14:22:38Live2026-11-04
0 / 15Advance Pendingpending advance projects / total projects
0 / 15IPC Pendingpending IPC projects / total projects
0 / 15Advance Paidadvance paid projects / total projects
0 / 15IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · EE: Puttalam · EE Office

567Projects20,718.2Contract Mn
Puttalam 15 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn3131.47.96% of contract123.5——————66.7%0.0%
Tender Below 50Mn9201.075.738% of contract125.3——————100.0%0.0%
DL Stage 01123.526.7114% of contract-3.2——————100.0%0.0%
DL Stage 02133.234.9105% of contract-1.7——————0.0%0.0%
DL Stage 0300.0——————————
DL Stage 04110.48.683% of contract1.7——————0.0%0.0%
Puttalam15399.5153.839% of contract245.7000.0000.080.0%0.0%
Tender Above 50Mn3 projects131.4Mn
6% paid7.9 Mn
Pending123.5Mn
Planned Fin66.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn9 projects201.0Mn
38% paid75.7 Mn
Pending125.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project23.5Mn
114% paid26.7 Mn
Pending—
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project33.2Mn
105% paid34.9 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 030 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 041 project10.4Mn
83% paid8.6 Mn
Pending1.7Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Puttalam15 projects399.5Mn
39% paid153.8 Mn
Pending245.7Mn
Planned Fin80.0%
Actual Fin0.0%

Avg Physical Progress per Province · EE: Puttalam

Project-wise Financials · EE: Puttalam (579 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · EE: Puttalam (Mn · incl. VAT)

Scroll horizontally — 579 projects

Puttalam Division · EE: Puttalam (Mn · incl. VAT)

Puttalam District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:15 awarded · EE: Puttalam
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

1–10/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
1RR/RDA/04/25/13/CP/KY
Gonaala Pasala Asala Sita Kubukkadura Athuru Margayak Wana Gurumada Margaya
Dharshana Construction
35,195,820.00————————————
2RR/RDA/04/25/15/CP/KY
Madolkale sita Huluganga dakwa yana athuru margaye Bandaranayakapura gam kotasat…
UGD Constructions
12,711,509.59————————————
3—
Palawa ihala meda Wijitha mawatha Waliyangadeniya margaya yakarana athuru Margay…
Galahitiyawa Builders
12,240,493.10————————————
4RR/RDA/04/25/17/CP/KY
Nuganga Margaya
Weebedda Construction
9,650,635.50————————————
5RR/RDA/04/25/19/CP/KY
Mulgama viduhala Asala sita lewalan dakwa
The Wise Lanka Construction Company (Pvt…
25,917,512.50————————————
6RR/RDA/04/25/20/CP/KY
Carpeting road Ratemulla to Wendesiwaththa End
Wiscon (Pvt) Ltd
36,995,817.10————————————
7RR/RDA/04/25/21/CP/KY
Galaha group sita finas kotasa Pahalagama-Ihalagama haraha nawa rohala dakwa Mar…
UGD Constructions
22,711,029.00————————————
8RR/RDA/04/25/22/CP/KY
Rambukwella viharasthanaya asala sita Dodamgolla Rambukwella nagenhira haraha Ud…
The Wise Lanka Construction Company (Pvt…
15,056,107.00————————————
9RR/RDA/04/25/23/CP/KY
Minuwangamuwa gammada margaye Aberathne mahathage niwasa asala sita Abesinha Ban…
The Wise Lanka Construction Company (Pvt…
27,734,432.55————————————
10RR/RDA/04/25/24/CP/KY
Galamuduna gamata pivisena Margaya
NAGMA ENGINEERING (PVT) LTD
157,638,978.90————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 1–10 of 579 projects · page 1/58