Financial Dashboard
Monitor financial performance across 0 awarded projects
— Mn
Total Contract
— Mn
Advance Paid (excl. VAT)
— Mn
IPCs Paid (excl. VAT)
— Mn
Total Paid (excl. VAT)
— Mn
Total Paid (incl. VAT)
— Mn
Advance Pend (incl. VAT)
— Mn
IPCs Pend (incl. VAT)
— Mn
Total (Paid+Pend) (incl. VAT)
Paid incl + Adv Pend incl + IPC Pend incl
0%
Financial Progress (excl. VAT)
Total (Paid+Pend) excl / Contract
0%
Planned Financial Progress
Planned share of contract value
Portfolio Breakdown — Financial (Exclusive Vat) · Emergency · Western Province · EE: Jaffna · EE Office
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 359.7 | — | — | — | — | — | — | — | — | 2.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| All Provinces | 2 | 359.7 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 2.2% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 359.7 | — | — | — | — | — | — | — | — | 2.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Northern Province | 2 | 359.7 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 2.2% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 359.7 | — | — | — | — | — | — | — | — | 2.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| All Districts | 2 | 359.7 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 2.2% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 359.7 | — | — | — | — | — | — | — | — | 2.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Jaffna | 2 | 359.7 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 2.2% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 129 | 22,610.7 | 4,184.219% of contract | 207.2 | 81 | 78 | 2,556.7 | 122 | 60 | 989.5 | 85.7% | 15.7% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| All EE Offices | 129 | 22,610.7 | 4,184.219% of contract | 207.2 | 81 | 78 | 2,556.7 | 122 | 60 | 989.5 | 85.7% | 15.7% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 22 | 4,976.9 | 892.818% of contract | — | 14 | 14 | 521.2 | 30 | 11 | 235.4 | 95.7% | 15.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Ratnapura | 22 | 4,976.9 | 892.818% of contract | 0.0 | 14 | 14 | 521.2 | 30 | 11 | 235.4 | 95.7% | 15.2% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 19 | 4,275.2 | 951.322% of contract | — | 15 | 15 | 615.2 | 19 | 13 | 190.9 | 92.4% | 18.9% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Badulla | 19 | 4,275.2 | 951.322% of contract | 0.0 | 15 | 15 | 615.2 | 19 | 13 | 190.9 | 92.4% | 18.9% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 10 | 2,440.9 | 548.422% of contract | — | 8 | 8 | 333.2 | 18 | 8 | 131.7 | 84.5% | 19.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kegalle | 10 | 2,440.9 | 548.422% of contract | 0.0 | 8 | 8 | 333.2 | 18 | 8 | 131.7 | 84.5% | 19.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,447.4 | 253.117% of contract | — | 6 | 6 | 214.5 | — | — | — | 100.0% | 14.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Gampaha | 8 | 1,447.4 | 253.117% of contract | 0.0 | 6 | 6 | 214.5 | 0 | 0 | 0.0 | 100.0% | 14.8% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,433.0 | 196.214% of contract | — | 5 | 5 | 110.1 | 10 | 6 | 56.1 | 100.0% | 11.6% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Colombo | 8 | 1,433.0 | 196.214% of contract | 0.0 | 5 | 5 | 110.1 | 10 | 6 | 56.1 | 100.0% | 11.6% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,345.4 | 272.220% of contract | 17.2 | 4 | 4 | 177.7 | 5 | 2 | 52.9 | 76.2% | 17.1% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Matale | 6 | 1,345.4 | 272.220% of contract | 17.2 | 4 | 4 | 177.7 | 5 | 2 | 52.9 | 76.2% | 17.1% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,251.4 | 304.624% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 84.3% | 20.6% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nuwara Eliya | 6 | 1,251.4 | 304.624% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 84.3% | 20.6% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,105.1 | 271.425% of contract | 33.9 | 5 | 5 | 151.1 | 9 | 4 | 79.0 | 73.7% | 20.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kundasale | 8 | 1,105.1 | 271.425% of contract | 33.9 | 5 | 5 | 151.1 | 9 | 4 | 79.0 | 73.7% | 20.8% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Chilaw | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 5 | 768.2 | 64.88% of contract | 38.9 | 3 | 2 | 43.6 | 3 | 1 | 11.4 | 72.5% | 7.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kurunegala | 5 | 768.2 | 64.88% of contract | 38.9 | 3 | 2 | 43.6 | 3 | 1 | 11.4 | 72.5% | 7.2% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 610.8 | 93.515% of contract | — | 3 | 3 | 73.1 | 1 | 1 | 6.2 | 96.7% | 13.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Anuradhapura | 6 | 610.8 | 93.515% of contract | 0.0 | 3 | 3 | 73.1 | 1 | 1 | 6.2 | 96.7% | 13.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 369.1 | 34.09% of contract | — | 2 | 2 | 28.9 | — | — | — | 96.0% | 7.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Norwood | 3 | 369.1 | 34.09% of contract | 0.0 | 2 | 2 | 28.9 | 0 | 0 | 0.0 | 96.0% | 7.8% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 359.7 | — | — | — | — | — | — | — | — | 2.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Jaffna | 2 | 359.7 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 2.2% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 5 | 235.4 | 64.727% of contract | — | 3 | 3 | 28.1 | 3 | 3 | 26.7 | 100.0% | 23.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Polonnaruwa | 5 | 235.4 | 64.727% of contract | 0.0 | 3 | 3 | 28.1 | 3 | 3 | 26.7 | 100.0% | 23.3% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 221.8 | — | — | — | — | — | — | — | — | 19.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kandy | 3 | 221.8 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 19.2% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 193.4 | 58.230% of contract | — | 1 | 1 | 33.3 | 4 | 1 | 16.0 | 100.0% | 25.5% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kadugannawa | 1 | 193.4 | 58.230% of contract | 0.0 | 1 | 1 | 33.3 | 4 | 1 | 16.0 | 100.0% | 25.5% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 160.3 | 59.237% of contract | — | 2 | 2 | 28.0 | 4 | 2 | 22.1 | 100.0% | 31.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Monaragala | 2 | 160.3 | 59.237% of contract | 0.0 | 2 | 2 | 28.0 | 4 | 2 | 22.1 | 100.0% | 31.3% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 112.6 | 20.218% of contract | 2.9 | 2 | 2 | 10.0 | 3 | 2 | 7.1 | 69.5% | 15.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nalanda | 3 | 112.6 | 20.218% of contract | 2.9 | 2 | 2 | 10.0 | 3 | 2 | 7.1 | 69.5% | 15.2% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 49.2 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Trincomalee | 1 | 49.2 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 0.0% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 47.8 | 9.219% of contract | — | 1 | 1 | 7.8 | — | — | — | 100.0% | 16.4% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Hanguranketha | 1 | 47.8 | 9.219% of contract | 0.0 | 1 | 1 | 7.8 | 0 | 0 | 0.0 | 100.0% | 16.4% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 42.8 | — | — | — | — | — | — | — | — | 62.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Vavuniya | 1 | 42.8 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 62.5% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 37.3 | — | — | — | — | — | — | — | — | 81.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Mullaitivu | 1 | 37.3 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 81.5% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 28.4 | — | — | — | — | — | — | — | — | 100.0% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Galle | 2 | 28.4 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 100.0% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
Avg Physical Progress per Province · Emergency · Western Province · EE: Jaffna
No province data available
Awarded projects will appear here
Financial Progress per Province (Mn) Excluding VAT · Emergency · Western Province · EE: Jaffna
No province financial data available
Awarded projects will appear here
Avg Physical Progress per EE Division · Emergency · Western Province · EE: Jaffna
No data available
Awarded projects will appear here
Financial Progress per EE Division (Mn) Excluding VAT · Emergency · Western Province · EE: Jaffna
No financial data available
Awarded projects will appear here
District-wise Physical Progress · Emergency · Western Province · EE: Jaffna
No district data available
Awarded projects will appear here
District-wise Financial Progress (Mn) Excluding VAT · Emergency · Western Province · EE: Jaffna
No financial data available
Awarded projects will appear here
Consultant-wise Physical Progress · Emergency · Western Province · EE: Jaffna
No consultant data available
Awarded projects will appear here
Consultant-wise Financial Progress (Mn) Excluding VAT · Emergency · Western Province · EE: Jaffna
No financial data available
Awarded projects will appear here
Project-wise Physical Progress: Actual vs Planned (%) · Emergency · Western Province · EE: Jaffna (0)
No data available
Awarded projects will appear here
Project-wise Financial Progress: Actual vs Planned (Mn) Excluding VAT · Emergency · Western Province · EE: Jaffna (0)
No financial data available
Awarded projects will appear here
Project-wise Financials · Emergency · Western Province · EE: Jaffna (171 Projects)
Project-wise Contract Value vs. Expenditure and Pending Payments · Emergency · Western Province · EE: Jaffna (Mn · incl. VAT)
Scroll horizontally — 171 projects
Jaffna Division · Emergency · Western Province · EE: Jaffna (Mn · incl. VAT)
District District Summary (Mn · incl. VAT)
District baseline — overall Emergency (consultant filter excluded for comparison) · amounts incl. VAT
Financial Summary
Advance payments, IPCs & expenditure per awarded project · 171 projects
Filter financial register
171 matching projects
| S/N | Contract No | Contract Name | Contractor | Contract (LKR) | Advance Paid (excl. VAT) | Advance Paid (incl. VAT) | Advance Pend (excl. VAT) | Advance Pend (incl. VAT) | IPCs Paid (excl. VAT) | IPCs Paid (incl. VAT) | IPCs Pend (excl. VAT) | IPCs Pend (incl. VAT) | Overall Expenditure (excl. VAT) | Pending Payments (excl. VAT) | Financial Progress | Financial Progress with Outstanding |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | RDA/DRP/CEN/KDY/KAD/11 | Rehabilitation / Improvement of Nawalapitiya - Dolosbage Road ( B -318) ( 10+50… | Tiasa Construction (Pvt) Ltd | 193,404,194.96 | 33,346,525.54 | 39,348,900.14 | — | — | 15,954,390.29 | 18,826,180.55 | — | — | 49,300,915.83 | — | 58.18Mn Watch30.1% | 58.18Mn 30.1% |
| 2 | RDA/DRP/CEN/KDY/KAN/14 | Rehabilitation /Improvement of Katugasthota Medawala road ( B 0206)( 0 + 000 - … | Alucon Industries (Pvt) Ltd | 74,836,014.77 | — | — | — | — | — | — | — | — | — | — | — | — |
| 3 | RDA/DRP/CEN/KDY/KDY/15 | Rehabilitation / Improvement of Galagedara Rambukkana ( B 122) ( 0+000 - 18+000) | Jayawansa Construction (Pvt) Ltd | 79,071,437.68 | — | — | — | — | — | — | — | — | — | — | — | — |
| 4 | RDA/DRP/CEN/KDY/KDY/19 | Rehabilitation / Improvement of Poojapitiya Alawathugoda road ( B 377) ( 0+000 -… | Jayawansa Construction (Pvt) Ltd | 67,935,586.77 | — | — | — | — | — | — | — | — | — | — | — | — |
| 5 | RDA/DRP/CEN/KDY/KUN/20 | Rehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuw… | Samindra Construction | 31,558,227.98 | — | — | — | — | — | — | — | — | — | — | — | — |
| 6 | RDA/DRP/CEN/KDY/KUN/21 | Improvement of Pitiyegedara-Waththegama-Iriyagasthenna Road (0+000-5+400) | Jayasinghe Construction (Pvt) Ltd | 257,721,453.96 | 46,231,491.42 | 54,553,159.88 | — | — | — | — | 8,483,606.80 | 10,010,656.02 | 46,231,491.42 | 8,483,606.80 | 54.55Mn Watch21.2% | 64.56Mn 25.1% |
| 7 | RDA/DRP/CEN/KDY/KUN/22 | Improvement to Damaged Road Section on Weeragantota - Randenigala Road. (From CH… | SD Civil Construction (Pvt) Ltd | 224,968,435.78 | 40,192,882.63 | 47,427,601.50 | — | — | 34,738,972.19 | 40,991,987.18 | — | — | 74,931,854.82 | — | 88.42Mn Watch39.3% | 88.42Mn 39.3% |
| 8 | RDA/DRP/CEN/KDY/KUN/24R | Rehabilitation / Improvement of Flood damage on Katugastota - Madawala - Bambere… | Nimsara Construction & Engineering (Pvt)… | 79,507,501.11 | — | — | — | — | — | — | — | — | — | — | — | — |
| 9 | RDA/DRP/CEN/KDY/KUN/25 | Construction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LH… | S N O Builders (Pvt) Ltd | 157,909,825.01 | 28,346,587.80 | 33,448,973.60 | — | — | 25,922,264.54 | 30,502,481.38 | 10,705,591.47 | 11,041,226.83 | 54,268,852.34 | 10,705,591.47 | 63.95Mn On Track40.5% | 74.99Mn 47.5% |
| 10 | RDA/DRP/CEN/KDY/KUN/26R | Improvement to Structures on Kandy - Jaffna Road 11+700 - 11+850 | SD Civil Construction (Pvt) Ltd | 148,430,322.65 | — | — | — | — | — | — | — | — | — | — | — | — |
| Total | 34,005,299,486.17 | 2,738,852,403.05 | 3,231,645,820.60 | 113,218,826.01 | 133,598,214.69 | 1,049,943,508.60 | 1,238,847,524.51 | 63,842,351.18 | 73,647,937.02 | 3,788,795,911.65 | 177,061,177.19 | 4,470.49Mn 13.1% | 4,677.74Mn 13.8% | |||