DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 15 awarded projects

2026-11-05
19:53:56Live2026-11-05
0 / 15Advance Pendingpending advance projects / total projects
0 / 15IPC Pendingpending IPC projects / total projects
0 / 15Advance Paidadvance paid projects / total projects
0 / 15IPCs PaidIPC paid projects / total projects
228.8 Mn

228.77 Mn

Total Contract

0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

0%

0%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

79.2%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · Matara · EE: Matara · EE Office

18Projects328.4Contract Mn
Matara 15 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Below 50Mn9118.5101.185% of contract17.4——————100.0%0.0%
DL Stage 01129.016.156% of contract12.9——————100.0%0.0%
DL Stage 02226.421.883% of contract4.6——————100.0%0.0%
DL Stage 0317.23.650% of contract3.6——————100.0%0.0%
DL Stage 04247.624.551% of contract23.1——————0.0%0.0%
Matara15228.8167.173% of contract61.7000.0000.086.7%0.0%
Tender Below 50Mn9 projects118.5Mn
85% paid101.1 Mn
Pending17.4Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project29.0Mn
56% paid16.1 Mn
Pending12.9Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 022 projects26.4Mn
83% paid21.8 Mn
Pending4.6Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 project7.2Mn
50% paid3.6 Mn
Pending3.6Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 042 projects47.6Mn
51% paid24.5 Mn
Pending23.1Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Matara15 projects228.8Mn
73% paid167.1 Mn
Pending61.7Mn
Planned Fin86.7%
Actual Fin0.0%

Avg Physical Progress per Province · Matara · EE: Matara

Project-wise Financials · Matara · EE: Matara (579 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · Matara · EE: Matara (Mn · incl. VAT)

Scroll horizontally — 579 projects

Matara Division · Matara · EE: Matara (Mn · incl. VAT)

Matara District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:15 awarded · Matara · EE: Matara
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

281–290/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
281RR/RDA/11/25/19/NP/MNR
Chilawathurai Maiyavadi Road
Abdul Cader Constructions
22,899,536.00————————————
282RR/RDA/11/25/20/NP/MNR
Kondachchi to Pasithenral Road
Abdul Cader Constructions
18,513,473.00————————————
283RR/RDA/11/25/22/NP/MNR
School back side road
Sintha Construction (Pvt) Ltd
17,295,437.50————————————
284RR/RDA/11/25/23/NP/MNR
Palakaimunai Beach Road
Sun Constructions (Pvt) Ltd.
111,500,000.00————————————
285RR/RDA/11/25/24/NP/MNR
Murukan Kovil Main Road
Abdul Cader Constructions
36,558,775.00————————————
286—
Pallavarayankaddu Junction - Kiranchi - Ponnaveli Road
Nimna Holdings (Pvt) Ltd
206,440,000.00————————————
287RR/RDA/14/25/06/NP/KLN
Skanthapuram Kannan Temple road
Sun Constructions (Pvt) Ltd.
138,750,000.00————————————
288RR/RDA/14/25/07/NP/KLN
Mayilvakanapuram kolunthupulavu road
RR Construction (Pvt) Ltd.
224,197,154.05————————————
289RR/RDA/14/25/08/NP/KLN
Kalmadu 7th unit 3rd lane
Kanola Constructions & Engineering (Pvt)…
58,116,410.00————————————
290RR/RDA/14/25/09/NP/KLN
Neliyai Amman kovil road
Kanola Constructions & Engineering (Pvt)…
113,238,042.50————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 281–290 of 579 projects · page 29/58