DRRRP · Sri Lanka
Project Monitoring Dashboard
Comprehensive overview of 3 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka.
Updated 2026-11-02 10:30Live
Graphs reflect current view:3 awarded · Gampaha · EE: Nittambuwa
60% awarded
0
Awarded
5 total projects 5 roads in portfolio
Awarded projects3
RR/RDA/02/25/08Carpeting of the road from near the Buddha Temple towards the Lindara Temple on the Neligama Guru Godella Road started from Halugama Dharmapala Colledge in the Lindara Grama Niladhari Division of the Mirigama Divisional Secretariat.RR/RDA/02/25/01Heendeniya Dumriya Sthanaya Dakwa Margaya
+1 more…
Click to filter the awarded table
73.6M
73.6 Mn
Contract Value
Awarded projects3
RR/RDA/02/25/08Carpeting of the road from near the Buddha Temple towards the Lindara Temple on the Neligama Guru Godella Road started from Halugama Dharmapala Colledge in the Lindara Grama Niladhari Division of the Mirigama Divisional Secretariat.RR/RDA/02/25/01Heendeniya Dumriya Sthanaya Dakwa Margaya
+1 more…
Click to filter the awarded table
Avg
60%
1
works in progress
1 completed
Avg Progress
Awarded projects3
RR/RDA/02/25/08Carpeting of the road from near the Buddha Temple towards the Lindara Temple on the Neligama Guru Godella Road started from Halugama Dharmapala Colledge in the Lindara Grama Niladhari Division of the Mirigama Divisional Secretariat.RR/RDA/02/25/01Heendeniya Dumriya Sthanaya Dakwa Margaya
+1 more…
Click to filter the awarded table
11.7M
11.7 Mn
Total Expenditure (incl. VAT)
Awarded projects3
RR/RDA/02/25/08Carpeting of the road from near the Buddha Temple towards the Lindara Temple on the Neligama Guru Godella Road started from Halugama Dharmapala Colledge in the Lindara Grama Niladhari Division of the Mirigama Divisional Secretariat.RR/RDA/02/25/01Heendeniya Dumriya Sthanaya Dakwa Margaya
+1 more…
Click to filter the awarded table
66.7%
0
On Progress
2 / 3 awarded
On Progress (incl. completed)2
RR/RDA/02/25/08Carpeting of the road from near the Buddha Temple towards the Lindara Temple on the Neligama Guru Godella Road started from Halugama Dharmapala Colledge in the Lindara Grama Niladhari Division of the Mirigama Divisional Secretariat.RR/RDA/02/25/01Heendeniya Dumriya Sthanaya Dakwa Margaya
Click to filter the awarded table
0%
0
Delay
0 / 3 awarded
Delay0
No projects
Click to filter the awarded table
0%
0
Critical Delay
0 / 3 awarded
Critical Delay0
No projects
Click to filter the awarded table
33.3%
0
Completed
1 / 3 awarded
Completed1
Click to filter the awarded table
Portfolio Breakdown · Gampaha · EE: Nittambuwa · EE Office
Avg Physical Progress per EE Division · Gampaha · EE: Nittambuwa
At-Risk Projects · Gampaha · EE: Nittambuwa
- RR/RDA/02/25/08Carpeting of the road from near the Buddha Temple towards the Lindara Temple on the Neligama Guru Godella Road started from Halugama Dharmapala Colledge in the Lindara Grama Niladhari Division of the Mirigama Divisional Secretariat.Delay152 Days in Delay · 20%
- Road from Pinnawatta Junction to Mr. Sandaruwan's shop on the Hapitiya entrance roadDelay106 Days in Delay · 0%
Portfolio Timeline· 3 scheduled projects · Gampaha · EE: Nittambuwa Toggle
2025-06-21 today2026-11-04
Portfolio · Awarded Works
Awarded Projects
1 projects
Filter awarded works
1 matching project1 active
| # | Contract No. | Package No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|---|---|
| 1 | RR/RDA/02/25/01 | — | Heendeniya Dumriya Sthanaya Dakwa Margaya | 100% | 13,144,147.11 | 13,144,147.11 | Awarded |
Showing 1–1 of 1
Source: DRRRP • 5 projects • Data updated 2026-11-02 10:30 • 16:27:18 System live • Sri Lanka • 1 districts