DRRRP · Sri Lanka
Project Monitoring Dashboard
Comprehensive overview of 24 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka.
Updated 2026-11-04 12:46Live
Graphs reflect current view:24 awarded · Nuwara Eliya
42.9% awarded
0
Awarded
56 total projects in portfolio
Awarded projects24
RDA/DRP/CEN/NUE/HAN/57Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )RDA/DRP/CEN/NUE/NUE/60RPeradeniya Badulla Chenkaladi Road (A005)RDA/DRP/CEN/NUE/NUE/66Nuwara Eliya Town Road (B331)RDA/DRP/CEN/NUE/NUE/67Harangala - Kalapitiya - Kumbaloluwa Road (B148)RDA/DRP/CEN/NUE/NUE/68Thawalanthenna Thalawakelle Road (B412)RDA/DRP/CEN/NUE/NUE/69Ulapane Pussallawa Road (B431)RDA/DRP/CEN/NUE/NUE/86Approch road to R'way station (Watagoda) RoadRDA/DRP/CEN/NUE/NUR/97Nawalapitiya Ginigathena Road (B-319)RDA/DRP/CEN/NUE/NUR/98Harangala Kalapitiya Road (B-148) (0+000-10+700), Approach Road to Harangala Dam Crest Road (B-491) (0+000-3+820), Nawalapitiya Harangala Road (B-306) (0+000-10+700)RDA/DRP/CEN/NUE/NUR/101Hatton Maskeliya Delhouse Road (B-149)RDA/DC/DRP/CP/NE/NRW/02REHABILITATION/ IMPROVEMENT OF APPROACH ROAD TO LAXAPANA POWER HOUSE ROAD CH (6+100 TO 12+000) KMRDA/DC/DRP/CP/NE/NE/04LADY MACALUMS DRIVE ROADRDA/DC/DRP/CP/NE/NRW/03RDA/DC/DRP/CP/NE/NE/14RDA/DC/DRP/CP/NE/NE/05
+9 more…
Click to filter the awarded table
8,516.5M
8,516.5 Mn
Contract Value
Awarded projects24
RDA/DRP/CEN/NUE/HAN/57Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )RDA/DRP/CEN/NUE/NUE/60RPeradeniya Badulla Chenkaladi Road (A005)RDA/DRP/CEN/NUE/NUE/66Nuwara Eliya Town Road (B331)RDA/DRP/CEN/NUE/NUE/67Harangala - Kalapitiya - Kumbaloluwa Road (B148)RDA/DRP/CEN/NUE/NUE/68Thawalanthenna Thalawakelle Road (B412)RDA/DRP/CEN/NUE/NUE/69Ulapane Pussallawa Road (B431)RDA/DRP/CEN/NUE/NUE/86Approch road to R'way station (Watagoda) RoadRDA/DRP/CEN/NUE/NUR/97Nawalapitiya Ginigathena Road (B-319)RDA/DRP/CEN/NUE/NUR/98Harangala Kalapitiya Road (B-148) (0+000-10+700), Approach Road to Harangala Dam Crest Road (B-491) (0+000-3+820), Nawalapitiya Harangala Road (B-306) (0+000-10+700)RDA/DRP/CEN/NUE/NUR/101Hatton Maskeliya Delhouse Road (B-149)RDA/DC/DRP/CP/NE/NRW/02REHABILITATION/ IMPROVEMENT OF APPROACH ROAD TO LAXAPANA POWER HOUSE ROAD CH (6+100 TO 12+000) KMRDA/DC/DRP/CP/NE/NE/04LADY MACALUMS DRIVE ROADRDA/DC/DRP/CP/NE/NRW/03RDA/DC/DRP/CP/NE/NE/14RDA/DC/DRP/CP/NE/NE/05
+9 more…
Click to filter the awarded table
Avg
31.3%
13
works in progress
0 completed
Avg Progress
Awarded projects24
RDA/DRP/CEN/NUE/HAN/57Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )RDA/DRP/CEN/NUE/NUE/60RPeradeniya Badulla Chenkaladi Road (A005)RDA/DRP/CEN/NUE/NUE/66Nuwara Eliya Town Road (B331)RDA/DRP/CEN/NUE/NUE/67Harangala - Kalapitiya - Kumbaloluwa Road (B148)RDA/DRP/CEN/NUE/NUE/68Thawalanthenna Thalawakelle Road (B412)RDA/DRP/CEN/NUE/NUE/69Ulapane Pussallawa Road (B431)RDA/DRP/CEN/NUE/NUE/86Approch road to R'way station (Watagoda) RoadRDA/DRP/CEN/NUE/NUR/97Nawalapitiya Ginigathena Road (B-319)RDA/DRP/CEN/NUE/NUR/98Harangala Kalapitiya Road (B-148) (0+000-10+700), Approach Road to Harangala Dam Crest Road (B-491) (0+000-3+820), Nawalapitiya Harangala Road (B-306) (0+000-10+700)RDA/DRP/CEN/NUE/NUR/101Hatton Maskeliya Delhouse Road (B-149)RDA/DC/DRP/CP/NE/NRW/02REHABILITATION/ IMPROVEMENT OF APPROACH ROAD TO LAXAPANA POWER HOUSE ROAD CH (6+100 TO 12+000) KMRDA/DC/DRP/CP/NE/NE/04LADY MACALUMS DRIVE ROADRDA/DC/DRP/CP/NE/NRW/03RDA/DC/DRP/CP/NE/NE/14RDA/DC/DRP/CP/NE/NE/05
+9 more…
Click to filter the awarded table
347.9M
347.9 Mn
Total Expenditure (incl. VAT)
Awarded projects24
RDA/DRP/CEN/NUE/HAN/57Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )RDA/DRP/CEN/NUE/NUE/60RPeradeniya Badulla Chenkaladi Road (A005)RDA/DRP/CEN/NUE/NUE/66Nuwara Eliya Town Road (B331)RDA/DRP/CEN/NUE/NUE/67Harangala - Kalapitiya - Kumbaloluwa Road (B148)RDA/DRP/CEN/NUE/NUE/68Thawalanthenna Thalawakelle Road (B412)RDA/DRP/CEN/NUE/NUE/69Ulapane Pussallawa Road (B431)RDA/DRP/CEN/NUE/NUE/86Approch road to R'way station (Watagoda) RoadRDA/DRP/CEN/NUE/NUR/97Nawalapitiya Ginigathena Road (B-319)RDA/DRP/CEN/NUE/NUR/98Harangala Kalapitiya Road (B-148) (0+000-10+700), Approach Road to Harangala Dam Crest Road (B-491) (0+000-3+820), Nawalapitiya Harangala Road (B-306) (0+000-10+700)RDA/DRP/CEN/NUE/NUR/101Hatton Maskeliya Delhouse Road (B-149)RDA/DC/DRP/CP/NE/NRW/02REHABILITATION/ IMPROVEMENT OF APPROACH ROAD TO LAXAPANA POWER HOUSE ROAD CH (6+100 TO 12+000) KMRDA/DC/DRP/CP/NE/NE/04LADY MACALUMS DRIVE ROADRDA/DC/DRP/CP/NE/NRW/03RDA/DC/DRP/CP/NE/NE/14RDA/DC/DRP/CP/NE/NE/05
+9 more…
Click to filter the awarded table
16.7%
0
On Progress
4 / 24 awarded
On Progress (incl. completed)4
RDA/DRP/CEN/NUE/NUE/60RPeradeniya Badulla Chenkaladi Road (A005)RDA/DC/DRP/CP/NE/NRW/02REHABILITATION/ IMPROVEMENT OF APPROACH ROAD TO LAXAPANA POWER HOUSE ROAD CH (6+100 TO 12+000) KMRDA/DC/DRP/CP/NE/NE/04LADY MACALUMS DRIVE ROADRDA/DC/DRP/CP/NE/NRW/03
Click to filter the awarded table
0%
0
Delay
0 / 24 awarded
Delay0
No projects
Click to filter the awarded table
37.5%
0
Critical Delay
9 / 24 awarded
Critical Delay9
RDA/DRP/CEN/NUE/HAN/57Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )RDA/DRP/CEN/NUE/NUE/66Nuwara Eliya Town Road (B331)RDA/DRP/CEN/NUE/NUE/67Harangala - Kalapitiya - Kumbaloluwa Road (B148)RDA/DRP/CEN/NUE/NUE/68Thawalanthenna Thalawakelle Road (B412)RDA/DRP/CEN/NUE/NUE/69Ulapane Pussallawa Road (B431)RDA/DRP/CEN/NUE/NUE/86Approch road to R'way station (Watagoda) RoadRDA/DRP/CEN/NUE/NUR/97Nawalapitiya Ginigathena Road (B-319)RDA/DRP/CEN/NUE/NUR/98Harangala Kalapitiya Road (B-148) (0+000-10+700), Approach Road to Harangala Dam Crest Road (B-491) (0+000-3+820), Nawalapitiya Harangala Road (B-306) (0+000-10+700)RDA/DRP/CEN/NUE/NUR/101Hatton Maskeliya Delhouse Road (B-149)
Click to filter the awarded table
0%
0
Completed
0 / 24 awarded
Completed0
No projects
Click to filter the awarded table
Portfolio Breakdown · Nuwara Eliya · District
Avg Physical Progress per EE Division · Nuwara Eliya
At-Risk Projects · Nuwara Eliya
- RDA/DRP/CEN/NUE/NUE/66Nuwara Eliya Town Road (B331)Delay96 Days in Delay · 69%
- RDA/DRP/CEN/NUE/NUE/86Approch road to R'way station (Watagoda) RoadDelay55 Days in Delay · 20%
- RDA/DRP/CEN/NUE/NUR/97Nawalapitiya Ginigathena Road (B-319)Delay50 Days in Delay · 62%
- RDA/DRP/CEN/NUE/HAN/57Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )Delay7 Days in Delay · 30%
- RDA/DRP/CEN/NUE/NUE/67Harangala - Kalapitiya - Kumbaloluwa Road (B148)Delay5 Days in Delay · 78%
- RDA/DRP/CEN/NUE/NUE/68Thawalanthenna Thalawakelle Road (B412)Delay5 Days in Delay · 40%
- RDA/DRP/CEN/NUE/NUE/69Ulapane Pussallawa Road (B431)Delay5 Days in Delay · 56%
Portfolio Timeline· 13 scheduled projects · Nuwara Eliya Toggle
2026-05-02 today2028-03-15
Portfolio · Awarded Works
Awarded Projects
9 projects
Filter awarded works
9 matching projects1 active
| Contract No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|
| RDA/DRP/CEN/NUE/HAN/57 | Rehabilitation / Improvement of Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 ) | 30% | 47,755,538.96 | 44,694,533.62 | Awarded |
| RDA/DRP/CEN/NUE/NUE/66 | Rehabilitation / Improvement of Nuwara Eliya Town Road (0+000 - 1+695 ) (0+000 - 0+240 ) | 69% | 161,841,095.70 | 205,630,098.81 | Awarded |
| RDA/DRP/CEN/NUE/NUE/67 | Rehabilitation / Improvement of Harangala - Kalapitiya - Kumbaloluwa Road (10+480 km - 17+140 km) | 78% | 239,417,811.34 | 302,933,613.60 | Awarded |
| RDA/DRP/CEN/NUE/NUE/68 | Rehabilitation / Improvement of Thawalanthenna Thalawakelle Road (0+000 - 8+000) & (10+000 - 33+200) | 40% | 213,999,600.01 | 296,813,201.99 | Awarded |
| RDA/DRP/CEN/NUE/NUE/69 | Rehabilitation / Improvement of Ulapane Pussallawa Road (6+440 - 15+950) | 56% | 266,045,892.19 | 365,868,062.33 | Awarded |
| RDA/DRP/CEN/NUE/NUE/86 | Rehabilitation / Improvement of Approch road to R'way station (Watagoda/ Thalawakele) Road | 20% | 33,765,626.86 | 41,996,395.31 | Awarded |
| RDA/DRP/CEN/NUE/NUR/97 | Rehabilitation/Improvement of Nawalapitiya Ginigathena Road (B-319)(7+200-12+200) | 62% | 93,758,217.76 | 104,490,700.33 | Awarded |
| RDA/DRP/CEN/NUE/NUR/98 | Rehabilitation/Improvement Harangala Kalapitiya Road (B-148) (0+000-10+700), Approach Road to Hrangala Dam Crest Road (B-491) (0+000-3+820), Nawalapitiya Harangala Road (B-306) (0+000-10+700) | 44% | 188,617,394.68 | 222,691,835.72 | Awarded |
| RDA/DRP/CEN/NUE/NUR/101 | Rehabilitation/Improvement of Hatton Maskeliya Delhouse Road (B-149) (0+000-31+970) | 31% | 86,746,198.17 | 108,611,538.67 | Awarded |
Showing 1–9 of 9