DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 73 awarded projects

2026-11-04
22:58:15Live2026-11-04
0 / 73Advance Pendingpending advance projects / total projects
0 / 73IPC Pendingpending IPC projects / total projects
0 / 73Advance Paidadvance paid projects / total projects
0 / 73IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Eastern Province · Province

579Projects23,829.3Contract Mn
Eastern Province 73 projects Open filtered view
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn6566.4152.027% of contract414.4——————96.8%0.0%
Tender Below 50Mn551,164.1376.332% of contract787.8——————41.8%0.0%
PIU00.0——————————
Tender Total611,730.5528.331% of contract1,202.2000.0000.047.2%0.0%
Direct LabourDL Stage 016311.7220.071% of contract91.7——————83.3%0.0%
DL Stage 02249.340.181% of contract9.2——————100.0%0.0%
DL Stage 03148.850.6104% of contract-1.8——————0.0%0.0%
DL Stage 04393.972.777% of contract21.3——————33.3%0.0%
Direct Labour Total12503.8383.476% of contract120.4000.0000.066.6%0.0%
—Eastern Province732,234.3911.741% of contract1,322.6000.0000.050.4%0.0%
Tender Above 50Mn6 projectsTender566.4Mn
27% paid152.0 Mn
Pending414.4Mn
Planned Fin96.8%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn55 projectsTender1,164.1Mn
32% paid376.3 Mn
Pending787.8Mn
Planned Fin41.8%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projectsTender0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 016 projectsDirect Labour311.7Mn
71% paid220.0 Mn
Pending91.7Mn
Planned Fin83.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 022 projectsDirect Labour49.3Mn
81% paid40.1 Mn
Pending9.2Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 projectDirect Labour48.8Mn
104% paid50.6 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 043 projectsDirect Labour93.9Mn
77% paid72.7 Mn
Pending21.3Mn
Planned Fin33.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Eastern Province73 projects2,234.3Mn
41% paid911.7 Mn
Pending1,322.6Mn
Planned Fin50.4%
Actual Fin0.0%

Avg Physical Progress per Province · Eastern Province

Graphs reflect current view:73 awarded · Eastern Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 218 projects (filtered from 579)

21–30/218 (filtered from 579)
ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
21RR/RDA/06/25/40/CP/NE
Walapane Samachaithya asalin Arambawana Kurundu oya diyaella dakwa Margaya
UGD Constructions
31,672,222.12————————————
22RR/RDA/06/25/41/CP/NE
Nayapana Gammada tharapara sanwardhanaya
Central Engineering Services Pvt Ltd. (C…
51,754,603.52————————————
23RR/RDA/06/25/42/CP/NE
AC Overlaying from Polpitiya Junction to 04th Mile Post (CH 3+700 – 8+700 km)
UKS Lanka Engineering Pvt Ltd.
220,116,957.84————————————
24—
Carpeting of road from Bambaragama Moragollahinna to Karamidula
Ajith Construction
61,551,869.38————————————
25—
Carpeting of Mahathenna to Hapugasdeniya Main Road
Ajith Construction
68,070,000.00————————————
26RR/RDA/16/25/03/AKK/AMP
Polbedda Junction to Galwalayaya Road
MOTEC Engineering & Construction
17,506,335.00————————————
27RR/RDA/SP/16/25/01/AKK/AMP
Rectification and Asphalt Surfacing on Ambahagawela -Namaloya Main Road
SMA Careem Engineering Consultancy Servi…
222,189,859.13————————————
28RR/RDA/STA II/16/25/03/AKK/A…
Padiyathalawa Navinna road from Navinna Junction A5 to Navinna Bridge
Vithu Construction
39,470,000.00————————————
29RR/RDA/16/25/10KM/01/AKK/AMP
The road from the bridge near Ridee ela Temple to Island Plot No. 197
Sawsiri Construction
24,113,338.37————————————
30RR/RDA/16/25/10KM/02/AKK/AMP
Road from Nelum Cafe Junction to Neeththa
Gama Construction & Consultant pvt Ltd
19,318,560.10————————————
Total8,978,398,226.97——————————
—Mn
0%
—Mn
0%
Showing 21–30 of 218 projects · page 3/22