DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 59 awarded projects

2026-11-05
21:42:39Live2026-11-05
0 / 59Advance Pendingpending advance projects / total projects
0 / 59IPC Pendingpending IPC projects / total projects
0 / 59Advance Paidadvance paid projects / total projects
0 / 59IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

0%

0%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

62.6%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · North Western Province · Province

579Projects23,829.3Contract Mn
North Western Province 59 projects Open filtered view
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn13690.693.113% of contract597.5——————84.6%0.0%
Tender Below 50Mn24529.0229.043% of contract300.0——————100.0%0.0%
PIU00.0——————————
Tender Total371,219.6322.126% of contract897.5000.0000.094.6%0.0%
Direct LabourDL Stage 016445.0385.387% of contract59.7——————83.3%0.0%
DL Stage 027264.3212.580% of contract51.7——————42.9%0.0%
DL Stage 03125.217.971% of contract7.4——————0.0%0.0%
DL Stage 048247.8169.268% of contract78.6——————0.0%0.0%
Direct Labour Total22982.3784.980% of contract197.4000.0000.036.4%0.0%
—North Western Province592,201.91,107.050% of contract1,094.9000.0000.072.9%0.0%
Tender Above 50Mn13 projectsTender690.6Mn
13% paid93.1 Mn
Pending597.5Mn
Planned Fin84.6%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn24 projectsTender529.0Mn
43% paid229.0 Mn
Pending300.0Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projectsTender0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 016 projectsDirect Labour445.0Mn
87% paid385.3 Mn
Pending59.7Mn
Planned Fin83.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 027 projectsDirect Labour264.3Mn
80% paid212.5 Mn
Pending51.7Mn
Planned Fin42.9%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 projectDirect Labour25.2Mn
71% paid17.9 Mn
Pending7.4Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 048 projectsDirect Labour247.8Mn
68% paid169.2 Mn
Pending78.6Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
North Western Province59 projects2,201.9Mn
50% paid1,107.0 Mn
Pending1,094.9Mn
Planned Fin72.9%
Actual Fin0.0%

Avg Physical Progress per Province · North Western Province

Graphs reflect current view:59 awarded · North Western Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

351–360/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
351RR/RDA/25/08/12/SP/MTR
Nawalahena Palamu Para Sanwardanaya Kirima (Jagath Mahathage Niwasa asala sita K…
Rathnayake Construction
5,399,259.80————————————
352RR/RDA/08/25/13/SP/MTR
Heelakanda Kanishta Vidyalaya asala sita Budu Medura Dakwa margaya Sanwardanaya …
Madurapperuma Construction & Supply
8,331,854.95————————————
353RR/RDA/08/25/14/SP/MTR
Kanaththewatta kade asala sita Mulana Ela Margaya Dakwa Sanwardanaya Kirima (Pet…
Madurapperuma Construction & Supply
12,885,039.94————————————
354RR/RDA/08/25/15/SP/MTR
Pasal Mawathe Weerathunga Petti Bokkuwa Asala Sita Iriyagaha Mulana Bokkuwa Dakw…
Madurapperuma Construction & Supply
20,214,236.58————————————
355RR/RDA/08/25/16/SP/MTR
Walgama Saddathissa Mawathe Primesity Niwasa Sankeernaye Prawesha Margaya Kapat …
Jagath construction
7,623,062.15————————————
356RR/RDA/08/25/18/SP/MTR
Dekatukella Margaya Pethibemma sahithawa Sanwardanaya kirima
Dashodhaya (Pvt)Ltd
4,080,866.90————————————
357RR/RDA/08/25/19/SP/MTR
Sahakara wathu Adikari nila niwasa asala sita koppara weediya pittaniya dakwa ma…
Gamage Builders
10,371,473.20————————————
358RR/RDA/08/25/20/SP/MTR
Naymbala kendawala haraha wellethota margaye wedugoda sthanaye pethi bemma sahit…
Rathnayake Construction
3,502,675.00————————————
359—
Development of the road by laying Asphalt starting from near Saddhatissa Junior …
GEL Construction
135,290,000.00————————————
360—
Development of the Pathegama Temple Road (Massalatiya Road) by carpeting
GEL Construction
81,100,000.00————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 351–360 of 579 projects · page 36/58