Financial Dashboard

Monitor financial performance across 31 awarded projects

2026-11-04
23:32:54Live2026-11-04
0 / 31Advance Pendingpending advance projects / total projects
0 / 31IPC Pendingpending IPC projects / total projects
0 / 31Advance Paidadvance paid projects / total projects
0 / 31IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · EE: Trincomalee · EE Office

567Projects20,718.2Contract Mn
Trincomalee 31 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn4304.746.715% of contract258.0——————95.2%0.0%
Tender Below 50Mn24521.5195.738% of contract325.8——————0.0%0.0%
DL Stage 01132.230.194% of contract2.1——————100.0%0.0%
DL Stage 02115.415.6101% of contract-0.2——————100.0%0.0%
DL Stage 0300.0——————————
DL Stage 04143.228.967% of contract14.3——————100.0%0.0%
Trincomalee31917.1317.035% of contract600.0000.0000.022.0%0.0%
Tender Above 50Mn4 projects304.7Mn
15% paid46.7 Mn
Pending258.0Mn
Planned Fin95.2%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn24 projects521.5Mn
38% paid195.7 Mn
Pending325.8Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project32.2Mn
94% paid30.1 Mn
Pending2.1Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project15.4Mn
101% paid15.6 Mn
Pending—
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 030 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 041 project43.2Mn
67% paid28.9 Mn
Pending14.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Trincomalee31 projects917.1Mn
35% paid317.0 Mn
Pending600.0Mn
Planned Fin22.0%
Actual Fin0.0%

Avg Physical Progress per Province · EE: Trincomalee

Project-wise Financials · EE: Trincomalee (291 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · EE: Trincomalee (Mn · incl. VAT)

Scroll horizontally — 291 projects

Trincomalee Division · EE: Trincomalee (Mn · incl. VAT)

Trincomalee District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:31 awarded · EE: Trincomalee
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 291 projects (filtered from 579)

231–240/291 (filtered from 579)
ActiveProgress 100–100%
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
231RR/RDA/10/25/23
Oorany Kudiyetta thidda Veethy
—
12,148,965.86————————————
232RR/RDA/25/24/07
Godawela Wela Middle Road (Const. side walls)
—
21,801,991.89————————————
233RR/RDA/25/24/15
D03 Road Near the Yaka Poll
—
52,683,572.48————————————
234RR/RDA/25/24/08
From Mr.Ranjth's House to Mr.Premasiri's House in Maduwanwela Janapadaya 2nd Lan…
—
39,030,233.29————————————
235RR/RDA/25/25/16
Ma dola Jansalu Mawatha Rathnapuara Colombo Road to Welangalla Maha ela Bridge
—
40,604,043.84————————————
236RR/RDA/25/25/17
Na gahamula Junction to 28 Janapadaya Road
—
30,370,502.56————————————
237RR/RDA/25/24/12
Siyabalagahayata Junction to Blue Mountain Housing Complex Road
—
23,571,917.19————————————
238RR/RDA/25/24/09
From Koralegama to Labuwalwaththa Road (From Mr.Pushpananda House)
—
33,251,409.79————————————
239RR/RDA/25/25/18
Concreting Beragala Army Camp to Beragala 3way Junction VIA Niyadagala
—
34,687,905.11————————————
240RR/RDA/25/25/21
Kalupahanawaththa Road
—
28,324,647.09————————————
Total8,230,991,569.86——————————
—Mn
0%
—Mn
0%
Showing 231–240 of 291 projects · page 24/30