Kanu ha Pathi Bami Yoda Carpet KirimaRR/RDA/07/25/12/SP/GALGalandeniya MargayaRR/RDA/07/25/13/SP/GALAganaketiya Anuruddagama Mansandiye sita Samagipura dakwa Pradana MaragayaRR/RDA/07/25/15/SP/GALDikhena MargayaRR/RDA/07/25/17/SP/GALDasa Kadaya Asala sita Jack Fruit Ceylon (Pvt) ayathanaya dakwa Margaya 1 Km carpert kirimaRR/RDA/07/25/19/SP/GALSuriEla MargayaRR/RDA/07/25/20/SP/GALRoad from Kammale Kadaya Junction to Udumalagala JuunctionRR/RDA/07/26/10KM/05Widening and Development of the road from Angaliya Junction to Akuratiya Hill with culvertsRR/RDA/07/26/10KM/08Development of 700 meters from Baddegama Vanduramba Road near Kola Kids Preschool and 300 meters from Temple Junction towards DolahenaRR/RDA/07/26/10KM/129 Pillar Junction to Mr. Asanka's Shop on Udubattawa Watta Road
+14 more…
Click to filter the awarded table
51.7%
0
On Progress
15 / 29 awarded
On Progress (incl. completed)15
RR/RDA/07/25/06/SP/GALMulana Nagenahira ha Panwila Grama Niladari Wasam Sambandha wana athuru MargayaRR/RDA/07/25/08/SP/GALMahajana Mawatha Magurukaduwa Margaya Elpitiya Pitigala Pradhana Margaye sita Magurukaduwa Awasanaya dakwa Concrete athura Sanwardanaya KirimaRR/RDA/07/25/11/SP/GALElathota Pituwara Margaya Depasa Kanu ha Pathi Bami Yoda Carpet KirimaRR/RDA/07/25/12/SP/GALGalandeniya MargayaRR/RDA/07/25/15/SP/GALDikhena MargayaRR/RDA/07/25/20/SP/GALRoad from Kammale Kadaya Junction to Udumalagala JuunctionRR/RDA/07/25/07Hapugala batuwanthuda Margaya Pivisume sita Roswudwatta Margaye Kelawara Dakwa Margaya (Jala Tankiya Margaya)RR/RDA/07/25/16Mahabodhiwatta sita Pongiliya haraha Vitahna Gedera Ela Dakwa Margaya Ketapathaliya Bokkuwa Athuluwa Bokku Sanwardanaya kara Concrete KirimaRR/RDA/07/25/03Wackwella Palama asala sita aranbe handiya dakwa MargayaRR/RDA/07/25/04Galwehera C.P. the Silva Mawatha Carpet kirimaRR/RDA/07/25/18Agaliya Uthura Tranformaraya Sita Savanna Wella desata Margaya Interlock KirimaRR/RDA/07/25/14Moonugoda RoadRR/RDA/07/25/22Asphalting Meepawala henegewaththa roadRR/RDA/07/25/21Asphalting Newungala Na tree to Bedimeda roadRR/RDA/07/25/01Keselgahahena Pradana Margaya (Kanu Paddathiya Bokku Samaga)
Click to filter the awarded table
13.8%
0
Delay
4 / 29 awarded
Delay4
RR/RDA/07/25/02/SP/GALDelgahabedda-Kirimatiya MargayaRR/RDA/07/25/05/SP/GALAtawalawatta Sri Rewatha Viduhala Idiripita MargayaRR/RDA/07/25/09/SP/GALPanwila Hena Pradhana Margaya Lalith Mahathage Niwasa Asala Sita Manjula Jayaweera Mahathage Niwasa Dakwa MargayaRR/RDA/07/25/19/SP/GALSuriEla Margaya
Click to filter the awarded table
31%
0
Critical Delay
9 / 29 awarded
Critical Delay9
RR/RDA/07/25/17/SP/GALDasa Kadaya Asala sita Jack Fruit Ceylon (Pvt) ayathanaya dakwa Margaya 1 Km carpert kirimaRR/RDA/07/26/10KM/05Widening and Development of the road from Angaliya Junction to Akuratiya Hill with culvertsRR/RDA/07/26/10KM/08Development of 700 meters from Baddegama Vanduramba Road near Kola Kids Preschool and 300 meters from Temple Junction towards DolahenaRR/RDA/07/26/10KM/129 Pillar Junction to Mr. Asanka's Shop on Udubattawa Watta RoadRR/RDA/07/26/10KM/14Kodagoda Thudugala RoadRR/RDA/07/26/10KM/18Expansion of Alikehena Road from Thalawa Junior College to Atakohota borderRR/RDA/07/26/10KM/20Development of Paramount City Road.RR/RDA/07/26/10KM/21Concretisation of Dikhena Welamedda road up to Addunkelle with 2 culverts and side walls on both sides.RR/RDA/07/26/10KM/22Kapalwila Olympus Waththa I.K. Road from Mr. Sunil's house to Rakshana Village Bodhi near Ketagoda Kada.
Click to filter the awarded table
48.3%
0
Completed
14 / 29 awarded
Completed14
RR/RDA/07/25/06/SP/GALMulana Nagenahira ha Panwila Grama Niladari Wasam Sambandha wana athuru MargayaRR/RDA/07/25/08/SP/GALMahajana Mawatha Magurukaduwa Margaya Elpitiya Pitigala Pradhana Margaye sita Magurukaduwa Awasanaya dakwa Concrete athura Sanwardanaya KirimaRR/RDA/07/25/11/SP/GALElathota Pituwara Margaya Depasa Kanu ha Pathi Bami Yoda Carpet KirimaRR/RDA/07/25/12/SP/GALGalandeniya MargayaRR/RDA/07/25/15/SP/GALDikhena MargayaRR/RDA/07/25/20/SP/GALRoad from Kammale Kadaya Junction to Udumalagala JuunctionRR/RDA/07/25/07Hapugala batuwanthuda Margaya Pivisume sita Roswudwatta Margaye Kelawara Dakwa Margaya (Jala Tankiya Margaya)RR/RDA/07/25/16Mahabodhiwatta sita Pongiliya haraha Vitahna Gedera Ela Dakwa Margaya Ketapathaliya Bokkuwa Athuluwa Bokku Sanwardanaya kara Concrete KirimaRR/RDA/07/25/03Wackwella Palama asala sita aranbe handiya dakwa MargayaRR/RDA/07/25/04Galwehera C.P. the Silva Mawatha Carpet kirimaRR/RDA/07/25/18Agaliya Uthura Tranformaraya Sita Savanna Wella desata Margaya Interlock KirimaRR/RDA/07/25/14Moonugoda RoadRR/RDA/07/25/22Asphalting Meepawala henegewaththa roadRR/RDA/07/25/21Asphalting Newungala Na tree to Bedimeda road
Click to filter the awarded table
Portfolio Breakdown · Galle · District
Avg Physical Progress per EE Division · Galle
At-Risk Projects · Galle
- RR/RDA/07/25/02/SP/GALDelgahabedda-Kirimatiya MargayaDelay323 Days in Delay · 93%
- RR/RDA/07/25/05/SP/GALAtawalawatta Sri Rewatha Viduhala Idiripita MargayaDelay323 Days in Delay · 95%
- RR/RDA/07/25/09/SP/GALPanwila Hena Pradhana Margaya Lalith Mahathage Niwasa Asala Sita Manjula Jayaweera Mahathage Niwasa Dakwa MargayaDelay323 Days in Delay · 98%
- RR/RDA/07/25/17/SP/GALDasa Kadaya Asala sita Jack Fruit Ceylon (Pvt) ayathanaya dakwa Margaya 1 Km carpert kirimaDelay323 Days in Delay · 47%
- RR/RDA/07/25/19/SP/GALSuriEla MargayaDelay300 Days in Delay · 96%
Portfolio Timeline· 28 scheduled projects · Galle Toggle
2025-06-21 today2026-12-24
Portfolio · Awarded Works
Awarded Projects
4 projects
Filter awarded works
4 matching projects1 active
| # | Contract No. | Package No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|---|---|
| 1 | RR/RDA/07/25/02/SP/GAL | RR/RDA/07/25/02 | Delgahabedda-Kirimatiya Margaya | 93% | 26,404,581.16 | 50,069,275.91 | Awarded |
| 2 | RR/RDA/07/25/05/SP/GAL | RR/RDA/07/25/05 | Atawalawatta Sri Rewatha Viduhala Idiripita Margaya | 95% | 25,809,376.97 | 45,727,567.86 | Awarded |
| 3 | RR/RDA/07/25/09/SP/GAL | RR/RDA/07/25/09 | Panwila Hena Pradhana Margaya Lalith Mahathage Niwasa Asala Sita Manjula Jayaweera Mahathage Niwasa Dakwa Margaya | 98% | 28,039,359.88 | 42,959,652.18 | Awarded |
| 4 | RR/RDA/07/25/19/SP/GAL | RR/RDA/07/25/19 | SuriEla Margaya | 96% | 14,387,747.00 | 18,573,267.25 | Awarded |
Showing 1–4 of 4
Source: DRRRP • 47 projects • Data updated 2026-11-02 10:30 • 13:36:51 System live • Sri Lanka • 1 districts