DRRRP Awarded Emergency

RDA/DRP/SAB/RAT/RAT/23

Rehabilitation / Improvement Construction of Retaining structures on Thiruwanaketiya Agalawatta Road (B421) (27/7-27/8) (27/8-27-9) (29/2-29/3) and Kalawana Deepdeen Rakwana Road (B181) (7 km)

RatnapuraSabaragamuwa ProvinceRatnapuraDivisional SecretariatAKC ConstructionContractorLKR 52,340,066.90Contract Sum182 daysProject Duration
45%
Complete
Physical Progress45%
Planned Progress92.2%
Time Elapsed79.7%
On Track • 37 days left

Project Timeline

LOA
2026-05-19
Completed
Possession
–
Pending
Commencement
2026-06-12
Completed
Scheduled Completion
2026-12-11
On Track
Anticipated Completion Date
2026-12-11
On Track

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictRatnapura
PD RegionSabaragamuwa Province
CE RegionRatnapura
EE DivisionRatnapura
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement Construction of Retaining structures on Thiruwanaketiya Agalawatta Road (B421) (27/7-27/8) (27/8-27-9) (29/2-29/3) and Kalawana Deepdeen Rakwana Road (B181) (7 km)
Estimated Road Lengths- km
Number of Roads-
Scope Summary4 gabion walls construction
Contractor & Award
Contract No.RDA/DRP/SAB/RAT/RAT/23
Tender Batch No.9
Contractor NameAKC Construction
Consultant-
Tender StatusAwarded
LOA Date2026-05-19
Contract Amount52,340,066.90
Engineer Estimate Amount (LKR)59,067,809.52
Duration (Days)182
CategoryEmergency