Pending—
Planned Fin95.7%
Actual Fin15.2%
Advance & IPC
Advance paid14 proj · 521.2 Mn
IPC paid11 proj · 235.4 Mn
Monitor financial performance across 22 awarded projects
4,976.89 Mn
Total Contract
521.21 Mn
Advance Paid (excl. VAT)
235.44 Mn
IPCs Paid (excl. VAT)
756.65 Mn
Total Paid (excl. VAT)
892.85 Mn
Total Paid (incl. VAT)
— Mn
Advance Pend (incl. VAT)
— Mn
IPCs Pend (incl. VAT)
892.85 Mn
Total (Paid+Pend) (incl. VAT)
Paid incl + Adv Pend incl + IPC Pend incl
15.2%
Financial Progress (excl. VAT)
Total (Paid+Pend) excl / Contract
95%
Planned Financial Progress
Planned share of contract value
Advance payments, IPCs & expenditure per awarded project · 92 projects (filtered from 171)
Filter financial register
92 matching projects1 active
| S/N | Contract No | Contract Name | Contractor | Contract (LKR) | Advance Paid (excl. VAT) | Advance Paid (incl. VAT) | Advance Pend (excl. VAT) | Advance Pend (incl. VAT) | IPCs Paid (excl. VAT) | IPCs Paid (incl. VAT) | IPCs Pend (excl. VAT) | IPCs Pend (incl. VAT) | Overall Expenditure (excl. VAT) | Pending Payments (excl. VAT) | Financial Progress | Financial Progress with Outstanding |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 71 | RDA/DRP/SAB/RAT/EMB/08 | Rehabilitation / Improvement of Pelmadulla - Embilipitiya - Naonagama Road (AA01… | Anura Construction | 259,436,963.35 | 46,754,356.98 | 55,170,141.24 | — | — | — | — | — | — | 46,754,356.98 | — | 55.17Mn Watch21.3% | 55.17Mn 21.3% |
| 72 | RDA/DRP/SAB/RAT/EMB/10 | Rehabilitation / Improvement of Pelmadulla - Embilipitiya - Nonagama Road (AA018… | Kanwel Constructions & Civil Engineering… | 260,776,583.43 | 47,155,924.26 | 55,643,990.62 | — | — | 11,394,017.64 | 13,444,940.82 | — | — | 58,549,941.90 | — | 69.09Mn Watch26.5% | 69.09Mn 26.5% |
| 73 | RDA/DRP/EAS/BAT/BAT/01 | Rehabilitation / Improvement and Surfacing from 56+900 km to 58+300km and from 5… | S S K Construction | 113,074,919.76 | — | — | — | — | 45,270,508.37 | 53,419,199.87 | — | — | 45,270,508.37 | — | 53.42Mn On Track47.2% | 53.42Mn 47.2% |
| 74 | RDA/DRP/SAB/RAT/EMB/05 | Rehabilitation / Improvement of Pelmadulla-Embilipitiya-Nonagama Road (30+000-32… | Anura Construction | 248,600,718.52 | — | — | — | — | — | — | — | — | — | — | — | — |
| 75 | RDA/DRP/SAB/RAT/EMB/06 | Rehabilitation / Improvement of Pelmadulla - Embilipitiya-Nonagama Road (33+500-… | Anura Construction | 237,998,681.32 | — | — | — | — | — | — | — | — | — | — | — | — |
| 76 | RDA/DRP/SAB/RAT/EMB/07 | Rehabilitation / Improvement of Pelmadulla - Embilipitiya-Nonagama Road (37+000-… | Anura Construction | 276,583,785.23 | — | — | — | — | — | — | — | — | — | — | — | — |
| 77 | RDA/DRP/SAB/RAT/EMB/09 | Rehabilitation / Improvement of Pelmadulla - Embilipitiya - Naonagama Road (47+1… | Anura Construction | 269,913,795.48 | — | — | — | — | — | — | — | — | — | — | — | — |
| 78 | RDA/DRP/SAB/RAT/EMB/11 | Rehabilitation / Improvement of Weligepola-Hadagiriya - Kapugala (2+000-11+000) | D K S Construction | 273,586,576.22 | 49,239,013.94 | 58,102,036.46 | — | — | — | — | — | — | 49,239,013.94 | — | 58.10Mn Watch21.2% | 58.10Mn 21.2% |
| 79 | RDA/DRP/WP/COL/COL/07 | Rehabilitation / Improvement of Colombo Hanwella Road (0+370 - 20+400) | INK Engineering | 146,665,907.47 | — | — | — | — | 5,477,974.44 | 6,464,009.84 | — | — | 5,477,974.44 | — | 6.46Mn Behind4.4% | 6.46Mn 4.4% |
| 80 | RDA/DRP/EAS/TRI/TRI/04 | Rehabilitation / Improvement of Town & Gravets Road (B140) (Inner Harbour Road) … | Motec Engineering & Construction | 40,407,339.17 | — | — | — | — | — | — | — | — | — | — | — | — |
| Total | 16,799,029,680.14 | 2,276,780,837.16 | 2,686,401,372.89 | — | — | 905,188,809.07 | 1,068,036,979.06 | 52,935,451.96 | 60,777,795.94 | 3,181,969,646.23 | 52,935,451.96 | 3,754.44Mn 22.3% | 3,815.22Mn 22.7% | |||