DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 18 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:18 awarded · Nuwara Eliya
0%

0

Delay

0 / 18 awarded

Portfolio Breakdown · Nuwara Eliya · District

579Awarded739Total
Nuwara Eliya 18 awarded of 25 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn106460%988.7494.6365.0111.923% of contract66.7%42.0%
Tender Below 50Mn63350%170.298.898.847.048% of contract100.0%38.3%
DL Stage 01330100%185.3184.3184.3186.1101% of contract100.0%100.0%
DL Stage 02110100%40.740.740.745.3111% of contract100.0%100.0%
DL Stage 03550100%126.7126.7126.760.147% of contract100.0%79.6%
DL Stage 040000%0.00.0————
PIU0000%0.00.0————
Not Specified0000%0.00.0————
Nuwara Eliya2518772%1,511.5945.1815.4450.548% of contract88.9%64.7%

Avg Physical Progress per EE Division · Nuwara Eliya

Portfolio Timeline· 18 scheduled projects · Nuwara Eliya Toggle
Portfolio · Awarded Works

Awarded Projects

0 projects

0/0 (filtered)

Filter awarded works

0 matching projects1 active

ActiveDelay
Showing 0–0 of 0
Per page:
Source: DRRRP • 25 projects • Data updated 2026-11-02 10:30 • 13:37:38