DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 12 awarded projects

2026-11-05
00:38:34Live2026-11-05
0.0 Mn

— Mn

Advance Pend (incl. VAT)

Portfolio Breakdown — Financial (Exclusive Vat) · EE: Kundasale · EE Office

155Projects31,163.5Contract Mn
Reset
Kundasale 12 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency81,105.1271.425% of contract33.955151.19479.074.0%20.8%
DC - Roads00.0——————————
DC - Slope1628.9————————0.0%0.0%
PD(CP) - Slope357.8————————0.0%0.0%
Kundasale121,791.8271.415% of contract33.955151.19479.049.3%12.8%
Emergency8 projects1,105.1Mn
25% paid271.4 Mn
Pending33.9Mn
Planned Fin74.0%
Actual Fin20.8%
Advance & IPC
Advance paid5 proj · 151.1 Mn
IPC paid4 proj · 79.0 Mn
Open filtered view
DC - Roads0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope1 project628.9Mn
0% paid0.0 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope3 projects57.8Mn
0% paid0.0 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Kundasale12 projects1,791.8Mn
15% paid271.4 Mn
Pending33.9Mn
Planned Fin49.3%
Actual Fin12.8%

Avg Physical Progress per Province · EE: Kundasale

Project-wise Financials · EE: Kundasale (171 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · EE: Kundasale (Mn · incl. VAT)

Scroll horizontally — 171 projects

Kundasale Division · EE: Kundasale (Mn · incl. VAT)

Kandy District Summary (Mn · incl. VAT)

District baseline — overall all categories (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:12 awarded · EE: Kundasale
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 171 projects

121–130/171

Filter financial register

171 matching projects

S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
121RDA/DRP/SAB/RAT/EMB/07
Rehabilitation / Improvement of Pelmadulla - Embilipitiya-Nonagama Road (37+000-…
Anura Construction
276,583,785.23————————————
122RDA/DRP/SAB/RAT/EMB/09
Rehabilitation / Improvement of Pelmadulla - Embilipitiya - Naonagama Road (47+1…
Anura Construction
269,913,795.48————————————
123RDA/DRP/SAB/RAT/EMB/11
Rehabilitation / Improvement of Weligepola-Hadagiriya - Kapugala (2+000-11+000)
D K S Construction
273,586,576.2249,239,013.9458,102,036.46——————49,239,013.94—
58.10Mn
21.2%
Watch
58.10Mn
21.2%
124RDA/DRP/WP/COL/COL/07
Rehabilitation / Improvement of Colombo Hanwella Road (0+370 - 20+400)
INK Engineering
146,665,907.47————5,477,974.446,464,009.84——5,477,974.44—
6.46Mn
4.4%
Behind
6.46Mn
4.4%
125RDA/DRP/EAS/TRI/TRI/03
Rehabilitation / Improvement of Town & Gravets Road (B140) (Fort Fredrick Road) …
Motec Engineering & Construction
37,828,051.78————15,201,592.3817,937,879.01——15,201,592.38—
17.94Mn
47.4%
On Track
17.94Mn
47.4%
126RDA/DRP/EAS/TRI/TRI/04
Rehabilitation / Improvement of Town & Gravets Road (B140) (Inner Harbour Road) …
Motec Engineering & Construction
40,407,339.17————————————
127RDA/DRP/NWP/KURU/MAHO/06R
Rehabilitation / Improvement of Kadigawa Bridge Approaches on Pahala Mawathagama…
RCDC Construction Company (Pvt) Ltd
75,025,358.95————————————
128RDA/DRP/NWP/CHI/CHI/08
Rehabilitation / Improvement of Baththuluoya - Udappuwa - Andimunai Road (B614) …
ST MARY Construction
83,944,711.21————15,224,674.7617,965,116.22——15,224,674.76—
17.97Mn
21.4%
Watch
17.97Mn
21.4%
129RDA/DPR/NCP/ANU/ANU/01
Rehabilitation / Improvement of Andarawewa - Balaluwewa Road (B501) (21+330 - 21…
Ranuja Construction
99,497,834.48————————————
130RDA/DRP/NCP/POL/HAB/04
Rehabilitation / Improvement of washed out section between 30/1 & 30/2 Bridges o…
Lahiru Construction and Consultants (Pvt…
49,203,550.22————————————
Total34,005,299,486.172,787,819,645.293,289,427,166.63113,218,826.01133,598,214.691,049,943,508.601,238,847,524.5163,842,351.1873,647,937.023,837,763,153.89177,061,177.19
4,528.27Mn
13.3%
4,735.52Mn
13.9%
Showing 121–130 of 171 projects · page 13/18