DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 579 awarded projects

2026-11-04
16:24:47Live2026-11-04
0 / 579Advance Pendingpending advance projects / total projects
0 / 579IPC Pendingpending IPC projects / total projects
0 / 579Advance Paidadvance paid projects / total projects
0 / 579IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Province

579Projects23,829.3Contract Mn
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn1068,082.61,572.919% of contract6,509.7——————51.7%0.0%
Tender Below 50Mn3006,498.82,506.039% of contract3,992.8——————55.3%0.0%
PIU32,119.9—2,119.9——————0.0%0.0%
Tender Total40916,701.34,079.024% of contract12,622.4000.0000.054.0%0.0%
Direct LabourDL Stage 01572,471.61,984.980% of contract486.7——————91.2%0.0%
DL Stage 02431,357.21,059.578% of contract297.8——————67.5%0.0%
DL Stage 0327949.4642.968% of contract306.4——————63.0%0.0%
DL Stage 04432,349.7976.642% of contract1,373.1——————23.3%0.0%
Direct Labour Total1707,127.94,663.965% of contract2,464.0000.0000.063.6%0.0%
—All Provinces57923,829.38,742.837% of contract15,086.4000.0000.056.8%0.0%
Tender Above 50Mn106 projectsTender8,082.6Mn
19% paid1,572.9 Mn
Pending6,509.7Mn
Planned Fin51.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn300 projectsTender6,498.8Mn
39% paid2,506.0 Mn
Pending3,992.8Mn
Planned Fin55.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU3 projectsTender2,119.9Mn
0% paid0.0 Mn
Pending2,119.9Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 0157 projectsDirect Labour2,471.6Mn
80% paid1,984.9 Mn
Pending486.7Mn
Planned Fin91.2%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 0243 projectsDirect Labour1,357.2Mn
78% paid1,059.5 Mn
Pending297.8Mn
Planned Fin67.5%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 0327 projectsDirect Labour949.4Mn
68% paid642.9 Mn
Pending306.4Mn
Planned Fin63.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 0443 projectsDirect Labour2,349.7Mn
42% paid976.6 Mn
Pending1,373.1Mn
Planned Fin23.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
All Provinces579 projects23,829.3Mn
37% paid8,742.8 Mn
Pending15,086.4Mn
Planned Fin56.8%
Actual Fin0.0%

Avg Physical Progress per Province

Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

11–20/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
11RR/RDA/04/25/25/CP/KY
Delgasthenna Road
NAGMA ENGINEERING (PVT) LTD
56,035,922.24————————————
12RR/RDA/04/25/27/CP/KY
Dadahogama pitiye gedara pathibami sahitha Margaya
Nimsara Construction & Holdings (PVT) Lt…
12,532,355.00————————————
13RR/RDA/04/25/28/CP/KY
Dehideniya sita Hedeniya dakwa Margaya
Senerath Engineering (pvt) Ltd
38,495,776.00————————————
14RR/RDA/04/25/31/CP/KY
Shantha Janapada Village middle road
Ajith Construction
42,357,645.00————————————
15RR/RDA/04/25/31(1)/CP/KY
Paththunupitiya School road to Gampola Road through Pallegama Anguruwala
Central Engineering Services Pvt Ltd. (C…
50,476,865.28————————————
16RR/RDA/04/25/32/CP/KY
Pilawala Navodya pasala asala sita Nelumpathhinna pansala dakwa margaya
Senerath Engineering (pvt) Ltd
18,059,531.27————————————
17RR/RDA/04/25/33/CP/KY
New forest kotase Jana Udana gammana margaya
The Wise Lanka Construction Company (Pvt…
6,992,144.50————————————
18RR/RDA/04/25/34/CP/KY
Liyandeniya wewa margya
Nimsara Construction & Holdings (PVT) Lt…
9,134,433.00————————————
19RR/RDA/04/25/35/CP/KY
Gamunupura Gonawatta pradana margaye Gamunupura pera pasala asala sita idiriyata…
Senerath Engineering (pvt) Ltd
30,043,716.01————————————
20RR/RDA/04/25/41/CP/KY
Karyala handiya pahala margya concrete kirima
UGD Constructions
22,047,564.00————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 11–20 of 579 projects · page 2/58