Project Monitoring Dashboard

Comprehensive overview of 26 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka. · Team Leader

Updated 2026-11-04 12:46Live
Graphs reflect current view:26 awarded · Team Leader

Portfolio Breakdown · Team Leader · Consultant

44Awarded45Total
Team Leader 26 awarded of 26 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %Kick Off PendingMobilization PendingWorks Not Started
Emergency15150100%2,335.52,082.21,333.7381.018% of contract61.8%30.4%111
DC - Roads660100%3,362.14,137.5——0.0%0.3%555
DC - Slope550100%1,967.51,984.710.4—0.5%4.7%444
PD(CP) - Slope0000%0.00.0———————
Team Leader26260100%7,665.18,204.41,344.1381.05% of contract35.8%18.5%101010

Project-wise Progress · Team Leader (26 projects in one graph)

Physical Actual vs Planned per project • Click bar to open project

Clear

Project-wise Physical Progress: Actual vs Planned (%) · Team Leader

Average Physical Progress by EE Division · Team Leader

Average District-wise Physical Progress (Kandy District)

Kandy district baseline — all categories (consultant filter excluded for comparison)

Portfolio Timeline· 16 scheduled projects · Team Leader Toggle
Portfolio · Awarded Works

Awarded Projects

26 projects

25/26

Filter awarded works

26 matching projects

Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/CEN/KDY/KAD/11
Rehabilitation / Improvement of Nawalapitiya - Dolosbage Road ( B -318) ( 10+500 - 19+350 ), Dedugala Dolosbage Road ( B -588) ( 10+100 - 12+410 )
26.5%
193,404,194.96275,515,701.42Awarded
RDA/DRP/CEN/KDY/KAN/14
Rehabilitation /Improvement of Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370)
9%
74,836,014.7772,827,654.90Awarded
RDA/DRP/CEN/KDY/KDY/15
Rehabilitation / Improvement of Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)
6%
79,071,437.6879,953,569.86Awarded
RDA/DRP/CEN/KDY/KDY/19
Rehabilitation / Improvement of Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000)
5%
67,935,586.7764,393,315.70Awarded
RDA/DRP/CEN/KDY/KUN/20
Rehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuwara Road (B 257) (4+000 - 8+000)
53%
31,558,227.9828,660,618.70Awarded
RDA/DRP/CEN/KDY/KUN/21
Improvement of Pitiyegedara-Waththegama-Iriyagasthenna Road (0+000-5+400)
12%
257,721,453.96314,486,807.16Awarded
RDA/DRP/CEN/KDY/KUN/22
Improvement to Damaged Road Section on Weeragantota - Randenigala Road. (From CH 19+000 To CH 27+200)
67%
224,968,435.78333,005,906.52Awarded
RDA/DRP/CEN/KDY/KUN/24R
Rehabilitation / Improvement of Flood damage on Katugastota - Madawala - Bamberella Road (B205) (0-000 - 7+200 and 13+000 - 13+045)
5%
79,507,501.1180,438,429.85Awarded
RDA/DRP/CEN/KDY/KUN/25
Construction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LHS 9+600 - 9+655), (15+450 - 15+500), (10+235 - 10+300) and Wattegama Matale road (0+400 - 0+435)
59%
157,909,825.01178,738,774.63Awarded
RDA/DRP/CEN/KDY/KUN/26R
Improvement to Structures on Kandy - Jaffna Road 11+700 - 11+850
0%
148,430,322.65140,123,428.78Awarded
RDA/DRP/CEN/KDY/KUN/27
Improvement to Structures on Kandy - Jaffna Road 6+500 - 9+910
66%
113,434,139.40122,896,558.88Awarded
RDA/DRP/CEN/KDY/KUN/29
Improvement to Structures on Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) and Moragahamula victoria damtop
61%
91,559,621.04100,543,979.99Awarded
RDA/DRP/CEN/MTL/MTL/31R
Rehabilitation / Improvement of Matale - Udupihilla Road (AB026) (0+000 - 6+000)
7.5%
63,704,849.78—Awarded
RDA/DRP/CEN/NUE/NUE/60R
Rehabilitation / Improvement of Peradeniya Badulla Chenkaladi Road (A005) (40+750 - 42+850)
10%
336,313,078.73338,287,510.33Awarded
RDA/DRP/CEN/NUE/NUE/66
Rehabilitation / Improvement of Nuwara Eliya Town Road (0+000 - 1+695 ) (0+000 - 0+240 )
69%
161,841,095.70205,630,098.81Awarded
RDA/DC/DRP/CP/NE/NE/04
REHABILITAION/ IMPROVEMENTS OF LADY MACALUMS DRIVE ROAD (2+850 - 5+600KM)
1%
636,338,397.00560,630,000.00Awarded
RDA/DC/DRP/SLOPE/CP/KDY/GAMPOLA-09
MITIGATION OF FAILURES ALONG RDA ROADS DUE TO CYCLONE DITWAH GAMPOLA NAWALAPITIYA ROAD (AB013) CHAINAGE 10+350 KM
9.3%
386,699,553.58479,898,195.86Awarded
RDA/DC/DRP/CP/NE/NE/14
Rehabilitation/ Improvement of Lady Macalums Drive (0+000 - 2+700)
0%
711,929,618.35575,100,000.00Awarded
RDA/DC/DRP/CP/NE/NE/05
Rehabilitation/ Improvement of Blackpool Ambewela Pattipola Hortan Plains (5+200 - 12+000)
0%
791,681,996.67612,060,000.00Awarded
RDA/DC/DRP/CP/NE/NE/01
Rehabilitation/ Improvement of Blackpool Ambewela Pattipola Hortan Plains (12+500 - 18+000)
0%
744,680,423.80605,620,000.00Awarded
RDA/DC/DRP/CP/NE/NE/09
Rehabilitation/ Improvement to Blackpool Ambewela Pattipola Hortan Plains ( 19+000 - 23+000)
0%
607,139,242.74487,070,000.00Awarded
RDA/DC/DRP/CP/NE/NE/07
Rehabilitation/ Improvement to Gomburuoya - Balapokuna Road 0+000-8+500Without 5+250-5+450 & 6+900-7+150
0%
645,688,890.82521,587,977.73Awarded
RDA/DC/DRP/SLOPE/CP/MAT/MAT/PACKAGE-23
REHABILITATION OF SELECTED ROAD SECTIONS ON KALALPITIYA UKUWELA-ELKADUWA ROAD (12th KM) AND SLOPE FAILURES DUE TO DITWAH CYCLONE -PACKAGE -23
0%
372,110,778.00337,000,000.00Awarded
RDA/DC/DRP/SLOPE/CP/NUE/NUE/PACKAGE-31
REHABILITATION OF SELECTED ROADSECTIONS ON PERADENIYA-BADULLA-CHENKALADI ROAD(44TH KM) AND SLOPE FAILURES DUE TO DITWAH CYCLONE
0%
376,649,403.13320,000,000.00Awarded
RDA/DC/DRP/SLOPE/CP/KDY/KUN/PACKAGE 06A
REHABILITATION OF SELECTED ROAD SECTIONS ON KANDY-MAHIYANGANA-PADIYATHALAWA ROAD (34th & 35th KM) & MORAGAHAMULA VICTORIA DAMTOP ROAD (6TH KM) AND SLOPE FAILURES DUE TO "DITWAH" CYCLONE- PACKAGE 06A
0%
628,900,686.30614,600,000.00Awarded
Showing 1–25 of 26
Per page:
Source: DRRRP • 26 projects • Data updated 2026-11-04 12:46 • 12:59:04