DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 73 awarded projects

2026-11-05
16:57:10Live2026-11-05
0 / 73Advance Pendingpending advance projects / total projects
0 / 73IPC Pendingpending IPC projects / total projects
0 / 73Advance Paidadvance paid projects / total projects
0 / 73IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Eastern Province · Province

579Projects23,829.3Contract Mn
Eastern Province 73 projects Open filtered view
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn6566.4152.027% of contract414.4——————96.9%0.0%
Tender Below 50Mn551,164.1376.332% of contract787.8——————41.8%0.0%
PIU00.0——————————
Tender Total611,730.5528.331% of contract1,202.2000.0000.047.2%0.0%
Direct LabourDL Stage 016311.7220.071% of contract91.7——————83.3%0.0%
DL Stage 02249.340.181% of contract9.2——————100.0%0.0%
DL Stage 03148.850.6104% of contract-1.8——————0.0%0.0%
DL Stage 04393.972.777% of contract21.3——————33.3%0.0%
Direct Labour Total12503.8383.476% of contract120.4000.0000.066.6%0.0%
—Eastern Province732,234.3911.741% of contract1,322.6000.0000.050.4%0.0%
Tender Above 50Mn6 projectsTender566.4Mn
27% paid152.0 Mn
Pending414.4Mn
Planned Fin96.9%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn55 projectsTender1,164.1Mn
32% paid376.3 Mn
Pending787.8Mn
Planned Fin41.8%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projectsTender0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 016 projectsDirect Labour311.7Mn
71% paid220.0 Mn
Pending91.7Mn
Planned Fin83.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 022 projectsDirect Labour49.3Mn
81% paid40.1 Mn
Pending9.2Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 projectDirect Labour48.8Mn
104% paid50.6 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 043 projectsDirect Labour93.9Mn
77% paid72.7 Mn
Pending21.3Mn
Planned Fin33.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Eastern Province73 projects2,234.3Mn
41% paid911.7 Mn
Pending1,322.6Mn
Planned Fin50.4%
Actual Fin0.0%

Avg Physical Progress per Province · Eastern Province

Graphs reflect current view:73 awarded · Eastern Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

231–240/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
231RR/RDA/12/25/30/NP/VVN
Maradammaduwa Rural Road
Sevvel Construction & Suppliers
25,533,435.95————————————
232RR/RDA/12/25/31/NP/VVN
Mahakachchakodiya to Ettambagaskada
Yansika Construction
45,254,190.85————————————
233RR/RDA/12/25/32/NP/VVN
Kalukummankaduwa to Alagalla Rural Road
Yansika Construction
36,671,440.85————————————
234RR/RDA/12/25/33/NP/VVN
Mamaduwa Thiyawaragama Road
5N Group Construction
20,811,747.00————————————
235RR/RDA/12/25/35/NP/VVN
Awusadapitiya Pubudugama Road
Nimna Holdings (Pvt) Ltd
32,504,637.43————————————
236RR/RDA/12/25/36/NP/VVN
Mamaduwa to Dikwewa
Sintha Construction (Pvt) Ltd
18,006,430.20————————————
237RR/RDA/12/25/37/NP/VVN
Parakumawatha
Ranasinghe Construction
26,672,047.60————————————
238RR/RDA/12/25/38/NP/VVN
Salalinigama 11 lane
Sintha Construction (Pvt) Ltd
30,830,906.70————————————
239RR/RDA/12/25/39/NP/VVN
Madukanda lake side road
Sintha Construction (Pvt) Ltd
22,687,590.20————————————
240RR/RDA/12/25/40/NP/VVN
Halabagaswewa
North Construction (Pvt) Ltd
25,032,191.25————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 231–240 of 579 projects · page 24/58