DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 579 awarded projects

2026-11-04
20:26:42Live2026-11-04
0 / 579Advance Pendingpending advance projects / total projects
0 / 579IPC Pendingpending IPC projects / total projects
0 / 579Advance Paidadvance paid projects / total projects
0 / 579IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Province

579Projects23,829.3Contract Mn
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn1068,082.61,572.919% of contract6,509.7——————51.7%0.0%
Tender Below 50Mn3006,498.82,506.039% of contract3,992.8——————55.3%0.0%
PIU32,119.9—2,119.9——————0.0%0.0%
Tender Total40916,701.34,079.024% of contract12,622.4000.0000.054.0%0.0%
Direct LabourDL Stage 01572,471.61,984.980% of contract486.7——————91.2%0.0%
DL Stage 02431,357.21,059.578% of contract297.8——————67.5%0.0%
DL Stage 0327949.4642.968% of contract306.4——————63.0%0.0%
DL Stage 04432,349.7976.642% of contract1,373.1——————23.3%0.0%
Direct Labour Total1707,127.94,663.965% of contract2,464.0000.0000.063.6%0.0%
—All Provinces57923,829.38,742.837% of contract15,086.4000.0000.056.8%0.0%
Tender Above 50Mn106 projectsTender8,082.6Mn
19% paid1,572.9 Mn
Pending6,509.7Mn
Planned Fin51.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn300 projectsTender6,498.8Mn
39% paid2,506.0 Mn
Pending3,992.8Mn
Planned Fin55.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU3 projectsTender2,119.9Mn
0% paid0.0 Mn
Pending2,119.9Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 0157 projectsDirect Labour2,471.6Mn
80% paid1,984.9 Mn
Pending486.7Mn
Planned Fin91.2%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 0243 projectsDirect Labour1,357.2Mn
78% paid1,059.5 Mn
Pending297.8Mn
Planned Fin67.5%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 0327 projectsDirect Labour949.4Mn
68% paid642.9 Mn
Pending306.4Mn
Planned Fin63.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 0443 projectsDirect Labour2,349.7Mn
42% paid976.6 Mn
Pending1,373.1Mn
Planned Fin23.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
All Provinces579 projects23,829.3Mn
37% paid8,742.8 Mn
Pending15,086.4Mn
Planned Fin56.8%
Actual Fin0.0%

Avg Physical Progress per Province

Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

51–60/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
51RR/RDA/06/25/38/CP/NE
Ketahira Gallella margya palama haraha Udagama dakwa Margaya
NAGMA ENGINEERING (PVT) LTD
38,465,634.79————————————
52RR/RDA/06/25/40/CP/NE
Walapane Samachaithya asalin Arambawana Kurundu oya diyaella dakwa Margaya
UGD Constructions
31,672,222.12————————————
53RR/RDA/06/25/41/CP/NE
Nayapana Gammada tharapara sanwardhanaya
Central Engineering Services Pvt Ltd. (C…
51,754,603.52————————————
54RR/RDA/06/25/42/CP/NE
AC Overlaying from Polpitiya Junction to 04th Mile Post (CH 3+700 – 8+700 km)
UKS Lanka Engineering Pvt Ltd.
220,116,957.84————————————
55—
Carpeting of road from Bambaragama Moragollahinna to Karamidula
Ajith Construction
61,551,869.38————————————
56—
Carpeting of Mahathenna to Hapugasdeniya Main Road
Ajith Construction
68,070,000.00————————————
57RR/RDA/16/25/04/AKK/AMP
Pokunugama near Mr. Dinesh Tharaga House to Road (From Pokunugama Pre School to …
Harischandra Idikirim
6,435,000.00————————————
58RR/RDA/16/25/01/AKK/AMP
Samanalathenna- Road from House No.63 To the Monastery Muwagammana -From First L…
Vithu Construction
21,336,681.87————————————
59RR/RDA/16/25/03/AKK/AMP
Polbedda Junction to Galwalayaya Road
MOTEC Engineering & Construction
17,506,335.00————————————
60RR/RDA/SP/16/25/01/AKK/AMP
Rectification and Asphalt Surfacing on Ambahagawela -Namaloya Main Road
SMA Careem Engineering Consultancy Servi…
222,189,859.13————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 51–60 of 579 projects · page 6/58