DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 59 awarded projects

2026-11-05
13:46:46Live2026-11-05
0 / 59Advance Pendingpending advance projects / total projects
0 / 59IPC Pendingpending IPC projects / total projects
0 / 59Advance Paidadvance paid projects / total projects
0 / 59IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

0%

0%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

62.6%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · North Western Province · Province

579Projects23,829.3Contract Mn
North Western Province 59 projects Open filtered view
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn13690.693.113% of contract597.5——————84.6%0.0%
Tender Below 50Mn24529.0229.043% of contract300.0——————100.0%0.0%
PIU00.0——————————
Tender Total371,219.6322.126% of contract897.5000.0000.094.6%0.0%
Direct LabourDL Stage 016445.0385.387% of contract59.7——————83.3%0.0%
DL Stage 027264.3212.580% of contract51.7——————42.9%0.0%
DL Stage 03125.217.971% of contract7.4——————0.0%0.0%
DL Stage 048247.8169.268% of contract78.6——————0.0%0.0%
Direct Labour Total22982.3784.980% of contract197.4000.0000.036.4%0.0%
—North Western Province592,201.91,107.050% of contract1,094.9000.0000.072.9%0.0%
Tender Above 50Mn13 projectsTender690.6Mn
13% paid93.1 Mn
Pending597.5Mn
Planned Fin84.6%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn24 projectsTender529.0Mn
43% paid229.0 Mn
Pending300.0Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projectsTender0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 016 projectsDirect Labour445.0Mn
87% paid385.3 Mn
Pending59.7Mn
Planned Fin83.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 027 projectsDirect Labour264.3Mn
80% paid212.5 Mn
Pending51.7Mn
Planned Fin42.9%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 projectDirect Labour25.2Mn
71% paid17.9 Mn
Pending7.4Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 048 projectsDirect Labour247.8Mn
68% paid169.2 Mn
Pending78.6Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
North Western Province59 projects2,201.9Mn
50% paid1,107.0 Mn
Pending1,094.9Mn
Planned Fin72.9%
Actual Fin0.0%

Avg Physical Progress per Province · North Western Province

Graphs reflect current view:59 awarded · North Western Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

151–160/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
151—
Development of the road from the main road to near the Kadawala Wewa School
Nadun Construction (Pvt) Ltd
93,990,000.00————————————
152—
Development of the road from near the house at Pulastigama 156 to Sungawila 1 Ca…
Nadun Construction (Pvt) Ltd
67,120,000.00————————————
153—
Road from near the Wota Gedi Bridge to Dambalu Stores
Nathan's Construction
69,810,000.00————————————
154RR/RDA/18/25/01/NWP/KRG
Development of Egodagama Talakolawewa road
Sri Ram Constructions
98,323,766.14————————————
155RR/RDA/18/25/02/NWP/KRG
Road from Parakumpura to Yaya 04
Ingress Engineering
20,126,522.24————————————
156RR/RDA/18/25/04/NWP/KRG
The road from Hunugallewa road junction to Madadenigama Hunugallewa Mahamaruwa B…
Shanho Enterprises Pvt Ltd.
59,066,766.74————————————
157RR/RDA/18/25/07/NWP/KRG
Road from Moragolla Junction to Nabadewa Girilla Carpet Road via Kirinda
Jayasinghe Constructions (Pvt) Ltd.
59,247,280.29————————————
158RR/RDA/18/25/08/NWP/KRG
Paving of road from Nammuawa to Nagansole temple
Omega Construction (Pvt) Ltd
33,899,382.00————————————
159RR/RDA/18/25/09/NWP/KRG
Paving the road from Pahala Galapitiyagama to Tharanagolla Sports Ground
Senerath Engineering (pvt) Ltd
70,405,428.60————————————
160RR/RDA/18/25/11/NWP/KRG
Development of road from Dambulu Road to Havanathenna via Ehelagollaya
Shanho Enterprises Pvt Ltd.
46,193,949.68————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 151–160 of 579 projects · page 16/58