Pending207.2Mn
Planned Fin85.3%
Actual Fin15.3%
Advance & IPC
Advance paid83 proj · 2,738.9 Mn
IPC paid62 proj · 1,049.9 Mn

Monitor financial performance across 12 awarded projects
1,941.61 Mn
Total Contract
66.85 Mn
Advance Paid (excl. VAT)
64.70 Mn
IPCs Paid (excl. VAT)
131.55 Mn
Total Paid (excl. VAT)
155.22 Mn
Total Paid (incl. VAT)
133.60 Mn
Advance Pend (incl. VAT)
— Mn
IPCs Pend (incl. VAT)
288.82 Mn
Total (Paid+Pend) (incl. VAT)
Paid incl + Adv Pend incl + IPC Pend incl
12.6%
Financial Progress (excl. VAT)
Total (Paid+Pend) excl / Contract
69.5%
Planned Financial Progress
Planned share of contract value
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 144 | 24,785.9 | 4,470.518% of contract | 207.2 | 86 | 83 | 2,738.9 | 125 | 62 | 1,049.9 | 85.3% | 15.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| All Provinces | 144 | 24,785.9 | 4,470.518% of contract | 207.2 | 86 | 83 | 2,738.9 | 125 | 62 | 1,049.9 | 85.3% | 15.3% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 32 | 7,417.7 | 1,441.219% of contract | — | 22 | 22 | 854.4 | 48 | 19 | 367.2 | 92.2% | 16.5% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Sabaragamuwa Province | 32 | 7,417.7 | 1,441.219% of contract | 0.0 | 22 | 22 | 854.4 | 48 | 19 | 367.2 | 92.2% | 16.5% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 25 | 5,571.5 | 1,201.222% of contract | — | 20 | 20 | 804.9 | 23 | 15 | 213.0 | 89.7% | 18.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Uva Province | 25 | 5,571.5 | 1,201.222% of contract | 0.0 | 20 | 20 | 804.9 | 23 | 15 | 213.0 | 89.7% | 18.3% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 31 | 4,646.7 | 969.921% of contract | 73.6 | 19 | 19 | 566.4 | 32 | 13 | 255.6 | 74.4% | 17.7% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Central Province | 31 | 4,646.7 | 969.921% of contract | 73.6 | 19 | 19 | 566.4 | 32 | 13 | 255.6 | 74.4% | 17.7% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 16 | 2,880.4 | 449.216% of contract | — | 11 | 11 | 324.6 | 10 | 6 | 56.1 | 100.0% | 13.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Western Province | 16 | 2,880.4 | 449.216% of contract | 0.0 | 11 | 11 | 324.6 | 10 | 6 | 56.1 | 100.0% | 13.2% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 12 | 1,941.6 | 155.28% of contract | 133.6 | 6 | 3 | 66.8 | 5 | 3 | 64.7 | 70.4% | 6.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| North Western Province | 12 | 1,941.6 | 155.28% of contract | 133.6 | 6 | 3 | 66.8 | 5 | 3 | 64.7 | 70.4% | 6.8% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 9 | 852.8 | 95.511% of contract | — | 2 | 2 | 20.5 | 3 | 2 | 60.5 | 86.6% | 9.5% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Eastern Province | 9 | 852.8 | 95.511% of contract | 0.0 | 2 | 2 | 20.5 | 3 | 2 | 60.5 | 86.6% | 9.5% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 11 | 846.2 | 158.219% of contract | — | 6 | 6 | 101.2 | 4 | 4 | 32.8 | 98.2% | 15.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| North Central Province | 11 | 846.2 | 158.219% of contract | 0.0 | 6 | 6 | 101.2 | 4 | 4 | 32.8 | 98.2% | 15.8% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 600.5 | — | — | — | — | — | — | — | — | 46.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Northern Province | 6 | 600.5 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 46.5% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 28.4 | — | — | — | — | — | — | — | — | 100.0% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Southern Province | 2 | 28.4 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 100.0% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 144 | 24,785.9 | 4,470.518% of contract | 207.2 | 86 | 83 | 2,738.9 | 125 | 62 | 1,049.9 | 85.3% | 15.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| All Districts | 144 | 24,785.9 | 4,470.518% of contract | 207.2 | 86 | 83 | 2,738.9 | 125 | 62 | 1,049.9 | 85.3% | 15.3% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 12 | 1,520.3 | 329.622% of contract | 33.9 | 6 | 6 | 184.4 | 13 | 5 | 95.0 | 62.3% | 18.4% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kandy | 12 | 1,520.3 | 329.622% of contract | 33.9 | 6 | 6 | 184.4 | 13 | 5 | 95.0 | 62.3% | 18.4% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 9 | 1,458.1 | 292.420% of contract | 20.2 | 6 | 6 | 187.7 | 8 | 4 | 60.1 | 73.9% | 17.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Matale | 9 | 1,458.1 | 292.420% of contract | 20.2 | 6 | 6 | 187.7 | 8 | 4 | 60.1 | 73.9% | 17.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 10 | 1,668.3 | 347.921% of contract | 19.5 | 7 | 7 | 194.3 | 11 | 4 | 100.5 | 89.4% | 17.7% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nuwara Eliya | 10 | 1,668.3 | 347.921% of contract | 19.5 | 7 | 7 | 194.3 | 11 | 4 | 100.5 | 89.4% | 17.7% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 395.9 | 24.26% of contract | — | 2 | 2 | 20.5 | — | — | — | 94.8% | 5.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Ampara | 3 | 395.9 | 24.26% of contract | 0.0 | 2 | 2 | 20.5 | 0 | 0 | 0.0 | 94.8% | 5.2% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 113.1 | 53.447% of contract | — | — | — | — | 2 | 1 | 45.3 | 100.0% | 40.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Batticaloa | 1 | 113.1 | 53.447% of contract | 0.0 | 0 | 0 | 0.0 | 2 | 1 | 45.3 | 100.0% | 40.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 5 | 343.9 | 17.95% of contract | — | — | — | — | 1 | 1 | 15.2 | 79.1% | 4.4% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Trincomalee | 5 | 343.9 | 17.95% of contract | 0.0 | 0 | 0 | 0.0 | 1 | 1 | 15.2 | 79.1% | 4.4% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 610.8 | 93.515% of contract | — | 3 | 3 | 73.1 | 1 | 1 | 6.2 | 96.7% | 13.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Anuradhapura | 6 | 610.8 | 93.515% of contract | 0.0 | 3 | 3 | 73.1 | 1 | 1 | 6.2 | 96.7% | 13.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 5 | 235.4 | 64.727% of contract | — | 3 | 3 | 28.1 | 3 | 3 | 26.7 | 100.0% | 23.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Polonnaruwa | 5 | 235.4 | 64.727% of contract | 0.0 | 3 | 3 | 28.1 | 3 | 3 | 26.7 | 100.0% | 23.3% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 843.3 | 64.88% of contract | 38.9 | 3 | 2 | 43.6 | 3 | 1 | 11.4 | 65.1% | 6.5% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kurunegala | 6 | 843.3 | 64.88% of contract | 38.9 | 3 | 2 | 43.6 | 3 | 1 | 11.4 | 65.1% | 6.5% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Puttalam | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 359.7 | — | — | — | — | — | — | — | — | 2.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Jaffna | 2 | 359.7 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 2.2% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 62.2 | — | — | — | — | — | — | — | — | 68.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kilinochchi | 1 | 62.2 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 68.2% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 98.5 | — | — | — | — | — | — | — | — | 62.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Mannar | 1 | 98.5 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 62.5% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 37.3 | — | — | — | — | — | — | — | — | 81.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Mullaitivu | 1 | 37.3 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 81.5% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 42.8 | — | — | — | — | — | — | — | — | 62.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Vavuniya | 1 | 42.8 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 62.5% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 10 | 2,440.9 | 548.422% of contract | — | 8 | 8 | 333.2 | 18 | 8 | 131.7 | 84.5% | 19.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kegalle | 10 | 2,440.9 | 548.422% of contract | 0.0 | 8 | 8 | 333.2 | 18 | 8 | 131.7 | 84.5% | 19.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 22 | 4,976.9 | 892.818% of contract | — | 14 | 14 | 521.2 | 30 | 11 | 235.4 | 95.7% | 15.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Ratnapura | 22 | 4,976.9 | 892.818% of contract | 0.0 | 14 | 14 | 521.2 | 30 | 11 | 235.4 | 95.7% | 15.2% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 28.4 | — | — | — | — | — | — | — | — | 100.0% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Galle | 2 | 28.4 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 100.0% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 23 | 5,411.1 | 1,142.021% of contract | — | 18 | 18 | 776.9 | 19 | 13 | 190.9 | 88.8% | 17.9% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Badulla | 23 | 5,411.1 | 1,142.021% of contract | 0.0 | 18 | 18 | 776.9 | 19 | 13 | 190.9 | 88.8% | 17.9% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 160.3 | 59.237% of contract | — | 2 | 2 | 28.0 | 4 | 2 | 22.1 | 100.0% | 31.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Monaragala | 2 | 160.3 | 59.237% of contract | 0.0 | 2 | 2 | 28.0 | 4 | 2 | 22.1 | 100.0% | 31.3% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,433.0 | 196.214% of contract | — | 5 | 5 | 110.1 | 10 | 6 | 56.1 | 100.0% | 11.6% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Colombo | 8 | 1,433.0 | 196.214% of contract | 0.0 | 5 | 5 | 110.1 | 10 | 6 | 56.1 | 100.0% | 11.6% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,447.4 | 253.117% of contract | — | 6 | 6 | 214.5 | — | — | — | 100.0% | 14.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Gampaha | 8 | 1,447.4 | 253.117% of contract | 0.0 | 6 | 6 | 214.5 | 0 | 0 | 0.0 | 100.0% | 14.8% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 31 | 4,646.7 | 969.921% of contract | 73.6 | 19 | 19 | 566.4 | 32 | 13 | 255.6 | 74.4% | 17.7% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| All Consultants | 31 | 4,646.7 | 969.921% of contract | 73.6 | 19 | 19 | 566.4 | 32 | 13 | 255.6 | 74.4% | 17.7% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 15 | 2,082.2 | 381.018% of contract | 43.8 | 7 | 7 | 213.4 | 15 | 6 | 109.6 | 61.9% | 15.5% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Team Leader | 15 | 2,082.2 | 381.018% of contract | 43.8 | 7 | 7 | 213.4 | 15 | 6 | 109.6 | 61.9% | 15.5% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 5 | 1,281.7 | 272.221% of contract | 17.2 | 4 | 4 | 177.7 | 5 | 2 | 52.9 | 76.3% | 18.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Matale EE | 5 | 1,281.7 | 272.221% of contract | 17.2 | 4 | 4 | 177.7 | 5 | 2 | 52.9 | 76.3% | 18.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 4 | 753.2 | 253.234% of contract | 9.7 | 3 | 3 | 128.7 | 9 | 3 | 85.9 | 100.0% | 28.5% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nuwara Eliya EE | 4 | 753.2 | 253.234% of contract | 9.7 | 3 | 3 | 128.7 | 9 | 3 | 85.9 | 100.0% | 28.5% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 369.1 | 34.09% of contract | — | 2 | 2 | 28.9 | — | — | — | 96.0% | 7.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Norwood EE | 3 | 369.1 | 34.09% of contract | 0.0 | 2 | 2 | 28.9 | 0 | 0 | 0.0 | 96.0% | 7.8% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 112.6 | 20.218% of contract | 2.9 | 2 | 2 | 10.0 | 3 | 2 | 7.1 | 69.5% | 15.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nalanda EE | 3 | 112.6 | 20.218% of contract | 2.9 | 2 | 2 | 10.0 | 3 | 2 | 7.1 | 69.5% | 15.2% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 47.8 | 9.219% of contract | — | 1 | 1 | 7.8 | — | — | — | 100.0% | 16.4% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Hanguranketha EE | 1 | 47.8 | 9.219% of contract | 0.0 | 1 | 1 | 7.8 | 0 | 0 | 0.0 | 100.0% | 16.4% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 129 | 22,610.7 | 4,184.219% of contract | 207.2 | 81 | 78 | 2,556.7 | 122 | 60 | 989.5 | 85.7% | 15.7% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| All EE Offices | 129 | 22,610.7 | 4,184.219% of contract | 207.2 | 81 | 78 | 2,556.7 | 122 | 60 | 989.5 | 85.7% | 15.7% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 22 | 4,976.9 | 892.818% of contract | — | 14 | 14 | 521.2 | 30 | 11 | 235.4 | 95.7% | 15.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Ratnapura | 22 | 4,976.9 | 892.818% of contract | 0.0 | 14 | 14 | 521.2 | 30 | 11 | 235.4 | 95.7% | 15.2% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 19 | 4,275.2 | 951.322% of contract | — | 15 | 15 | 615.2 | 19 | 13 | 190.9 | 92.4% | 18.9% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Badulla | 19 | 4,275.2 | 951.322% of contract | 0.0 | 15 | 15 | 615.2 | 19 | 13 | 190.9 | 92.4% | 18.9% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 10 | 2,440.9 | 548.422% of contract | — | 8 | 8 | 333.2 | 18 | 8 | 131.7 | 84.5% | 19.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kegalle | 10 | 2,440.9 | 548.422% of contract | 0.0 | 8 | 8 | 333.2 | 18 | 8 | 131.7 | 84.5% | 19.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,447.4 | 253.117% of contract | — | 6 | 6 | 214.5 | — | — | — | 100.0% | 14.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Gampaha | 8 | 1,447.4 | 253.117% of contract | 0.0 | 6 | 6 | 214.5 | 0 | 0 | 0.0 | 100.0% | 14.8% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,433.0 | 196.214% of contract | — | 5 | 5 | 110.1 | 10 | 6 | 56.1 | 100.0% | 11.6% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Colombo | 8 | 1,433.0 | 196.214% of contract | 0.0 | 5 | 5 | 110.1 | 10 | 6 | 56.1 | 100.0% | 11.6% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,345.4 | 272.220% of contract | 17.2 | 4 | 4 | 177.7 | 5 | 2 | 52.9 | 76.2% | 17.1% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Matale | 6 | 1,345.4 | 272.220% of contract | 17.2 | 4 | 4 | 177.7 | 5 | 2 | 52.9 | 76.2% | 17.1% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,251.4 | 304.624% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 84.3% | 20.6% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nuwara Eliya | 6 | 1,251.4 | 304.624% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 84.3% | 20.6% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,105.1 | 271.425% of contract | 33.9 | 5 | 5 | 151.1 | 9 | 4 | 79.0 | 73.7% | 20.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kundasale | 8 | 1,105.1 | 271.425% of contract | 33.9 | 5 | 5 | 151.1 | 9 | 4 | 79.0 | 73.7% | 20.8% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Chilaw | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 5 | 768.2 | 64.88% of contract | 38.9 | 3 | 2 | 43.6 | 3 | 1 | 11.4 | 72.5% | 7.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kurunegala | 5 | 768.2 | 64.88% of contract | 38.9 | 3 | 2 | 43.6 | 3 | 1 | 11.4 | 72.5% | 7.2% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 610.8 | 93.515% of contract | — | 3 | 3 | 73.1 | 1 | 1 | 6.2 | 96.7% | 13.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Anuradhapura | 6 | 610.8 | 93.515% of contract | 0.0 | 3 | 3 | 73.1 | 1 | 1 | 6.2 | 96.7% | 13.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 369.1 | 34.09% of contract | — | 2 | 2 | 28.9 | — | — | — | 96.0% | 7.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Norwood | 3 | 369.1 | 34.09% of contract | 0.0 | 2 | 2 | 28.9 | 0 | 0 | 0.0 | 96.0% | 7.8% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 359.7 | — | — | — | — | — | — | — | — | 2.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Jaffna | 2 | 359.7 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 2.2% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 5 | 235.4 | 64.727% of contract | — | 3 | 3 | 28.1 | 3 | 3 | 26.7 | 100.0% | 23.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Polonnaruwa | 5 | 235.4 | 64.727% of contract | 0.0 | 3 | 3 | 28.1 | 3 | 3 | 26.7 | 100.0% | 23.3% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 221.8 | — | — | — | — | — | — | — | — | 19.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kandy | 3 | 221.8 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 19.2% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 193.4 | 58.230% of contract | — | 1 | 1 | 33.3 | 4 | 1 | 16.0 | 100.0% | 25.5% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kadugannawa | 1 | 193.4 | 58.230% of contract | 0.0 | 1 | 1 | 33.3 | 4 | 1 | 16.0 | 100.0% | 25.5% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 160.3 | 59.237% of contract | — | 2 | 2 | 28.0 | 4 | 2 | 22.1 | 100.0% | 31.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Monaragala | 2 | 160.3 | 59.237% of contract | 0.0 | 2 | 2 | 28.0 | 4 | 2 | 22.1 | 100.0% | 31.3% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 112.6 | 20.218% of contract | 2.9 | 2 | 2 | 10.0 | 3 | 2 | 7.1 | 69.5% | 15.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nalanda | 3 | 112.6 | 20.218% of contract | 2.9 | 2 | 2 | 10.0 | 3 | 2 | 7.1 | 69.5% | 15.2% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 49.2 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Trincomalee | 1 | 49.2 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 0.0% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 47.8 | 9.219% of contract | — | 1 | 1 | 7.8 | — | — | — | 100.0% | 16.4% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Hanguranketha | 1 | 47.8 | 9.219% of contract | 0.0 | 1 | 1 | 7.8 | 0 | 0 | 0.0 | 100.0% | 16.4% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 42.8 | — | — | — | — | — | — | — | — | 62.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Vavuniya | 1 | 42.8 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 62.5% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 37.3 | — | — | — | — | — | — | — | — | 81.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Mullaitivu | 1 | 37.3 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 81.5% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 28.4 | — | — | — | — | — | — | — | — | 100.0% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Galle | 2 | 28.4 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 100.0% | 0.0% |
Advance payments, IPCs & expenditure per awarded project · 171 projects
Filter financial register
171 matching projects
| S/N | Contract No | Contract Name | Contractor | Contract (LKR) | Advance Paid (excl. VAT) | Advance Paid (incl. VAT) | Advance Pend (excl. VAT) | Advance Pend (incl. VAT) | IPCs Paid (excl. VAT) | IPCs Paid (incl. VAT) | IPCs Pend (excl. VAT) | IPCs Pend (incl. VAT) | Overall Expenditure (excl. VAT) | Pending Payments (excl. VAT) | Financial Progress | Financial Progress with Outstanding |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | RDA/DRP/CEN/KDY/KAD/11 | Rehabilitation / Improvement of Nawalapitiya - Dolosbage Road ( B -318) ( 10+50… | Tiasa Construction (Pvt) Ltd | 193,404,194.96 | 33,346,525.54 | 39,348,900.14 | — | — | 15,954,390.29 | 18,826,180.55 | — | — | 49,300,915.83 | — | 58.18Mn Watch30.1% | 58.18Mn 30.1% |
| 2 | RDA/DRP/CEN/KDY/KAN/14 | Rehabilitation /Improvement of Katugasthota Medawala road ( B 0206)( 0 + 000 - … | Alucon Industries (Pvt) Ltd | 74,836,014.77 | — | — | — | — | — | — | — | — | — | — | — | — |
| 3 | RDA/DRP/CEN/KDY/KDY/15 | Rehabilitation / Improvement of Galagedara Rambukkana ( B 122) ( 0+000 - 18+000) | Jayawansa Construction (Pvt) Ltd | 79,071,437.68 | — | — | — | — | — | — | — | — | — | — | — | — |
| 4 | RDA/DRP/CEN/KDY/KDY/19 | Rehabilitation / Improvement of Poojapitiya Alawathugoda road ( B 377) ( 0+000 -… | Jayawansa Construction (Pvt) Ltd | 67,935,586.77 | — | — | — | — | — | — | — | — | — | — | — | — |
| 5 | RDA/DRP/CEN/KDY/KUN/20 | Rehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuw… | Samindra Construction | 31,558,227.98 | — | — | — | — | — | — | — | — | — | — | — | — |
| 6 | RDA/DRP/CEN/KDY/KUN/21 | Improvement of Pitiyegedara-Waththegama-Iriyagasthenna Road (0+000-5+400) | Jayasinghe Construction (Pvt) Ltd | 257,721,453.96 | 46,231,491.42 | 54,553,159.88 | — | — | — | — | 8,483,606.80 | 10,010,656.02 | 46,231,491.42 | 8,483,606.80 | 54.55Mn Watch21.2% | 64.56Mn 25.1% |
| 7 | RDA/DRP/CEN/KDY/KUN/22 | Improvement to Damaged Road Section on Weeragantota - Randenigala Road. (From CH… | SD Civil Construction (Pvt) Ltd | 224,968,435.78 | 40,192,882.63 | 47,427,601.50 | — | — | 34,738,972.19 | 40,991,987.18 | — | — | 74,931,854.82 | — | 88.42Mn Watch39.3% | 88.42Mn 39.3% |
| 8 | RDA/DRP/CEN/KDY/KUN/24R | Rehabilitation / Improvement of Flood damage on Katugastota - Madawala - Bambere… | Nimsara Construction & Engineering (Pvt)… | 79,507,501.11 | — | — | — | — | — | — | — | — | — | — | — | — |
| 9 | RDA/DRP/CEN/KDY/KUN/25 | Construction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LH… | S N O Builders (Pvt) Ltd | 157,909,825.01 | 28,346,587.80 | 33,448,973.60 | — | — | 25,922,264.54 | 30,502,481.38 | 10,705,591.47 | 11,041,226.83 | 54,268,852.34 | 10,705,591.47 | 63.95Mn On Track40.5% | 74.99Mn 47.5% |
| 10 | RDA/DRP/CEN/KDY/KUN/26R | Improvement to Structures on Kandy - Jaffna Road 11+700 - 11+850 | SD Civil Construction (Pvt) Ltd | 148,430,322.65 | — | — | — | — | — | — | — | — | — | — | — | — |
| Total | 34,005,299,486.17 | 2,738,852,403.05 | 3,231,645,820.60 | 113,218,826.01 | 133,598,214.69 | 1,049,943,508.60 | 1,238,847,524.51 | 63,842,351.18 | 73,647,937.02 | 3,788,795,911.65 | 177,061,177.19 | 4,470.49Mn 13.1% | 4,677.74Mn 13.8% | |||