Project Monitoring Dashboard

Comprehensive overview of 26 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka. · Team Leader

Updated 2026-11-04 12:46Live
Graphs reflect current view:26 awarded · Team Leader · Central Province

Portfolio Breakdown · Team Leader · Central Province · Consultant

44Awarded45Total
Team Leader 26 awarded of 26 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %Kick Off PendingMobilization PendingWorks Not Started
Emergency15150100%2,335.52,082.21,333.7381.018% of contract61.8%30.4%111
DC - Roads660100%3,362.14,137.5——0.0%0.3%555
DC - Slope550100%1,967.51,984.710.4—0.5%4.7%444
PD(CP) - Slope0000%0.00.0———————
Team Leader26260100%7,665.18,204.41,344.1381.05% of contract35.8%18.5%101010

Project-wise Progress · Team Leader · Central Province (26 projects in one graph)

Physical Actual vs Planned per project • Click bar to open project

Clear

Project-wise Physical Progress: Actual vs Planned (%) · Team Leader · Central Province

Average Physical Progress by EE Division · Team Leader · Central Province

Average District-wise Physical Progress (Kandy District)

Kandy district baseline — all categories (consultant filter excluded for comparison)

Portfolio Timeline· 16 scheduled projects · Team Leader · Central Province Toggle
Portfolio · Awarded Works

Awarded Projects

4 projects

4/4 (filtered)

Filter awarded works

4 matching projects1 active

ActiveDelay
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/CEN/KDY/KAN/14
Rehabilitation /Improvement of Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370)
9%
74,836,014.7772,827,654.90Awarded
RDA/DRP/CEN/KDY/KDY/15
Rehabilitation / Improvement of Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)
6%
79,071,437.6879,953,569.86Awarded
RDA/DRP/CEN/KDY/KUN/24R
Rehabilitation / Improvement of Flood damage on Katugastota - Madawala - Bamberella Road (B205) (0-000 - 7+200 and 13+000 - 13+045)
5%
79,507,501.1180,438,429.85Awarded
RDA/DRP/CEN/KDY/KUN/29
Improvement to Structures on Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) and Moragahamula victoria damtop
61%
91,559,621.04100,543,979.99Awarded
Showing 1–4 of 4
Per page:
Source: DRRRP • 26 projects • Data updated 2026-11-04 12:46 • 14:32:05