Project Monitoring Dashboard

Comprehensive overview of 6 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:6 awarded · EE: Nuwara Eliya

Portfolio Breakdown · EE: Nuwara Eliya · EE Office

567Awarded667Total
Nuwara Eliya 6 awarded of 6 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn110100%64.851.851.83.26% of contract100.0%35.0%
Tender Below 50Mn110100%43.138.838.84.512% of contract100.0%5.0%
DL Stage 01110100%65.365.365.376.6117% of contract100.0%100.0%
DL Stage 02110100%40.740.740.745.3111% of contract100.0%100.0%
DL Stage 03220100%18.918.918.914.476% of contract100.0%100.0%
DL Stage 040000%0.00.0————
Not Specified0000%0.00.0————
Nuwara Eliya660100%232.8215.5215.5144.167% of contract100.0%73.3%

Avg Physical Progress per EE Division · EE: Nuwara Eliya

Portfolio Timeline· 6 scheduled projects · EE: Nuwara Eliya Toggle
Portfolio · Awarded Works

Awarded Projects

2 projects

2/2 (filtered)

Filter awarded works

2 matching projects1 active

ActiveCritical Delay
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/06/25/32/CP/NERR/RDA/06/25/32
Nanuoya Glaso pahala kotasa Margaya
5%
38,841,280.5043,085,721.61Awarded
2RR/RDA/06/25/41/CP/NERR/RDA/06/25/41
Nayapana Gammada tharapara sanwardhanaya
35%
51,754,603.5264,794,731.20Awarded
Showing 1–2 of 2
Per page:
Source: DRRRP • 6 projects • Data updated 2026-11-02 10:30 • 13:38:30