DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 5 awarded projects

2026-11-05
02:20:49Live2026-11-05
0.0 Mn

— Mn

Advance Pend (incl. VAT)

Portfolio Breakdown — Financial (Exclusive Vat) · Matale EE · Central Province · Consultant

44Projects11,748.0Contract Mn
Reset
Matale EE 5 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency51,281.7272.221% of contract17.244177.75252.976.6%18.0%
DC - Roads00.0——————————
DC - Slope00.0——————————
PD(CP) - Slope00.0——————————
Matale EE51,281.7272.221% of contract17.244177.75252.976.6%18.0%
Emergency5 projects1,281.7Mn
21% paid272.2 Mn
Pending17.2Mn
Planned Fin76.6%
Actual Fin18.0%
Advance & IPC
Advance paid4 proj · 177.7 Mn
IPC paid2 proj · 52.9 Mn
Open filtered view
DC - Roads0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Matale EE5 projects1,281.7Mn
21% paid272.2 Mn
Pending17.2Mn
Planned Fin76.6%
Actual Fin18.0%

Avg Physical Progress per Province · Matale EE · Central Province

Project-wise Financials · Matale EE · Central Province (171 Projects)

Clear

Project-wise Contract Value vs. Expenditure and Pending Payments · Matale EE · Central Province (Mn · incl. VAT)

Scroll horizontally — 171 projects

Matale EE Division · Matale EE · Central Province (Mn · incl. VAT)

Matale District Summary (Mn · incl. VAT)

District baseline — overall all categories (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:5 awarded · Matale EE · Central Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 171 projects

151–160/171

Filter financial register

171 matching projects

S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
151RDA/DRP/UVA/BAD/BAN/23
Rehabilitation / Improvement of Colombo Rathnapura Wellawaya Batticaloa Road (AA…
D K S Construction
322,192,938.6958,090,759.3168,547,095.98——————58,090,759.31—
68.55Mn
21.3%
Watch
68.55Mn
21.3%
152RDA/DRP/SP/GAL/GAL/02
Rehabilitation of Gabbion Walls along Galle - Deniyaya - Madampe Road (from7+700…
Ceylon Construction Industry Development…
8,991,852.34————————————
153RDA/DRP/SP/GAL/HIN/03
Rehabilitation / Improvement of Gabbion Walls along Udugama - Hiniduma (9+920-…
Ceylon Construction Industry Development…
19,453,314.54————————————
154RDA/DRP/UVA/BAD/BAN/31
Rehabilitation / Improvement of Colombo Rathnapura Wellawaya Batticaloa Road (AA…
Nimna Holdings (Pvt) Ltd
239,935,072.90————————————
155RDA/DRP/NOR/MUL/KIL/07
Rehabilitation / Improvement of Sholder of 1. Kandy - Jaffna Road (251+000 - 252…
SSK Construction
62,162,612.70————————————
156RDA/DRP/NOR/VOU/MAN/08
Rehabilitation / Improvement of 85/3 Bridge Approach Reconstruction with Gabion …
Asset Engineering (Pvt) Ltd
98,477,554.94————————————
157RDA/DRP/NOR/MUL/MUL/09
Rehabilitation /Improvement & Rectification of flood damages in Mullaitivu ( Man…
Jana Civil Work Contractors & Material S…
37,338,982.74————————————
158RDA/DRP/NOR/VOU/VOU/15
Rehabilitation /Improvement of Kandy-Jaffna Road (AA009) & Madawachchiya-Mannar-…
Jana Civil Work Contractors & Material S…
42,832,926.51————————————
159RDA/DRP/NOR/JAF/POI/10
REHABILITATION/IMPROVEMENT OF FLOOD DAMAGES IN CHAVAKACHCHERI-PULOLY ROAD (B075…
S S K Construction
159,578,757.33————————————
160RDA/DRP/NOR/JAF/JAF/06
REHABILITATION / IMPROVEMENT OF FLOOD DAMAGES IN KARAINAGAR CIRCULAR ROAD (B 197…
Nimna Holdings (Pvt) Ltd
200,137,805.22————————————
Total34,005,299,486.172,787,819,645.293,289,427,166.63113,218,826.01133,598,214.691,049,943,508.601,238,847,524.5163,842,351.1873,647,937.023,837,763,153.89177,061,177.19
4,528.27Mn
13.3%
4,735.52Mn
13.9%
Showing 151–160 of 171 projects · page 16/18