DRRRP Awarded Emergency

RDA/DRP/NOR/MUL/KIL/07

Rehabilitation / Improvement of Sholder of 1. Kandy - Jaffna Road (251+000 - 252+200), 2.0Kandy - Jaffna Road (260+000 - 270+000), 3.Nawatkuly - Kerativu - Mannar Road(54+000 - 57+000), 4.Paranthan - Karachchi - Mullaitivu (0+000 - 1+000, 6+000- 8+000, 9+000-11+000, 12+500-14+500, 16+000-17+500, 19+400-19+800) 5.Paranthan - Ponakary Road (9+000-16+000) 6.Soranpattu - Thalaiyadi road (2+500-5+000)

KilinochchiNorthern Province-Divisional SecretariatSSK ConstructionContractorLKR 62,162,612.70Contract Sum91 daysProject Duration
7%
Complete
Physical Progress7%
Planned Progress68.2%
Time Elapsed63.7%
On Track • 33 days left

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2026-09-07
Completed
Scheduled Completion
2026-12-07
On Track
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorthern Province
DistrictKilinochchi
PD RegionNorthern Province
CE RegionMullaitivu
EE Division-
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Sholder of 1. Kandy - Jaffna Road (251+000 - 252+200), 2.0Kandy - Jaffna Road (260+000 - 270+000), 3.Nawatkuly - Kerativu - Mannar Road(54+000 - 57+000), 4.Paranthan - Karachchi - Mullaitivu (0+000 - 1+000, 6+000- 8+000, 9+000-11+000, 12+500-14+500, 16+000-17+500, 19+400-19+800) 5.Paranthan - Ponakary Road (9+000-16+000) 6.Soranpattu - Thalaiyadi road (2+500-5+000)
Estimated Road Lengths- km
Number of Roads-
Scope Summary-
Contractor & Award
Contract No.RDA/DRP/NOR/MUL/KIL/07
Tender Batch No.13
Contractor NameSSK Construction
Consultant-
Tender StatusAwarded
LOA Date—
Contract Amount62,162,612.70
Engineer Estimate Amount (LKR)55,617,040.01
Duration (Days)91
CategoryEmergency