Pending—
Planned Fin88.8%
Actual Fin17.9%
Advance & IPC
Advance paid18 proj · 776.9 Mn
IPC paid13 proj · 190.9 Mn
Monitor financial performance across 23 awarded projects
5,411.14 Mn
Total Contract
776.87 Mn
Advance Paid (excl. VAT)
190.93 Mn
IPCs Paid (excl. VAT)
967.80 Mn
Total Paid (excl. VAT)
1,142.00 Mn
Total Paid (incl. VAT)
— Mn
Advance Pend (incl. VAT)
— Mn
IPCs Pend (incl. VAT)
1,142.00 Mn
Total (Paid+Pend) (incl. VAT)
Paid incl + Adv Pend incl + IPC Pend incl
17.9%
Financial Progress (excl. VAT)
Total (Paid+Pend) excl / Contract
89.2%
Planned Financial Progress
Planned share of contract value
Advance payments, IPCs & expenditure per awarded project · 92 projects (filtered from 171)
Filter financial register
92 matching projects1 active
| S/N | Contract No | Contract Name | Contractor | Contract (LKR) | Advance Paid (excl. VAT) | Advance Paid (incl. VAT) | Advance Pend (excl. VAT) | Advance Pend (incl. VAT) | IPCs Paid (excl. VAT) | IPCs Paid (incl. VAT) | IPCs Pend (excl. VAT) | IPCs Pend (incl. VAT) | Overall Expenditure (excl. VAT) | Pending Payments (excl. VAT) | Financial Progress | Financial Progress with Outstanding |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 91 | RDA/DRP/NCP/POL/POL/11 | Rehabilitation / Improvement and Construction of New Drainage on Polonnaruwa-Tha… | A.D.M Construction | 44,474,738.82 | 7,582,108.44 | 8,946,887.96 | — | — | — | — | — | — | 7,582,108.44 | — | 8.95Mn Watch20.1% | 8.95Mn 20.1% |
| 92 | RDA/DRP/SP/GAL/HIN/03 | Rehabilitation / Improvement of Gabbion Walls along Udugama - Hiniduma (9+920-… | Ceylon Construction Industry Development… | 19,453,314.54 | — | — | — | — | — | — | — | — | — | — | — | — |
| Total | 16,799,029,680.14 | 2,276,780,837.16 | 2,686,401,372.89 | — | — | 905,188,809.07 | 1,068,036,979.06 | 52,935,451.96 | 60,777,795.94 | 3,181,969,646.23 | 52,935,451.96 | 3,754.44Mn 22.3% | 3,815.22Mn 22.7% | |||