DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 15 awarded projects

2026-11-04
16:34:56Live2026-11-04
0 / 15Advance Pendingpending advance projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

Portfolio Breakdown — Financial (Exclusive Vat) · Emergency · Team Leader · Consultant

31Projects4,646.7Contract Mn
Reset
Team Leader 15 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency152,082.2381.018% of contract43.877213.4156109.661.9%15.5%
DC - Roads00.0——————————
DC - Slope00.0——————————
PD(CP) - Slope00.0——————————
Team Leader152,082.2381.018% of contract43.877213.4156109.661.9%15.5%
Emergency15 projects2,082.2Mn
18% paid381.0 Mn
Pending43.8Mn
Planned Fin61.9%
Actual Fin15.5%
Advance & IPC
Advance paid7 proj · 213.4 Mn
IPC paid6 proj · 109.6 Mn
Open filtered view
DC - Roads0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Team Leader15 projects2,082.2Mn
18% paid381.0 Mn
Pending43.8Mn
Planned Fin61.9%
Actual Fin15.5%

Avg Physical Progress per Province · Emergency · Team Leader

Project-wise Financials · Emergency · Team Leader (171 Projects)

Clear

Project-wise Contract Value vs. Expenditure and Pending Payments · Emergency · Team Leader (Mn · incl. VAT)

Scroll horizontally — 171 projects

Team Leader · Emergency · Team Leader (Mn · incl. VAT)

Kandy District Summary (Mn · incl. VAT)

District baseline — overall Emergency (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:15 awarded · Emergency · Team Leader
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 171 projects

11–20/171

Filter financial register

171 matching projects

S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
11RDA/DRP/CEN/KDY/KUN/27
Improvement to Structures on Kandy - Jaffna Road 6+500 - 9+910
Gihan Enterprise
113,434,139.4020,128,022.3723,751,066.40——2,934,355.863,462,539.91——23,062,378.23—
27.21Mn
24%
Watch
27.21Mn
24%
12RDA/DRP/CEN/KDY/KUN/29
Improvement to Structures on Kandy - Mahiyanganaya - Padiyaththalawa Road (24+00…
S N O Builders (Pvt) Ltd
91,559,621.0416,157,282.8419,065,593.75——15,442,292.2818,221,904.8910,906,899.2212,870,141.0831,599,575.1210,906,899.22
37.29Mn
40.7%
On Track
50.16Mn
54.8%
13RDA/DRP/CEN/MTL/MTL/31R
Rehabilitation / Improvement of Matale - Udupihilla Road (AB026) (0+000 - 6+000)
Alucon Industries (Pvt) Ltd
63,704,849.78————————————
14RDA/DRP/CEN/MTL/MTL/32
Rehabilitation / Improvement of Kandy Jaffna (A-009)(17+710 - 46+450), Thalgodap…
Lahiru Construction and Consultants (Pvt…
292,279,354.0852,461,047.8461,904,036.46——23,455,869.7327,677,926.2714,693,549.1617,243,721.7475,916,917.5714,693,549.16
89.58Mn
30.6%
Watch
106.83Mn
36.5%
15RDA/DRP/CEN/MTL/MTL/33
Rehabilitation / Improvement of Wattegama Matale Road (5+280 - 13+160) and Ukuwe…
Jayasinghe Construction (Pvt) Ltd
165,006,430.7929,068,239.7134,300,522.86——————29,068,239.71—
34.30Mn
20.8%
Watch
34.30Mn
20.8%
16RDA/DRP/CEN/MTL/MTL/35
Rehabilitation / Improvement of Rattota Gammaduwa Road (7+100 - 11+260)
Kanwel Constructions & Civil Engineering…
266,607,902.1546,351,528.3654,694,803.46——29,493,532.2434,802,368.04——75,845,060.60—
89.50Mn
33.6%
Watch
89.50Mn
33.6%
17RDA/DRP/CEN/MTL/MTL/38
Rehabilitation / Improvement of Kalalpitiya Ukuwela Elkaduwa Road (B 180) (0+000…
Ediriweera Construction
281,166,339.8049,863,459.1058,838,881.72——————49,863,459.10—
58.84Mn
20.9%
Watch
58.84Mn
20.9%
18RDA/DRP/CEN/MTL/MTL/41
Rehabilitation / Improvement of Matale Illukkumbura Laggala Road (B 274) (4+000 …
Vikum Construction
276,683,432.37————————————
19RDA/DRP/CEN/MTL/NAL/48R
Rehabilitation/Improvement of surfacing (ASphalt) hard shoulder,Shoulder, drain…
S A P Engineering (Pvt) Ltd
50,471,466.08————————————
20RDA/DRP/CEN/MTL/NAL/49
Rehabilitation /Improvement of Drains,Hard shoulder & Cash barrier at Naula- E…
Platinum Holdings Lanka (Private) Limite…
44,706,119.137,270,523.428,579,217.63——5,063,036.565,974,383.14——12,333,559.98—
14.55Mn
32.6%
Watch
14.55Mn
32.6%
Total34,005,299,486.172,787,819,645.293,289,427,166.63113,218,826.01133,598,214.691,049,943,508.601,238,847,524.5163,842,351.1873,647,937.023,837,763,153.89177,061,177.19
4,528.27Mn
13.3%
4,735.52Mn
13.9%
Showing 11–20 of 171 projects · page 2/18